COVID-19 Damages and Time Recovery: Contract Checklist and Analysis
April 27, 2020 —
Patrick J. Greene, Jr. - Peckar & AbramsonThis Alert explores the contract provisions and related rights that are likely to govern time and compensation adjustments for COVID-19 impacts. As parties begin analyzing such rights, this is intended to serve as a useful guide and checklist.
Analysis of relevant contract provisions should start with careful consideration of the specific impacts that have been experienced and the causes of those impacts. The nature of the impact (delay, extra work, disruption, etc.) and the causes of such impacts (owner direction, government order, etc.) will generally govern the analysis and resulting course of action. Listing or creating a matrix of impacts and their causes may be an effective working tool.
Essentially, there are five primary impacts that will likely require critical analysis under the relevant contract provisions, and notably, more than one impact may be present:
a) complete or partial suspension of work,
b) additional work or requirements,
c) added cost,
d) delay, and
e) disruption.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick J. Greene, Jr., Peckar & AbramsonMr. Greene may be contacted at
pgreene@pecklaw.com
Construction Defects through the Years
July 31, 2013 —
CDJ STAFFBuilder has an article on the some building changes over the years that have led to construction defect problems. Is insulation evil? Well, that what some thought in the 1930s. Early attempts at insulating walls trapped moisture causing paint to peel. Then in the 1960s, the rise of aluminum wire lead to an even more serious problem: house fires.
And it continues. The plastic piping that was though to last forever when it was installed in the late 70s turned out to have about a decade of life. It’s a short forever. Eventually, polybutylene plumbing was forbidden by building codes.
The article has a series of building innovations that seemed like great ideas at the time, but were later found to be problematic.
Read the court decisionRead the full story...Reprinted courtesy of
Reasons to Be Skeptical About a Millennial Homebuying Boom in 2016
December 10, 2015 —
Patrick Clark – BloombergPredicting whether millennials are finally going to start buying homes in large numbers has become a seasonal sporting event for real estate experts (also something resembling a periodic parental nag). There's good reason for the abiding fixation. Millennials are the largest generation in the U.S. labor force and something akin to guppies in the housing market food chain: When a first-time buyer moves into an entry-level house, it lets the sellers upgrade. But they've been held back by housing price increases that outpace wage hikes, not to mention limited access to credit, and rising rents that make it harder to save for a down payment.
Will next year be the year that millennials1 finally satisfy builders and real estate agents (not to mention mom and dad) by making their presence felt in the housing market? Yes, but not to the degree that many might hope.
Millennials will make up the largest share of homebuyers in 2016
This is more of a demographic inevitability than a prediction. Historically, the largest share of U.S. homebuyers have been between 25 and 34 years old. Millennials will buy one out of three homes in 2016, predicts Jonathan Smoke, chief economist for Realtor.com, a small uptick from this year. If you prefer your glass half empty, though, Zillow Chief Economist Svenja Gudell thinks the median age of first-time home buyers will hit a new high next year. In either case, Americans will continue the trend of buying their first homes later in life than they did in past decades, as the chart below shows—likely due to some mix of wage stagnation, rising housing costs, and a tendency to start families later in life.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Clark, Bloomberg
Construction Law Alert: Concrete Supplier Botches Concrete Mix, Gets Thrashed By Court of Appeal for Trying to Blame Third Party
January 21, 2015 —
Steven M. Cvitanovic and Whitney L. Stefko – Haight Brown & Bonesteel LLPOn January 8, 2015, the Second Appellate district affirmed judgment of the lower court in State Ready Mix Inc. v. Moffatt & Nichol, and barred a concrete supplier from blaming a third party consultant for the concrete supplier's failure to deliver concrete that met project specifications.
In 2012, Major Engineering Marine, Inc. was hired by a project manager to construct a harbor pier in the Channel Islands Harbor. Major hired State Ready Mix, Inc. to supply the concrete for the project. State wrote and submitted a concrete mix design and, at the request of Major, civil engineer Moffatt & Nichol reviewed and approved State's mix design at no charge.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Fraud Claims and Breach Of Warranty Claims Against Manufacturer
March 04, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent case touches upon two issues that are noteworthy when considering fraud claims and breach of warranty claims against a manufacturer. Below contains a discussion on these claims.
Independent Tort Doctrine
“Florida’s independent tort doctrine provides that a party may not recover in tort for a contract dispute unless the tort is independent of any breach of contract.” MidAmerica C2L Inc. v. Siemens Energy, Inc., 2024 WL 414620, *6 (M.D.Fla. 2024). This means tort allegations and claims MUST be separate and distinct from performance under the contract. Id. (citation omitted).
In MidAmerica C2L, a plaintiff sued a manufacturer relating to sophisticated equipment for a coal gasification plant. The parties entered into different agreements for the equipment and a license where the plaintiff could use the manufacturer’s patented technology for its coal gasification plants. A dispute arose and the plaintiff sued the manufacturer under various legal theories. The manufacturer moved for summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Certificate of Merit to Sue Architects or Engineers Bill Proposed
May 03, 2011 —
CDJ STAFFNorth Carolina may become the twelfth state to require a Certificate of Merit to sue an architect or engineer. If North Carolina Senate Bill 435 (SB435) passes, then plaintiffs when filing a complaint will need to also attach an affidavit of a third-party licensed professional engineer or architect stating that the case has merit.
SB435 is a short two pages in its current form. The bill states that the “third-party licensed professional engineer or licensed architect shall (i) be competent to testify and hold the same professional license and practice in the same area of practice as the defendant design professional and (ii) offer testimony based upon knowledge, skill, experience, education, training, and practice. The affidavit shall specifically state for each theory of recovery for which damages are sought, the negligence, if any, or other action, error, or omission of the design professional in providing the professional service, including any error or omission in providing advice, judgment, opinion, or a similar professional skill claimed to exist and the factual basis for each such claim. The third-party licensed professional engineer or licensed architect shall be licensed in this State and actively engaged in the practice of engineering or architecture respectively.”
A few of the amendments allude to disciplining design professionals who certify civil actions that are without merit. The bill has been referred to the Committee on Judiciary I.
While North Carolina is considering enacting a Certificate of Merit law, eleven other states already require one, including Arizona, California, Colorado, Georgia, Maryland, Minnesota, New Jersey, Oregon, Pennsylvania, South Carolina, and Texas. Christopher D. Montez, a partner with Thomas, Feldman & Wilshusen, LLP, has written a useful summary for each state’s certificate of merit scheme.
Read the text of SB435
Track the progress of SB435
Read more from Christopher D. Montez’s article on Thomas, Feldman & Wilshusen, LLP site
Read the court decisionRead the full story...Reprinted courtesy of
The Pitfalls of Oral Agreements in the Construction Industry
June 28, 2021 —
Matthew A. Margolis - Construction ExecutiveToo often, construction professionals engage with each other to handle a project or series of projects and instead of memorializing their terms in writing, the agreement between the parties consists of nothing more than a conversation and a handshake. Both parties put their trust in each other that the terms they discussed will be honored. Nevertheless, one (or both) of the parties may eventually determine that their trust was misplaced, resulting in a big-money, big-headache dispute.
By having a written contract at the commencement of their relationship, these issues could have been avoided. Here are nine reasons to have a written contract.
Reprinted courtesy of
Matthew A. Margolis, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Margolis may be contacted at
mmargolis@sbwh.law
How Finns Cut Construction Lead Times in Half
December 17, 2024 —
Aarni Heiskanen - AEC BusinessRakennustieto organized a Q&A on December 5, 2024, titled “Halving Construction Lead Times—Responsible or Irresponsible?” The discussion focused on speeding up residential construction and renovations.
The experts answering questions were representatives from two Finnish contractors (COfLOW and Fira), a client organization (HOAS), a building materials retailer (STARK), and a research institute.
Can you halve construction lead time without sacrificing quality?
Jaana Matilainen of Rakennustieto asked the panelists whether halving construction time is a realistic goal today, whether they can provide any examples, and if the speed-up has increased or decreased quality.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi