Why Builders Should Reconsider Arbitration Clauses in Construction Contracts
October 21, 2019 —
David M. McLain – Colorado Construction LitigationMy advice to home builders has long been to arbitrate construction defect claims instead of litigating them in front of juries. Based on my experience and watching others litigate claims, I have learned that home builders usually fare better in arbitration than in jury trials, both in terms of what they have to pay the homeowners or HOAs and also in what they recover from subcontractors and design professionals. Because of these dynamics, conventional wisdom has been that builders should arbitrate construction defect claims. For several reasons, I am now questioning whether the time is right to consider a third option.
First, plaintiffs’ attorneys dislike arbitration and will continue their attempts to do away with arbitration for construction defect claims. In 2018, the Colorado Legislature considered HB 18-1261 and HB 18-1262. While both bills were ultimately killed, they showed the plaintiffs’ attorneys disdain for arbitration, and serve as a warning that attempts to prevent arbitration legislatively will continue. If the legislature does away with the ability to arbitrate construction defect claims, and that is the only means of dispute resolution contained in a builder’s contracts, that builder may find itself in front of a jury.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
North Carolina Weakened Its Building Codes in 2013
October 09, 2018 —
Ari Natter - BloombergFive years ago, encouraged by home builders and an anti-regulatory zeal, lawmakers in North Carolina joined other states in weakening building code requirements.
It’s a decision they may regret as Hurricane Florence takes aim at the Carolinas.
The Legislature in 2013 increased the amount of time between updates to its building code from three years to six. That means that updates that set new standards for elevating the floors in flood-prone homes aren’t in effect, according to the Federal Alliance for Safe Homes Inc., a non-profit disaster safety organization.
Read the court decisionRead the full story...Reprinted courtesy of
Ari Natter, Bloomberg
Never, Ever, Ever Assume! (Or, How a Stuck Shoe is Like a Construction Project Assumption)
October 21, 2019 —
Melissa Dewey Brumback - Construction Law in North CarolinaThis summer, I had the fortune of taking a trip to Europe. The first place I visited was Amsterdam. A lovely town with a lot of culture and more canals than you can shake a stick at. I was meeting family there, but had hours to kill ahead of time. So, I decided to take the train from the airport into the City Centre, leave my bags at the train station luggage locker, and begin exploring.
My plan took its first misstep when I attempted to board the train. Not being in a hurry, I let the other passengers get on first. Sure, I noticed the train conductor blowing his whistle while I stepped onto the train, but figured I was fine since I was already on the steps up. Until, that is, the door began to close, with me in the doorway, suitcase in the train, one foot inside, and one foot mid step up to the cabin. The door closed on my backpack (which was still on my back), but I managed to force it into the train compartment. My shoe, however, was not quite as lucky. Part of my shoe made it inside, and part was outside the door.
No worry– just look for the door release mechanism, right? Wrong! There was none. The train started up, with my shoe still halfway in and halfway out of the train. (Luckily my foot itself made it inside all in one piece). The conductor came along to scold me, and told me that he could *probably* rescue my shoe once we got to Central Station. In the meantime, I sat on a nearby jump seat, keeping tabs on my shoe and fuming that this was *not* the way I planned to start my vacation. Long story short– the train conductor was able to salvage my shoe, but not without a lot of commentary on how I should never have boarded the train after the whistle blew. Lesson learned.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale Liggett PLLCMs. Brumback may be contacted at
mbrumback@rl-law.com
Court Throws Wet Blanket On Prime Contractor's Attorneys' Fees Request In Prompt Payment Case
September 03, 2015 —
Steven M. Cvitanovic & Abigail E. Lighthart – Haight Brown & Bonesteel LLPPrompt payment penalty cases do not come around very often, but when they do, there is bound to be fireworks.
In James L. Harris Painting & Decorating, Inc. v. West Bay Builders, Inc., et al. (No. C072169, filed 8/27/15), the California Court of Appeal for the Third Appellate District upheld the trial court's discretion to not award prevailing party attorneys' fees to the party who won a prompt payment dispute. California Business and Professions Code §7108.5 and Public Contract Code §§7107 and 10262 are the mechanisms for obtaining prompt payment relief in California. As shown by the outcome, it is possible to win and lose at the same time.
West Bay Builders, Inc. (“West Bay”) was the prime contractor on a school construction project for Stockton Unified School District. West Bay entered into a subcontract agreement with James L. Harris Painting & Decorating, Inc. (“Harris”) on the project. During construction there were disagreements between West Bay and Harris regarding the contractual scope of work, and Harris performed work it believed was outside the contract, believing it would be paid for the additional work. After West Bay refused to pay for the additional work, Harris left the project, and West Bay hired another subcontractor to complete the work.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Abigail E. Lighthart, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Ms. Lighthart may be contacted at alighthart@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Delaware Supreme Court Choice of Law Ruling Vacates a $13.7 Million Verdict Against Travelers
August 07, 2018 —
Gregory Capps & Zachery Roth - White and Williams LLPOn July 16, 2018, the Delaware Supreme Court held in Travelers Indemnity Company v. CNH Industrial America, LLC, No. 420, 2017 (Del. Jul. 16, 2018), that a court’s choice of law inquiry in an insurance coverage dispute should focus on the contacts most relevant to the insurance contract rather than the location of the underlying claims. In Travelers, CNH Industrial America, LLC (CNH), sought coverage for asbestos liabilities associated with J.I. Case, Inc., a subsidiary it had acquired, under policies issued to J.I. Case and its former parent company, Tenneco, Inc. The issue before the Delaware Supreme Court was whether the anti-assignment clause in three Travelers policies issued to Tenneco, Inc. precluded the assignment of the policies to CNH. The validity of the assignment turned on which state’s law governed the dispute. (Under Wisconsin law, the parties agreed that the assignment was valid, while under Texas law, the parties agreed the assignment was invalid.)
Reprinted courtesy of
Gregory Capps, White and Williams LLP and
Zachery Roth, White and Williams LLP
Mr. Capps may be contacted at cappsg@whiteandwilliams.com
Mr. Roth may be contacted at rothz@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Breaking Down Homeowners Association Laws In California
April 03, 2019 —
Lauren Hickey - Bremer Whyte Brown & O'Meara LLPPurpose of HOAs
Property ownership often combines elements of individual and common ownership interests. For example, a property owner may individually own his or her living quarters, but also own a common interest in amenities that are considered too expensive for a single homeowner to purchase individually (such as a pool, gym, or trash collection service). Properties with such elements usually take the form of apartments, condominiums, planned developments, or stock cooperatives (together known as “common interest developments” or “CIDs”). Whenever a CID is built, California law requires the developer to organize a homeowner association (or “HOA), which can take several different names, including “community association”. Initially, the developer relies on the HOA to market the development to prospective buyers. Once each unit in the development is sold, management of the HOA is passed to a board of directors elected by the homeowners. At that point, the primary purpose of the HOA shifts to maintenance of common amenities and enforcement of community standards.
Dues/Assessments
HOAs generally charge each homeowner monthly or annual dues to cover the cost of their services. HOAs may also charge special assessments to cover large, abnormal expenses, such as the cost of upgrades or improvements. The amount charged in dues and assessments is established by the HOA’s board of directors, within the limits set by the HOA’s governing documents and California Civil Code section 1366. Section 1366 provides that HOA dues may not be increased by more than 20 percent of the amount set in the previous year, and the total amount of any special assessments charged in a given year generally may not exceed 5 percent of the HOA’s budgeted expenses.
Read the court decisionRead the full story...Reprinted courtesy of
Lauren Hickey, Bremer Whyte Brown & O'Meara LLP
Fargo Shows Record Home Building
October 01, 2013 —
CDJ STAFFHome builders in the area of Fargo, North Dakota are describing growth in the area as “enormous.” Darrick Guthmiller, the president of the Home Builders Association of Fargo-Moorhead noted that in sixteen years of building homes, this was the best he’d seen. The Home Builders Association expects that next year might even be better.
Read the court decisionRead the full story...Reprinted courtesy of
Hospital Inspection to Include Check for Construction Defects
October 08, 2013 —
CDJ STAFFThe Temecula Valley Hospital is almost ready to be opened. One last step is an inspection from the California Department of Public Health’s Licensing and Certification Division. The inspection will take place over three to five days and will include not only building defects, but will also seek to identify problems that could compromise patient care. Any problems identified by the inspectors will have to be remedied before the hospital can open.
Darlene Wetton, the CEO/president of the hospital said that the hospital worked with both the state and contractors to assure that the construction met the state standards. Currently, the city of Temecula does not have a hospital.
Read the court decisionRead the full story...Reprinted courtesy of