Insurer’s Discovery Requests Ruled to be Overbroad in Construction Defect Suit
October 28, 2011 —
CDJ STAFFThe US District Court has ruled in the case of D.R. Horton Los Angeles Holding Co. Inc. v. American Safety Indemnity, Co. D.R. Horton was involved in a real estate development project. Its subcontractor, Ebensteiner Co., was insured by ASIC and named D.R. Horton as an additional insured and third-party beneficiary. D.R. Horton, in response to legal complaints and cross-complaints, filed for coverage from ASIC under the Ebensteiner policy. This was refused by ASIC. ASIC claimed that “there is no potential coverage for Ebensteiner as a Named Insurer and/or D.R. Horton as an Additional Insured.” They stated that “the requirements for coverage are not satisfied.”
The case same to trial with the deadline for discovery set at March 1, 2011. ASIC stated they were seeking the developer’s “job file” for the Canyon Gate project. D.R. Horton claimed that ASIC’s discovery request was overbroad and that it would be “unduly burdensome for it to produce all documents responsive to the overbroad requests.”
D.R. Horton did agree to produce several categories of documents, which included:
“(1) final building inspection sign-offs for the homes that are the subject of the underlying litigation;(2) an updated homeowner matrix for the underlying actions; (3) the concrete subcontractor files; (4) the daily field logs for D.R. Horton’s on-site employee during Ebensteiner’s work; (5) documents relating to concrete work, including documents for concrete suppliers; (6) documents relating to compacting testing; (7) documents relating to grading; and (8) D.R. Horton’s request for proposal for grading”
The court found that the requests from ASIC were overbroad, noting that the language of the ASIC Request for Production of Documents (RFP) 3-5 would include “subcontractor files for plumbing, electric, flooring, etc. - none of these being at issue in the case.” The court denied the ASIC’s motion to compel further documents.
The court also found fault with ASIC’s RFPs 6 and 7. Here, D.R. Horton claimed the language was written so broadly it would require the production of sales information and, again, subcontractors not relevant to the case.
Further, the court found that RFPs 8, 10, 11, and 13 were also overbroad. RFP 8 covered all subcontractors. D.R. Horton replied that they had earlier complied with the documents covered in RFPs 10 and 11. The court concurred. RFP 13 was denied as it went beyond the scope of admissible evidence, even including attorney-client communication.
The court denied all of ASIC’s attempts to compel further discovery.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Delaware “occurrence” and exclusions j(5) and j(6)
June 10, 2011 —
CDCoverage.comIn Goodville Mut. Cas. Co. v. Baldo, No. 09-338 (D. Del. June 2, 2011), claimants condominium association and unit owners sued project developer Rehoboth and general contractor Capano seeking damages because of moisture penetration property damage to common elements and individual units resulting from construction defects. Rehoboth and Capano filed a third party complaint against insured property manager Baldo alleging that, if Rehoboth and Capano were liable to claimants, Baldo was also liable because of Baldo’s failure to properly manage, maintain, and repair the property
Read the full story…
Reprinted courtesy of CDCoverage.com
Read the court decisionRead the full story...Reprinted courtesy of
Don’t Spoil Me: Oklahoma District Court Rules Against Spoliation Sanctions
January 08, 2024 —
Kyle Rice - The Subrogation StrategistIn Okla. Farm Bureau Mut. Ins. Co. v. Omega Flex, Inc., No. CIV-22-18-D, 2023 U.S. Dist. LEXIS 197755, the United States District Court for the Western District of Oklahoma (the District Court) determined spoliation sanctions were not warranted after a home was demolished for repair following a joint scene examination.
The insurer, Oklahoma Farm Bureau Mutual Insurance Company (Insurer) provided a policy of insurance to Michael and Sondra Diel (the Diels). On July 11, 2020, the Diels’ home was struck by lightning and their attic caught fire. Following the loss, Insurer retained both counsel and fire origin and cause experts to inspect the Diels’ property. Insurer’s counsel informed in-house counsel for Omega Flex, Inc. (Omega Flex) via a letter dated July 14, 2020, that a preliminary investigation indicated the fire may have been caused by an Omega Flex product—specifically, TracPipe Corrugated Stainless Steel Tubing (CSST). Insurer’s counsel invited Omega Flex to inspect the property, noting: “It is anticipated that the loss will exceed $300,000” and stating that any inspection “must be completed during the next two weeks.
At that time, the homeowner will proceed with demolition to rebuild.” (Emphasis added).
Read the court decisionRead the full story...Reprinted courtesy of
Kyle Rice, White and WilliamsMr. Rice may be contacted at
ricek@whiteandwilliams.com
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
Mitigating FCRA Risk Through Insurance
November 30, 2020 —
Sergio F. Oehninger, Geoffrey B. Fehling & Matt Revis - Hunton Insurance Recovery BlogAs reported in a recent Hunton Andrews Kurth client alert, Mitigating FCRA Risks in the COVID-19 World (Oct. 23, 2020), consumer litigation claims related to the Fair Credit Reporting Act (FCRA) doubled in the years leading up to the COVID-19 pandemic. After a slight decrease in FCRA filings due to court closures and other COVID-19 restrictions, claims will likely resume their previous upward trajectory. In fact, the Consumer Financial Protection Bureau (CFPB) has already seen an uptick in consumer complaints, many of which mention COVID-19 specific keywords.
Given the anticipated rise in FCRA complaints, the alert highlights the need for financial institutions and financial services companies to develop FCRA-compliant policies and procedures, including training on those policies and procedures, to mitigate the risk of FCRA-related enforcement actions and litigation claims, particularly in light of the regulatory changes relating to the COVID-19 pandemic.
Another important risk mitigation tool to consider is insurance, which can offer protection when even the most robust preventative measures fail to prevent an FCRA claim. Coverage for FCRA-related claims—often from directors’ and officers’ (D&O) or errors and omissions (E&O) policies—might be broader than one would initially expect. Policies may cover defense costs involving legal fees, as well as indemnification for damages.
Reprinted courtesy of
Sergio F. Oehninger, Hunton Andrews Kurth,
Geoffrey B. Fehling, Hunton Andrews Kurth and
Matt Revis, Hunton Andrews Kurth
Mr. Oehninger may be contacted at soehninger@HuntonAK.com
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Trump Soho May Abandon Condos to Operate Mainly as Hotel
January 28, 2015 —
Nadja Brandt – BloombergLower Manhattan’s Trump Soho, the five-year-old tower that was seized in a foreclosure amid slow sales of its condominiums, may drop its focus on part-time residences and operate most of the property solely as a hotel.
The building’s new owner, Los Angeles-based CIM Group, is “stepping away” from marketing the roughly two-thirds of condos that remain unsold, said Gary Schweikert, the building’s managing director. The company is considering converting the unsold units at the tower permanently into hotel rooms, he said.
Read the court decisionRead the full story...Reprinted courtesy of
Nadja Brandt, BloombergMs. Brandt may be contacted at
nbrandt@bloomberg.net
Mitsui Fudosan Said to Consider Rebuilding Tilted Apartments
October 28, 2015 —
Katsuyo Kuwako – BloombergMitsui Fudosan Co., Japan’s biggest developer, is considering rebuilding an apartment complex in Yokohama after one of the four buildings started to tilt, according to a person familiar with the situation.
Kiyotaka Fujibayashi, president and chief executive officer of Mitsui Fudosan Residential Co., on Thursday explained the plans to residents, according to the person, who asked not to be named because the information is private. Another option the company is studying is buying back the apartments from the residents at a price higher than what they had paid, the person said. The project was sold in 2006.
Mitsui Fudosan is the latest developer to come under scrutiny for defects at residential projects in the Tokyo area. Mitsubishi Estate Co., Japan’s biggest developer by market value, said last year it would rebuild a residential complex in the upscale Aoyama neighborhood after finding faults. Also last year, Sekisui House Ltd. said it would reconstruct a residential complex that was being built by Taisei Corp. after finding some columns were missing reinforcing metals.
Read the court decisionRead the full story...Reprinted courtesy of
Katsuyo Kuwako, Bloomberg
The “Ugly” Property Next Door is Ruining My Property Value
September 14, 2017 —
Kevin J. Parker - Snell & Wilmer Real Estate Litigation BlogTraditional bases for private nuisance claims include circumstances where noise, light, vibration, or odor emanating from a neighboring property harm the value of your property. Such bases can be objectively verified and quantified. Courts in various states depart, however, on the issue of whether pure unsightliness of a neighboring property, which diminishes the value of your property, supports a cognizable damages claim against the neighboring property owner under the law of nuisance.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin J. Parker, Snell & WilmerMr. Parker may be contacted at
kparker@swlaw.com