Subcontractors Have a Duty to Clarify Ambiguities in Bid Documents
August 19, 2015 —
Craig Martin – Construction Contractor AdvisorSeveral months ago, I wrote about an escalator subcontractor that sued a general contractor, demanding payment for work completed based on approved shop drawings. The trial court agreed with the subcontractor, but the general contractor appealed. Ten months later, the Court of Appeals reversed, finding that the subcontractor had a duty to bring to the general contractor’s attention major discrepancies or errors they detect in the bid documents.
“The subcontractor failed to disclose ambiguities in the plans and must suffer the peril.”
Construction Difficulties
The subcontractor installed 32 inch escalators throughout the project, but the plans called for 40 inch escalators. The general contractor and subcontractor could not reach agreement on how the dispute should be resolved. The subcontractor sued the general to get paid for replacing the escalators and the general sued to subcontractor for concessions it had to pay to the owner.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Part II: Key Provisions of School Facility Construction & Design Contracts
July 21, 2018 —
David R. Cook - Autry, Hall & Cook, LLPIn
Part I of this article, published in late April, we discussed the performance risk and time risk involved with construction and design contracts, and in Part II, we will cover cost risk and political risk.
Cost Risk
School budgets are limited for many reasons, and the construction budget is no exception. As a result, contracts should guard against unwarranted cost increases and claims. In the absence of a written change order signed by the appropriate officer, the contract should absolutely prohibit additional compensation for changes in the work. It should forbid claims for all events except those within the school authority’s sole control. Even for permitted claims, the contractor must provide written notice so that the authority might alleviate the problem and control its costs. To encourage the contractor to limit costs and claims, the contract could include a shared-savings clause, which grants an incentive payment for completion within the budget.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Emotional Distress Damages Not Distinct from “Annoyance and Discomfort” Damages in Case Arising from 2007 California Wildfires
February 16, 2017 —
Kirsten Lee Price & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPIn Hensley v. San Diego Gas & Elec. Co., (No. D070259, filed 1/31/17), the California Court of Appeal for the Fourth Appellate District held that emotional distress damages are available on claims for trespass and nuisance as part of “annoyance and discomfort” damages.
In Hensley, plaintiffs sustained fire damage to their home and property during the 2007 California wildfires. The Hensleys were forced to evacuate as the fires advanced. Although their home was not completely destroyed, it sustained significant damage and they were not able to return home permanently for nearly two months. Thereafter, the Hensleys filed suit against San Diego Gas and Electric Company (“SDG&E”) asserting causes of action for trespass and nuisance, among others. Mr. Hensley, who had suffered from Crohn’s disease since 1991, further claimed that as a result of the stress from the fire, he experienced a substantial increase in his symptoms and his treating physician opined that “beyond a measure of reasonable medical certainty... the stress created by the 2007 San Diego fires caused an increase of [Mr. Hensley’s] disease activity, necessitating frequent visits, numerous therapies, and at least two surgeries since the incident.” SDGE moved, in limine, to exclude evidence of Mr. Hensley’s asserted emotional distress damages arguing he was not legally entitled to recover them under theories of trespass and nuisance. The trial court agreed and excluded all evidence of such damages.
Reprinted courtesy of
Kirsten Lee Price, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Ms. Price may be contacted at kprice@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Replacement of Defective Gym Construction Exceeds Original Cost
January 22, 2013 —
CDJ STAFFAustin, Texas has torn down a school gym, the Turner-Roberts Recreation Center at the Overton Elementary School, due to structural problems which became evident after the gym was completed four years ago. The cost of the new gym is $6.4 million, more than the cost of building the gym in the first place. The city is paying $3 million in repair costs with the rest of the money coming from the companies that designed and built the now demolished gym. According to the Austin Statesman, the total cost to the city will be about $8.6 million.
The Turner-Roberts Recreation Center cost $5.6 million to build, but soon after it opened, structural problems were discovered. Cracks formed in walls and glass doors buckled. The settlement with the designer, contractor, and engineering firm did not require the firms to admit fault as they paid $3.4 million to fix the situation. The Statesman was unable to get a breakdown of how much each firm paid. Tom Cornelius, president of the GSC, the architectural firm on the project told the Statesman that "the foundation issues were not caused by design defects."
Initially, the city sought to repair the gym, but early excavation determined that the defects were too extensive. In addition to the structural flaws, it was also determined that the HVAC system was faulty. Excavation also damaged plumbing work. Tearing down the gym turned out to be the most cost-effective response.
Read the court decisionRead the full story...Reprinted courtesy of
Disputes Over Arbitrator Qualifications: The Northern District of California Offers Some Guidance
August 10, 2021 —
Justin K. Fortescue - White and WilliamsThe selection of an arbitration panel can often lead to disputes between the parties regarding things like whether a particular candidate is qualified, whether a challenge to an arbitrator’s qualifications can be addressed pre-award and whether a party that names an unqualified arbitrator should lose the opportunity to name a replacement. In Public Risk Innovations v. Amtrust Financial Services, No. 21-cv-03573, 2021 U.S. Dist. LEXIS 129464 (N.D. Ca. July 12, 2021), the court provided answers on all three of these issues.
In Amtrust, the parties filed cross-motions to compel arbitration. Although both parties agreed the dispute was arbitrable, they disagreed about whether Public Risk Innovations, Solutions and Management’s (PRISM) arbitrator was qualified under the terms of the applicable contract. In seeking to have PRISM’s arbitrator disqualified, Amtrust argued that he: (1) was not a “current or former official of an insurance or reinsurance company”; and (2) was not “disinterested.” Amtrust also argued that because PRISM named an unqualified arbitrator (and presumably the time to appoint had passed), PRISM should be deemed to have failed to select an arbitrator as required by the contract and that Amtrust had the right to select a second arbitrator of its choice.
Read the court decisionRead the full story...Reprinted courtesy of
Justin K. Fortescue, White and WilliamsMr. Fortescue may be contacted at
fortescuej@whiteandwilliams.com
Work without Permits may lead to Problems Later
September 10, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to the Los Angeles Register, “Southern California homeowners often have repairs or improvements done to their property without getting the required building permits,” which sometimes, may be fine, but other times it leads to disastrous problems.
The Register used an example of a San Clemente couple who had issues selling their home when a building inspector found that weep screeds were covered up by a cement deck installed by a contractor. The contractor also failed to get building permits for the work that was done. The buyer stated that repairs needed to be done prior to the sale.
According to Mac MacKenzie, an agent at Coldwell Banker in Irvine, the situation is not uncommon: “We’ve had (permit problems) kill deals before, and we’ve had them almost kill deals. If it’s serious enough, it can stop a transaction from closing.”
Permits are generally required “for any alteration, major repairs or new construction,” according to the Register, while they are not necessary “for minor repairs, such as fixing leaky pipes, painting, new carpeting or new kitchen countertops.”
Read the court decisionRead the full story...Reprinted courtesy of
French Laundry Spices Up COVID-19 Business Interruption Debate
April 20, 2020 —
Jeffrey J. Vita & Melanie A. McDonald - Saxe Doernberger & VitaOn March 26, 2020, Michelin-rated Napa Valley restaurants, French Laundry and Bouchon Bistro, and their celebrity chef, Thomas Keller, filed the second known
coronavirus-related declaratory judgment (DJ) lawsuit by a restaurant. The restaurants filed their DJ against Hartford Fire Insurance Company just seven days after Napa County issued a Shelter at Home Order.1 Chef Keller’s suit comes on the heels of the first such suit by a restaurant seeking to recover business income losses, filed by iconic New Orleans French Quarter restaurant Oceana Grill2 on March 17, just four days after the Louisiana governor issued an order prohibiting gatherings of more than 250 people.
As local governments seek to protect their citizens and prevent an onslaught of cases in area hospitals, they are issuing various “stay home,” “shelter at home,” and similar orders to force social distancing and to help flatten the curve of the growth in COVID-19 cases. Restaurants nationwide are especially hard hit by these orders, as many of these orders contain size limitations on gatherings, which have required that restaurants and bars limit capacity (as in the March 13th Louisiana order). Other such orders require non-essential businesses to “cease all activities in the County” (as in the Napa County Shelter at Home order). The Napa County order does not exempt restaurants as “essential businesses,” except when providing food for take-out or delivery. Other orders, still, directly address restaurants and require them to cease allowing public consumption of food and beverages (as in the subsequent, March 17th Louisiana order).
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C. and
Melanie A. McDonald, Saxe Doernberger & Vita, P.C.
Mr. Vita may be contacted at jjv@sdvlaw.com
Ms. McDonald may be contacted at mam@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Vallagio v. Metropolitan Homes: The Colorado Court of Appeals’ Decision Protecting a Declarant’s Right to Arbitration in Construction Defect Cases
May 20, 2015 —
David M. McLain – Colorado Construction LitigationOn May 7th, the Colorado Court of Appeals issued its much anticipated ruling in Vallagio at Inverness Residential Condominium Association, Inc. v. Metropolitan Homes, Inc., et al., 2015COA65 (Colo. App. May 7, 2015). By way of background, the Vallagio at Inverness Residential Condominiums were developed by Metro Inverness, LLC, which also served as the declarant for its homeowners association. Metropolitan Homes was Metro Inverness’ manager and the general contractor on the project. Greg Krause and Peter Kudla served as declarant-appointed members of the Association’s board during the period of declarant control.
When it set up the Association, Metro Inverness included within the Association’s declaration a mandatory arbitration provision specifically for construction defect claims. This provision stated that it “shall not ever be amended without the written consent of Declarant and without regard to whether Declarant owns any portion of the Real Estate at the time of the amendment.”
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at