Changes to Va. Code Section 43-13: Another Arrow in a Subcontractor’s Quiver
November 02, 2020 —
Christopher G. Hill - Construction Law MusingsAs is always the case here in Virginia, our General Assembly has made some legislative changes that affect construction contracting. One of these changes is an amendment to Va. Code 43-13 found in the mechanic’s lien section of the Virginia Code.
This section of the code has always required that any money paid to a contractor must first go toward paying its subcontractors, suppliers and laborers prior to being used for any other purpose. Prior to 2020, the only remedy for violaiton of Va. Code 43-13 was to go to the local Commonwealth’s Attorney and request a prosecution of the wrongdoer. For various reasons, including that such action did not get the subcontractor or supplier that remained unpaid under this section paid, this remedy was not often pursued except in the most egrigious cases.
A key change in the statute occurred during the 2020 legislative session states as follows:
Any breach or violation of this section may give rise to a civil cause of action for a party in contract with the general contractor or subcontractor, as appropriate; however, this right does not affect a contractor’s or subcontractor’s right to withhold payment for failure to properly perform labor or furnish materials on the project. Any contract or subcontract provision that allows a contracting party to withhold funds due under one contract or subcontract for alleged claims or damages due on another contract or subcontract is void as against public policy.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Wisconsin Federal Court Addresses Scope Of Appraisal Provision In Rental Dwelling Policy
September 05, 2022 —
James M. Eastham - Traub LiebermanIn Higgins v. State Farm Fire & Cas. Co., No. 22-C-198, 2022 U.S. Dist. LEXIS 117477 (E.D. Wis. July 5, 2022), the Court addressed the often disputed question of whether an appraisal provision in an insurance policy is limited to disputes over valuation or extends beyond valuation to causation and/or coverage. The underlying loss in the Higgins case involved a fire at a rental dwelling owned by the Plaintiff and insured by State Farm under a Rental Dwelling policy for, among other things, fire losses. Subsequent to being notified of the fire, State Farm investigated and provided the Plaintiff with its estimated cost of repair. Plaintiff disputed the estimate, including the repairs necessary, and also sought additional sums for debris removal and lost rent.
The insurance policy at issue in Higgins included an appraisal provision which provided: “If you and we fail to agree on the amount of loss, either one can demand that the amount of the loss be set by appraisal.” Pursuant to this provision, Plaintiff demanded that State Farm submit to an appraisal to resolve the parties' disagreements. State Farm responded by indicating that it would enter into appraisal over the areas where there were "pricing differences" but not areas where there were "scope differences." According to State Farm, there were a number of issues regarding the scope of repairs necessary to restore the dwelling to its pre-loss condition. Plaintiff disagreed with State Farm's position and did not seek to move forward with the appraisal process on only the items State Farm identified as appropriate for appraisal.
Read the court decisionRead the full story...Reprinted courtesy of
James M. Eastham, Traub LiebermanMr. Eastham may be contacted at
jeastham@tlsslaw.com
Subcontractor Exception to Your Work Exclusion Paves the Way for Coverage
April 03, 2013 —
CDJ STAFFIn a brief opinion, the Second Circuit vacated the district court's denial of coverage for construction defects. Scottsdale Ins. Co. v. R.I. Pools Inc., 2013 U.S. App. LEXIS 5680 (2nd Cir. March 21, 2013).
The insured, R.I. Pools, employed outside companies to supply concrete and to shoot the concrete into the ground. During the summer of 2006, it obtained its concrete from one subcontractor and used another to shoot the concrete. In 2009, nineteen customers of R.I. Pools from 2006 complained damage to their pools, including cracking, flaking, and deteriorating concrete.
Scottsdale sought a declaratory judgment against R.I. Pools that it had no obligations under the policy to defend or indemnify for claims related to cracks in the pools.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Real Estate & Construction News Roundup (07/05/23) – A Hospitality Strike in Southern California, Agencies Step in With Lenders and the Social in ESG
August 14, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, we see promising developments for climate change action in commercial real estate, how homeowners are reacting to new energy concerns, the fallout of the U.S. debt ceiling fight on global M&A deals, and more!
- There are new ways the commercial real estate sector can grow its commitment to climate goals and contributions to reducing its carbon footprint. (Mahesh Ramanujam, Forbes)
- Thousands of hospitality workers in Southern California went on strike to demand higher wages, access to affordable family health care benefits and stronger workplace protections. (Julianne McShane, NBC)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
U.S. Supreme Court Oral Arguments: Maritime Charters and the Specter of a New Permitting Regime
February 24, 2020 —
Anthony B. Cavender - Gravel2GavelEarlier this month, the Supreme Court heard oral arguments in two important environmental cases—one that could change the approach to routine maritime charters and another that could introduce a potentially punishing permitting regime via a CWA citizen suit.
Cleaning the Delaware: CITGO Asphalt Refining Company v. Frescati Shipping Company
The CITGO case involves a large oil spill into the Delaware River, and who bears financial responsibility for the cleanup. CITGO chartered an oil tanker to bring Venezuelan crude oil to CITGO’s New Jersey refinery located on the Delaware River. The tanker struck a submerged and abandoned anchor within yards of the refinery, and a large and expensive oil spill resulted. In accordance with the Oil Pollution Act, both the shipper, Frescati Shipping Company, and the United States, paid for the immediate oil spill response, and CITGO was later sued for a large share of these costs based on the fact that it entered into a charter with Frescati, which obliged CITGO to provide a “safe berth.” The U.S. Court of Appeals for the Third Circuit held that CITGO was liable under the principles of maritime law, meaning that CITGO was strictly liable for the spill even if no one knew that the anchor was present on the floor of the river or lurking in the waters of the Delaware River. CITGO has argued that this result is unfair and poses a threat to the maritime shipping industry if it is held to be strictly liable for this spill. It appears that this is may well be the majority rule that is applied when interpreting these routinely entered maritime charters. The Court’s decision will be immensely important to the shipping industry.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Inverse Condemnation and Roadwork
October 09, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPThe following case, issued yesterday by the Georgia Supreme Court, addresses the accrual of the statute of limitations on a claim of inverse condemnation based on nuisance.
Wise Bus. Forms, Inc. v. Forsyth Cnty., S22G0874, 2023 WL 6065278 (Ga. Sept. 19, 2023)
We granted certiorari in this case to clarify the standards for determining when a claim for inverse condemnation by permanent nuisance accrues for purposes of applying the four-year statute of limitation set forth in OCGA § 9-3-30 (a).
[. . .]
Permanent nuisance cases vary in relation to when the alleged harm to a plaintiff’s property caused by the nuisance becomes “observable” to the plaintiff. Forrister, 289 Ga. at 333 (2), 711 S.E.2d 641. In some cases, the harm to the plaintiff’s property is immediately observable “upon the creation of the nuisance.” Id. For example, where a landowner or governmental agency “erects a harmful structure such as a bridge or conducts a harmful activity such as opening a sewer that pollutes a stream,” and it is immediately obvious that the structure or activity interferes with the plaintiff’s interests, the plaintiff must file “one cause of action for the recovery of past and future damages caused by [the] permanent nuisance” within four years of the date the structure is completed or the harmful activity is commenced. Id. at 333-336 (2) and (3), 711 S.E.2d 641 (citing Restatement (Second) of Torts §§ 899 and 930). Phrased another way, where the “construction and continuance” of the permanent nuisance at issue is “necessarily an injury, the damage is original, and may be at once fully compensated. In such cases[,] the statute of limitations begins to run upon the construction of the nuisance.” City Council of Augusta v. Lombard, 101 Ga. 724, 727, 28 S.E. 994 (1897).
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Eliminating Waste in Construction – An Interview with Turner Burton
June 29, 2020 —
Aarni Heiskanen - AEC BusinessI had the pleasure of interviewing Turner Burton, President of Hoar Construction. We discussed waste in construction and how his company is on a mission to eliminate it.
Can you say a few words about yourself and your company?
I grew up around construction and this company, hearing about the business from both my grandfather and my father. I started working on job sites in high school forming concrete, continued working on projects throughout college, and since graduating from college, I’ve taken on different roles in the company to ensure I understand all aspects of the business.
Hoar Construction was founded 80 years ago, and throughout our history, we’ve been committed to learning from every project to improve our processes and deliver the best building experience possible for our clients and partners. But it’s the relentless pursuit of improvement that really sets us apart as builders – to always strive to be the best and do the right thing for our customers and partners. There’s something to be said for setting a goal that you’ll always be working toward. It fosters hard work, collaboration, and productive effort. If we’re always working to find a better way, then we will always be improving. That effort drives better results for our owners and everyone we work with. Essentially, we’re always working toward something. Always improving. Always in process.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Drug Company Provides Cure for Development Woes
November 18, 2011 —
CDJ STAFFVertex Pharmaceuticals is poised to become the holder of Boston’s biggest commercial lease, paying $72.5 million for 1.1 million square feet on Boston’s waterfront. Vertex’s new buildings are still under construction, but the plans have spurred other development in the Fan Pier area, according to the New York Times. The Times quotes Mary A. Burke, a senior economist at the Federal Reserve Bank of Boston that the Vertex project gives “a big push” to the “momentum for economic growth.”
The Fallon Company is building Vertex’s new laboratory and office space. They are separately planning to build a high-rise with 150 luxury condominium units. According to Joseph Fallon, the chief executive and president of the Fallon Company, there is already a waiting list of 50 buyers for the condominiums.
Across the street from the Vertex site, a group including Morgan Stanley and Boston Global Investors is planning a 23-block mixed use project that would include 1.2 million square feet of retail space. Additionally, the New England Development and the Hanover Group is building a 356-unit apartment building at the adjacent Pier 4.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of