Substituting Materials and Failure to Comply with Contractual Requirements
November 19, 2021 —
David Adelstein - Florida Construction Legal UpdatesIt is important to remember that if you are going to substitute materials from those specified, you need to make sure there is proper approval in doing so–make sure to comply with the contractual requirements to substitute materials. Otherwise, you could be in a situation where you are contractually required to remove the installed substituted materials and replace with the correct specified materials. This is not the situation you want to find yourself in because this is oftentimes a costly endeavor. This was the situation in Appeal-of-Sauer, Inc., discussed below, on a federal project. The best thing that you can do is comply with the contractual requirements if you want to substitute materials. If you are in the situation where it is too late, i.e., you already installed incorrect materials, you want to demonstrate the substituted materials are functionally equivalent to the specified materials and/or come up with an engineering solution, as required, that could be less costly then ripping out the installed material and replacing with the correct material. Even doing so, however, is not a “get out of jail free card” and does not necessarily mean there is not a strong basis to require you to install the correct specified material.
In Appeal of- Sauer, Inc., ASBCA 61847, 2021 WL 4888192 (ASBCA September 29, 2021), a federal project’s engineering requirements required cast iron piping for the above ground sanitary system. However, the prime contractor installed PVC piping instead of cast iron piping. The prime contractor believed it had the appropriate approval through its submittal. The government, through its contracting officer, directed the prime contractor to remove installed PVC piping to replace with cast iron. The government did not believe PVC piping was the functional equivalent of cast iron piping for the above ground sanitary system due to its concern with the noise level of waste materials flowing through the piping. The prime contractor submitted a claim for its removal and replacement costs which was denied by the contracting officer. On appeal with the Armed Services Board of Contract Appeals, the Board agreed with the contracting officer explaining: “While we agree that a design change could be approved by the designer of record and brought to the attention of the government before being incorporated into the design documents, the [prime contractor’s] task order required that such a design change meet the minimum requirements of the solicitation and accepted proposal. The plumbing submittal [the prime contractor] issued here, showing the use of PVC instead of cast iron for the above ground waste piping, did not meet the minimum requirements of the solicitation.” Appeal of-Sauer, Inc., supra.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
More Clear, But Not Yet Crystal: Virginia Amends its Prompt Payment Law and Legislation Banning “Pay-If-Paid Clauses in Construction Contracts Effective July 1, 2023
November 16, 2023 —
Hanna Lee Blake - ConsensusDocsThe Virginia General Assembly has joined a minority of jurisdictions that ban pay-if-paid clauses in construction contracts on public and private projects. Senate Bill 550 went into effect applying to contracts executed after January 1, 2023, and most recently has been amended effective July 1, 2023. This update highlights the recent amendments to Virginia’s prohibition against pay-if-paid provisions, of which owners and contractors should be aware to ensure that their contracts comply with developing law in the Commonwealth.
Recap on Senate Bill 550
On April 27, 2022, the Virginia General Assembly passed Senate Bill 550, which amended Virginia Code §§ 2.2-4354 and 11-4.6, which govern both public and private sector contracts. In short, SB 550 (as the bill is commonly known) prohibited pay-if-paid clauses, and established fixed deadlines for the payment of invoices on private projects. Previously, Virginia’s Prompt Payment Act only applied to public projects.
Read the court decisionRead the full story...Reprinted courtesy of
Hanna Lee Blake, Watt TiederMs. Blake may be contacted at
hblake@watttieder.com
Home Prices in 20 U.S. Cities Rose at a Faster Pace in October
January 06, 2016 —
Victoria Stilwell & Michelle Jamrisko – BloombergHome values in 20 U.S. cities rose at a faster pace in the year ended October as lean inventories of available properties combined with steadily improving demand.
The S&P/Case-Shiller index of property values climbed 5.5 percent from October 2014 after rising 5.4 percent in the year ended September, the group said Tuesday in New York. The median projection of 21 economists surveyed by Bloomberg called for a 5.6 percent advance. Nationally, prices rose 5.2 percent year-over-year.
A limited supply of properties for sale has helped prop up home values, boosting the household wealth levels of U.S. homeowners in the process. Faster wage growth and continued low borrowing costs will be needed to keep low-income and first-time buyers in the market and provide the next leg of growth in the housing recovery.
Reprinted courtesy of
Victoria Stilwell, Bloomberg and
Michelle Jamrisko, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Berlin Lawmakers Get a New Green Workspace
June 21, 2021 —
Iain Rogers - BloombergOn a site steeped in history a few hundred meters from the Reichstag in central Berlin, an office building is rapidly taking shape that handily symbolizes how climate protection has come to dominate the political narrative ahead of September’s election.
The modular Luisenblock West, which will provide working space for Germany’s Bundestag, or lower house of parliament, is mostly wooden beyond a reinforced concrete core. The individual units that make up the bulk of the building are assembled at a site in the east of the city and designed to reduce carbon footprint by capturing thousands of tons of carbon dioxide.
With just four months until the national vote that will mark the end of Angela Merkel’s 16-year reign, the Greens are leading the chancellor’s conservative bloc in some opinion polls and climate protection is high on the list of priorities for many voters. The former fringe party has a real chance of leading a German government for the first time, while traditional parties scramble to affirm their environmental credentials.
Read the court decisionRead the full story...Reprinted courtesy of
Iain Rogers, Bloomberg
MBS’s $500 Billion Desert Dream Just Keeps Getting Weirder
August 29, 2022 —
Vivian Nereim - BloombergOne day last September, a curious email arrived in Chris Hables Gray’s inbox. An author and self-described anarchist, feminist, and revolutionary, Gray fits right into Santa Cruz, Calif., where he lives. He’s written extensively about genetic engineering and the inevitable rise of cyborgs, attending protests in between for causes such as Black Lives Matter.
While Gray had taken some consulting gigs over the years, he’d never received an offer like this one. The first shock was the money: significantly more than he’d earned from all but one of his books. The second was the task: researching the aesthetics of seminal works of science fiction such as Blade Runner. The biggest surprise, however, was the ultimate client: Mohammed bin Salman, the 36-year-old crown prince of Saudi Arabia.
MBS, as he’s known abroad, was in the early stages of one of the largest and most difficult construction projects in history, which involves turning an expanse of desert the size of Belgium into a high-tech city-region called Neom. Starting with a budget of $500 billion, MBS bills Neom as a showpiece that will transform Saudi Arabia’s economy and serve as a testbed for technologies that could revolutionize daily life. And as Gray’s proposed assignment suggested, the crown prince’s vision bears little resemblance to the cities of today. Intrigued, Gray took the job. “If I can be honest with how I see the world, I’ll pretty much put my work out to anyone,” he says.
Read the court decisionRead the full story...Reprinted courtesy of
Vivian Nereim, Bloomberg
Case-Shiller Redo Shows Less Severe U.S. Home-Price Slump
September 03, 2014 —
Lorraine Woellert – BloombergThe collapse in U.S. home prices that stoked the worst recession since the Great Depression wasn’t quite as severe as initially estimated, according to data from S&P/Case-Shiller.
Property values nationally fell 26 percent from the February 2007 peak to the December 2011 trough, not 34 percent as previously reported, revised data showed last week. The index will now be issued monthly rather than quarterly.
The change is the result of CoreLogic Inc. (CLGX)’s $6 million purchase of the S&P/Case-Shiller index from technology company Fiserv Inc. in March 2013. Case-Shiller has spent more than a year retrofitting its model with CoreLogic’s bigger, higher-quality data set, leading to a change in how the index looks.
Read the court decisionRead the full story...Reprinted courtesy of
Lorraine Woellert, BloombergMs. Woellert may be contacted at
lwoellert@bloomberg.net
Traub Lieberman Partner Lisa Rolle Obtains Summary Judgment in Favor of Defendant
November 15, 2022 —
Lisa M. Rolle - Traub LiebermanTraub Lieberman Partner Lisa M. Rolle obtained summary judgment in favor of defendant SRI Fire Sprinkler, LLC, a family-owned and operated fire sprinkler company which generally provides fire sprinkler installation, inspection, and maintenance services throughout the Northeast and New England. The judgment was determined pursuant to CPLR 3211(a)(5) on the grounds that Philadelphia Indemnity Insurance Company’s (Plaintiff) negligent construction claim accrued on the date when work was completed at the premises, not on the date of the incident as alleged in the Plaintiff’s complaint. In the underlying subrogation action, the Plaintiff commenced the action in subrogation of its insured, Bet Am Shalom Synagogue (Bet Am), to recover damages in excess of $173,390.86 which it allegedly paid to Bet Am for water damage cleanup and remodeling after certain sprinkler pipes froze and burst in the recently constructed wing of the Westchester synagogue on January 1, 2019 and January 7, 2019. The Plaintiff alleged that its subrogor, Bet Am, sustained interior water damage on the first floor and basement levels of the premises, including the carpets, drywall, insulation, bathroom, kitchen and appliances, dining room, hallways, closets, basement storage rooms and supplies, and basement classrooms.
Read the court decisionRead the full story...Reprinted courtesy of
Lisa M. Rolle, Traub LiebermanMs. Rolle may be contacted at
lrolle@tlsslaw.com
Builder Exposes 7 Myths regarding Millennials and Housing
January 12, 2015 —
Beverley BevenFlorez-CDJ STAFFBuilder Magazine discussed seven myths regarding Generation Y and housing, and stated whether it was fact or fiction. First, they answered whether “Millennials Carry Historically High Student Debt Levels,” (True), and second they concluded it was true that “Millenials Can’t Afford Down Payment at Today’s Standards.” However, Builder was split on whether “Millennials Will Pay a Premium for Green and Tech Features.”
Read the court decisionRead the full story...Reprinted courtesy of