Chicago Criticized for Not Maintaining Elevator Inspections
October 29, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Crain’s Chicago Business, “as few as a fifth of elevators get the required annual checkup,” Chicago Inspector General Joe Ferguson claimed.
Ferguson audited the roughly 5,100 buildings that city inspectors were assigned to inspect elevators, and found that only 965 were actually inspected, reported Crain’s Chicago Business. Furthermore, “when problems were found in inspections conducted by city personnel, they often were not fixed in a timely manner, again according to city records.”
Read the court decisionRead the full story...Reprinted courtesy of
California Case Adds Difficulties for Contractors & Material Suppliers
August 20, 2014 —
Beverley BevenFlorez-CDJ STAFFGarret Murai in his California Law Blog declared that “things just got a lot tougher for contractors and material suppliers in the Golden State.” In his blog, Murai analyzed the recent case Golden State Boring & Pipe Jacking, Inc. v. Eastern Municipal Water District, Case No. E054618 (July 23, 2014), in which “the California Court of Appeals for the Fourth Appellate District found that a subcontractor’s public works payment bond claim was time barred because its stop payment notice was served ‘before’ a notice of completion was recorded.”
Murai explained the importance of the ruling and how it changed the status quo: “Whereas before, it was commonly understood that you could serve a stop payment notice ‘during’ construction (after all, that was the point wasn’t it, to stop construction funds before they are paid out), now you may have only have a 30 day window (probably less) to serve a stop notice within 30 days after a notice of completion or notice of cessation is recorded.”
Read the court decisionRead the full story...Reprinted courtesy of
Minimum Wage on Federal Construction Projects is $10.10
November 26, 2014 —
Craig Martin – Construction Contractor AdvisorThe Department of Labor issued its final regulations to implement President Obama’s Executive Order raising the minimum wage to $10.10 per hour for workers on federal construction projects. The new minimum wage will not be effective until January 1, 2015, and will apply to most workers and most federal projects.
Covered Contracts
Executive Order 13658 applies to four major categories of contractual agreements:
- procurement contracts for construction covered by the Davis-Bacon Act (DBA) that exceed $2,000;
- service contracts covered by the Service Contract Act (SCA) that exceed $2,500;
- concessions contracts, including any concessions contract excluded from the SCA by the Department of Labor’s regulations at 29 CFR 4.133(b); and
- contracts in connection with Federal property or lands and related to offering services for Federal employees, their dependents, or the general public.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Exact Dates Not Needed for Construction Defect Insurance Claim
March 01, 2012 —
CDJ STAFFThe Texas Court of Appeals reversed the decision of the trial court in Vines-Herrin Custom Homes v Great American Lloyds Insurance Company on December 21, 2011. Vines-Herrin Custom Homes built a single-family home in Plano, Texas in 1999. They obtained a commercial general liability policy from Great American, later purchasing coverage from Mid-Continent, which the decision describes as “a sister company of Great American.”
While the home was under construction, Emil G. Cerullo sought to purchase it. At the time, it was under contract to another buyer. Two months later, Vines-Herrin told Cerullo that the deal had “fell through.” Cerullo bought the house with modifications from the original plan. Upon moving in, Cerullo began having water intrusion and other problems. “Cerullo noticed water gathering on window sills and damage to the sheetrock and baseboard.” Additional problems followed, including cracks, leaks, “and in early 2002, the ceiling and roof began to sag.”
Cerullo sued Vines-Herrin, claiming negligent construction. Vines-Herrin filed a claim seeking defense and indemnification under the insurance policies. Coverage was denied and Vines-Herrin filed suit to require coverage and also bringing claims for “breach of the duty of good faith and fair dealing, breach of contract, and DTPA and insurance code violations.”
In May, 2006 Vines-Herrin stated that it had no more defense funds and went into arbitration with Cerullo. The underlying construction defect action was settled for about $2.5 million. As part of the settlement, “Cerullo became the rightful owner of all remaining claims, rights, and causes of action against” Vines-Herrin’s insurers. He then joined the coverage lawsuit.
The non-jury trial was held under the controlling law of the time which “imposed a duty to defend only if the property damage manifested or became apparent during the policy period.” The court concluded in Cerullo’s favor. During the post-judgment motions, the Texas Supreme Court rejected the manifestation rule. Under this ruling, the trial court set aside its judgment and found in favor of the insurance companies. The trial court noted that although “the Residence was covered by an uninterrupted period of insurance (which began before the Residence was constructed) and that the damages to the Residence manifested during the uninterrupted period of insurance coverage,” “Mr. Cerullo failed to allege the date when actual physical damage to the property occurred.”
The first claim by Cerullo and Vines-Herrin was that the “Final Judgment” occurred in October 2004, and that all proceedings thereafter were void. The court rejected this as the “final judgment” is not “final for the purposes of an appeal unless it actually disposes of every pending claim and party or unless it clearly and unequivocally states that it finally disposes of all claims and all parties.” Despite the use of the word “final,” the trial court’s decision did not do this.
The second issue was the application of the Texas Supreme Court case Don’s Building Supply Inc. v. OneBeacon Insurance. In this case, framing rot due to defective stucco was not discovered until after the end of the policy period. The Supreme Court noted that “the key date is when injury happens, not when someone happens on it.”
The appeals court found that the trial court misapplied the Don’s Building Supply decision. Rather than an exact date, “so long as that damage occurred within the policy period, coverage was provided.” The appeals court noted that “Cerullo alleged the house was constructed in 1999 and he purchased it in May 2000.” “By April of 2001, Cerullo noticed that the windowsills in the study were showing signs of leakage and water damage.” As the court put it, “the petitions then alleged a litany of defects.”
The court noted that coverage by Great American was in effect from November 9, 1999 to November 9, 2000. In May of 2000, the house suffered “substantial flooding from a rainstorm that caused damage.” This was during the policy period. “As a matter of law, actual damages must occur no later than when they manifest.”
The court concluded that as damage manifested during the period of coverage, so must have the damage. The court ruled that “contrary to the trial court’s determination otherwise, the evidence showed Great American’s duty to indemnify was triggered, and expert testimony establishing the exact date of injury was not required to trigger the duty.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
After Restoring Power in North Carolina, Contractor Faces Many Claims
August 10, 2017 —
Jim Parsons - Engineering News-RecordHaving successfully helped to restore power to two North Carolina barrier islands, PCL Civil Constructors now faces the fallout from a July 27 construction incident that forced a week-long evacuation of 60,000 visitors, putting a potential multimillion-dollar dent in the region’s tourism-dependent economy.
Read the court decisionRead the full story...Reprinted courtesy of
Jim Parsons, ENRENR may be contacted at
ENR.com@bnpmedia.com
Real Estate & Construction News Roundup (05/17/23) – A Flop in Flipping, Plastic Microbes and Psychological Hard Hats
May 29, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, we look at a downturn in home-flipping and a continuing overabundance of commercial office space, plus psychological support for construction workers and surging demand for industrial space materials.
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Brazil Builder Bondholders Burned by Bribery Allegations
October 22, 2014 —
Paula Sambo and Sabrina Valle – BloombergBrazil’s biggest construction companies are leaving bondholders with losses in the wake of allegations they bribed Petroleo Brasileiro SA to win contracts.
Queiroz Galvao SA’s $700 million of notes due 2019 have dropped 2.5 percent since Oct. 9, when the Department of Justice made available video in which former Petrobras head of refining Paulo Roberto Costa alleged that builders formed a cartel to overcharge for projects and divert money to politicians. OAS SA’s $875 million of 2019 notes have slumped 1.9 percent in that span, versus a 0.1 percent loss for emerging markets.
Ms. Sambo may be contacted at psambo@bloomberg.net; Ms. Valle may be contacted at svalle@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Paula Sambo and Sabrina Valle, Bloomberg
Engineer Pauses Fix of 'Sinking' Millennium Tower in San Francisco
September 13, 2021 —
Richard Korman - Engineering News-RecordEngineers paused work for at least two weeks on the $100-million foundation upgrade for San Francisco's 645-ft-tall Millennium Tower high-rise residential condominium after measurements showed increased settlement during the installation of pile casings for the new piles.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of