Prevailing Payment Bond Surety Entitled to Statutory Attorneys’ Fees Even if Defended by Principal
January 09, 2023 —
Garret Murai - California Construction Law BlogFor contractors involved in California public works projects the scenario is not uncommon: The general contractor awarded the public works project is required to obtain a payment bond for the benefit of subcontractors and suppliers and the payment bond surety issuing the payment bond requires the general contractor to defend and indemnify the surety from and against any claims against the payment bond.
In Cell-Crete Corporation v. Federal Insurance Company, 82 Cal.App.5th 1090 (2022), the 4th District Court of Appeal examined whether a payment bond surety, who prevails in a claim against the payment bond, is entitled to statutory attorneys’ fees when the party actually incurring the attorneys’ fees was the general contractor, pursuant to its defense and indemnity obligations, as opposed to the surety itself.
The Cell-Crete Case
General contractor Granite Construction Company was awarded a public works contract issued by the City of Thermal known as the Airport Boulevard at Grapefruit Boulevard and Union Pacific Railroad Grade Separation Project. We’ll just call it the “Project.” Subcontractor Cell-Crete Corporation entered into a subcontract with Granite for lightweight concrete and related work.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Mind The Appeal Or: A Lesson From Auto-Owners Insurance Co. V. Bolt Factory Lofts Owners Association, Inc. On Timing Insurance Bad Faith And Declaratory Judgment Insurance Claims Following A Nunn-Agreement
August 06, 2019 —
Jean Meyer - Colorado Construction LitigationOn May 30, 2019, Judge Richard Brooke Jackson of the United States District Court for the District of Colorado offered an insightful lesson to the parties in Auto-Owners Insurance Co. v. Bolt Factory Lofts Owners Association, Inc.[1] on the importance of ripeness in declaratory judgment insurance actions and bad faith counterclaims. The case arrived in front of Judge Jackson based on the following fact pattern.
A homeowner association (Bolt Factory Lofts Owners Association, Inc.) (“Association”) brought construction defect claims against a variety of prime contractors and those contractors subsequently brought third-party construction defect claims against subcontractors. One of the prime contractors assigned their claims against a subcontractor by the name Sierra Glass Co., Inc. (“Sierra”) to the Association and all the other claims between all the parties settled. On the eve of trial involving only the Association’s assigned claims against Sierra, the Association made a settlement demand on Sierra for $1.9 million. Sierra asked its insurance carrier, Auto-Owners Insurance, Co. (“AOIC”), which had been defending Sierra under a reservation of rights letter, to settle the case for that amount, but AOIC refused. This prompted Sierra to enter into a “Nunn-Agreement” with the Association whereby the case would proceed to trial, Sierra would refrain from offering a defense at trial, the Association would not pursue any recovery against Sierra for the judgment, and Sierra would assign any insurance bad faith claims it may have had against AOIC to the Association. (“Nunn-Agreement”)
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at
meyer@hhmrlaw.com
CA Court of Appeal Reinstates Class Action Construction Defect Claims Against Homebuilder
September 03, 2015 —
Beverley BevenFlorez-CDJ STAFFLaurence R. Phillips, Andrew S. Azarmi, and Stefani Warren of Dentons reported that “on August 19, the California Court of Appeal, Fourth District, reinstated a class action asserting construction defect claims against a nationwide homebuilder.” According to the article, the decision is significant because “it effectively opens the door to class claims against homebuilders (and potentially other service providers employed in the homebuilding industry) arising out of alleged construction defects on California residential development and construction projects.”
The decision is unpublished, but “could signal a troubling trend for companies involved in the homebuilding industry in California. It is not yet clear whether the decision will be appealed to the California Supreme Court.”
Read the court decisionRead the full story...Reprinted courtesy of
Supreme Judicial Court of Maine Addresses Earth Movement Exclusion
March 01, 2021 —
James M. Eastham - Traub LiebermanIn Bibeau v. Concord Gen. Mut. Ins. Co., 2021 WL 243867, 2021 ME 4, the Supreme Judicial Court of Maine addressed an earth movement exclusion contained in a residential homeowners policy. In 2017, the insured submitted a claim to Concord for damage to the insured’s home which included foundation cracks and settlement resulting in interior damage to the home. The insured contended that the damage was the result of a 2006 water line leak. Concord denied the claim based on the Earth Movement exclusion contained in it’s policy which precluded coverage for losses caused by earthquakes, landslides, mudslides, mudflow, subsidence, sinkholes or “[a]ny other earth movement including earth sinking, rising or shifting; caused by or resulting from human or animal forces or any act of nature”.
The insured filed suit asserting a breach of the policy and unfair claims settlement practices. According to the insured’s expert, the damage was caused by a 2006 water line leak -- which in turn caused the foundation to settle. Concord's expert, however, concluded that the settling was caused by the house being built on “unprepared or uncontrolled fill” which allowed the house to settle at different rates. Despite the disagreement regarding the cause of the settling, the parties ultimately agreed that the damage was the result of earth moving under the house's foundation. Concord moved for summary judgment and the trial court entered summary judgment for Concord, reasoning that because there was no genuine dispute that the losses were caused by “subsurface soils being undermined and earth movement,” the Earth Movement exclusion precluded coverage. The trial court further concluded that the disagreement over the cause of the settlement was not material because regardless of the cause of the earth movement, the losses were clearly excluded by the policy's Earth Movement exclusion.
Read the court decisionRead the full story...Reprinted courtesy of
James M. Eastham, Traub LiebermanMr. Eastham may be contacted at
jeastham@tlsslaw.com
Axa Unveils Plans to Transform ‘Stump’ Into London Skyscraper
June 17, 2015 —
Patrick Gower – BloombergPlans for a skyscraper at 22 Bishopsgate in the City of London go on show for the first time today before developers Axa Real Estate and Lipton Rogers seek planning approval.
Axa bought the site in February, three years after work halted on the tower during the financial crisis. The plot became known as “the stump” because only the foundations, basements and the lift core up to level nine were built.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Gower, Bloomberg
Yet Another Reminder that Tort and Contract Don’t Mix
January 25, 2021 —
Christopher G. Hill - Construction Law MusingsI have stated on numerous occasions here at Musings that in Virginia, contract claims and tort claims (read fraud) don’t mix. A recent case from the Federal District Court for the Eastern District of Virginia presents another example of this principle. In Itility LLC v. The Staffing Resource Group, Judge Ellis of the Alexandria Division, considered ITility’s claims of fraud and breach of contract against SRG and one of its officers based upon SRG’s alleged violation of its duties under a teaming agreement. The claim by ITility was that TSRG provided false and misleading resumes and thus damaged ITility. SRG filed a Motion to Dismiss and the Court was therefore required to resolve the following issues: (1) whether plaintiff’s fraud claim is barred by Virginia’s “source of duty” rule; (2) whether plaintiff’s claim for tortious interference with a business expectancy is barred by SRG’s participation in the business expectancy, and (3) whether the teaming agreement between the parties bars plaintiff’s claims for consequential and punitive damages.
Reprinted courtesy of
The Law Office of Christopher G. Hill
Mr. Hill may be contacted at chrisghill@constructionlawva.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Clarifies Deadline to File Anti-SLAPP Motions in Light of Amended Pleadings
July 02, 2018 —
Tony Carucci - Snell & Wilmer Real Estate Litigation BlogCalifornia’s “anti-SLAPP” (“SLAPP” is an acronym for strategic lawsuit against public participation) statute—codified at California Code of Civil Procedure section 425.16 et seq.—is the primary vehicle for defending against any action involving petitioning or free speech. The statute was designed to provide an early and fast summary judgment-like procedure to allow defendants and cross-defendants to file a motion to dismiss either an entire complaint, specific causes of action, or even just portions of a cause of action, and to require the plaintiff to respond before conducting discovery. By facilitating an early challenge to a plaintiff or cross-complainant’s claims, the anti-SLAPP statute allows the responding party to avoid the costs and delay that chill the exercise of constitutionally protected rights.
Under California Code of Civil Procedure section 425.16(f), an anti-SLAPP motion must be filed “within 60 days of the service of the complaint . . . .” But what if the plaintiff files an ameded complaint? In Newport Harbor Ventures, LLC v. Morris Cerullo World Evangelism (2018) 4 Cal.5th 637, the California Supreme Court held that the 60-day timeline runs from the date a complaint is filed with the cause(s) of action challenged in the anti-SLAPP motion.
Read the court decisionRead the full story...Reprinted courtesy of
Tony Carucci, Snell & WilmerMr. Carucci may be contacted at
acarucci@swlaw.com
Housing Starts Plunge by the Most in Four Years
March 19, 2015 —
Bloomberg News(Bloomberg) -- Housing starts plummeted in February by the most since 2011 as plunging temperatures and snow became the latest hurdles for an industry struggling to recover.
Work began on 897,000 houses at an annualized rate, down 17 percent from January and the fewest in a year, the Commerce Department reported Tuesday in Washington. The pace was slower than the most pessimistic projection in a Bloomberg survey of 81 economists.
“Today’s report leaves me a little concerned,” said Michelle Meyer, deputy head of U.S. economics at Bank of America Corp. in New York. “While the initial reaction is to dismiss much of the drop because of the bad weather, the level of home construction continues to be depressed.”
Read the court decisionRead the full story...Reprinted courtesy of