Is The Enforceability Of A No-Damage-For-Delay Provision Inappropriate For Summary Judgment
February 24, 2020 —
David Adelstein - Florida Construction Legal UpdatesIs the enforceability of a no-damage-for-delay provision inappropriate for resolution on a summary judgment? The recent decision in U.S. f/u/b/o Kingston Environmental Services, Inc. v. David Boland, Inc., 2019 WL 6178676 (D. Hawaii 2019), dealing with Florida law, suggests that it is inappropriate for a summary judgment resolution, particularly when there is a right to a jury trial.
In this case, a prime contractor was hired on a federal construction project in Hawaii. The prime contractor hired a subcontractor and the subcontractor sued the prime contractor and its surety under the Miller Act. Of interest, the subcontractor was seeking to recover for the costs it incurred due to construction delays. The prime contractor moved for summary judgment as to the no-damage-for-delay provision in the subcontract. The no-damages-for-delay provision read as follows (and it is a well-written no-damage-for-delay provision):
The Subcontractor expressly agrees that the Contractor shall not be liable to the Subcontractor for any damages or additional costs, whether foreseeable or unforeseeable, resulting in whole or in part from a delay, hindrance, suspension, or acceleration of the commencement or execution of the Work, caused in whole or in part by the acts or omissions, whether negligent or not, of the Contractor including other subcontractors or material suppliers to the Project, its agents, employees, or third parties acting on behalf of the Contractor. The Subcontractor’s sole remedy for any such delay, hindrance, suspension, or acceleration shall be a noncompensable time extension.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Recovering Unabsorbed Home Office Overhead Due to Delay
May 30, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn the
preceding article, I discussed the use of a retrospective as-built delay analysis in a case before the Civilian Board of Contract Appeals (CBCA). This case also discussed a damages component in certain delay claims known as unabsorbed home office overhead—a challenging damages component to recover because this deals with indirect costs as opposed to direct costs.
Unabsorbed home office overhead is a damages component when the contractor is on standby, but this is NOT as easy as just claiming standby thereby you are automatically entitled to unabsorbed home office overhead. There are requirements that MUST be met.
To obtain an equitable adjustment for unabsorbed home office overhead as compensation for being on standby, [the contractor] must initially show “[1] a government-caused delay of uncertain duration,” that “[2] the delay extended the original time for performance” or precluded the contractor from finishing earlier than scheduled, and that “[3] the contractor [was] on standby and unable to take on other work during the delay period.
CTA I, LLC v. Department of Veteran Affairs, CBCA 5826, 2022 WL 884710 (CBCA 2022) quoting Nicon, Inc. v. U.S., 331 F.3d 878, 883 (Fed. Cir. 2003).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Not So Unambiguous: California Court of Appeal Finds Coverage for Additional Insured
October 11, 2017 —
Malcom Ranger-Murdock - Saxe Doernberger & Vita, P.C.California’s Fourth District Court of Appeal recently determined that manuscript additional insured endorsements (AIEs), which purportedly provided coverage for ongoing operations only, were ambiguous. The court also found the insurer that issued the policies, American Safety Indemnity Co. (American Safety), acted in bad faith due to its systematic efforts to deny coverage to general contractors as additional insureds.
In Pulte Home Corp. v. American Safety Indemnity Co.,1 Pulte Home Corporation (Pulte Home), a general contractor, sued American Safety for failure to defend Pulte Home as an additional insured in connection with two underlying construction defect lawsuits. American Safety contended that it did not have a duty to defend Pulte Home because the loss occurred after the construction project was complete and the applicable AIEs did not provide coverage for completed operations, and/or because the policy’s faulty workmanship exclusions applied. The trial court awarded $1.4 million in compensatory and punitive damages to Pulte Home, and American Safety appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Malcom Ranger-Murdock, Saxe Doernberger & Vita, P.C.Mr. Ranger-Murdock may be contacted at
mrm@sdvlaw.com
Regional US Airports Are Back After Years of Decay
September 23, 2024 —
Lebawit Lily Girma - BloombergThe ski resorts near Gunnison and Crested Butte, Colorado, are so close to Aspen, you’d think the area wouldn’t need its own airport. Their glitzier neighbor is just 48 miles north as the crow flies, though that’s roughly 150 miles by road.
But people flocking to Crested Butte’s laid back town, extreme ski slopes and epic mountain biking have a new reason to bypass farther-away Aspen: the destination’s gleaming new airport, which debuted in January 2023.
Not only is the Gunnison-Crested Butte Regional Airport terminal easy to get across quickly, at just 40,000 square feet, it's also heated and cooled with geothermal energy and uses triple glazed windows to keep travelers warm in a town known to be one of the coldest places in the US.
And Crested Butte isn’t the only small town airport receiving an upgrade.
All across the US, at least a dozen small and medium-size facilities are being renovated and, in some cases, entirely rebuilt—typically on budgets that stretch eight and nine figures. That contradicts a long-held belief among aviation industry pros that these regional facilities were destined to gather dust and die out.
Read the court decisionRead the full story...Reprinted courtesy of
Lebawit Lily Girma, Bloomberg
Manufacturer of Asbestos-Free Product May Still Be Liable for Asbestos Related Injuries
July 30, 2015 —
Kristian B. Moriarty, R. Bryan Martin and Lee Marshall – Haight Brown & Bonesteel LLPIn Sherman v. Hennessy Industries, Inc. (No. B252566, filed June 18, 2015), the Court of Appeal, Second District, reversed a trial court’s grant of summary judgment in favor of a manufacturer of a brake grinding machine. The Court cited an exception to the general rule that manufacturers may not be held liable, under a strict products liability theory, where the plaintiff’s injuries arise from other products that are used in conjunction with the defendant’s product.
Plaintiff and appellant, Michael Sherman, was an automobile mechanic from 1962 to 1977. Mr. Sherman alleged that during this period he used an arcing machine, which abraded brake linings by means of sand paper moving at high speeds. Sherman alleged the machine released asbestos dust, which he then brought home, exposing his wife Debra Sherman to asbestos. Ms. Sherman developed mesothelioma and passed away from exposure to the asbestos dust carried home by her husband.
Reprinted courtesy of
Kristian B. Moriarty,
R. Bryan Martin and
Lee Marshall of Haight Brown & Bonesteel LLP
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Mr. Martin may be contacted at bmartin@hbblaw.com
Mr. Marshall may be contacted at lmarshall@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Five-Year Statute of Limitations on Performance-Type Surety Bonds
December 01, 2017 —
David Adelstein - Florida Construction Legal UpdatesThe statute of limitations on a claim against a performance-type bond is 5 years from the breach of the bond, i.e., the bond-principal’s default (based on the same statute of limitations that governs written contracts / obligations). See Fla. Stat. s. 95.11(2)(b). This 5-year statute of limitations is NOT extended and does NOT commence when the surety denies the claim. It commences upon the default of the bond-principal, which would be the act constituting the breach of the bond. This does not mean that the statute of limitations starts when a latent defect is discovered. This is not the case. In dealing with a completed project, the five-year statute of limitations would run when the obligee (beneficiary of the bond) accepted the work. See Federal Insurance Co. v. Southwest Florida Retirement Center, Inc., 707 So.2d 1119, 1121-22 (Fla. 1998).
This 5-year statute of limitations on performance-type surety bonds has recently been explained by the Second District in Lexicon Ins. Co. v. City of Cape Coral, Florida, 42 Fla. L. Weekly D2521a (Fla. 2d DCA 2017), a case where a developer planned on developing a single-family subdivision.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Colorado Introduces Construction Defect Bill for Commuter Communities
January 23, 2013 —
CDJ STAFFA Colorado State Senator has introduced a bill suggesting a change to the way that construction defect claims are handled in "transit-oriented developments." And what are these? According to the bill these are "any multi-family residential or mixed-use project within one-half mile of any commuter rail stop, commuter light rail stop, or commuter bus stop." So the bill would treat homes with good public transportation differently from those not so convenient to public transportation.
The bill, SB 52, would institute a right to repair for construction defects in these developments. Construction defect claims would be referred to binding arbitration. Further, construction professionals could not be sued for environmental conditions related to transit, commercial, public, or retail use.
Read the court decisionRead the full story...Reprinted courtesy of
Liquidated Damages Clause Not Enforced
October 02, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPA liquidated-damages clause was not enforced in a recent case before the Georgia Court of Appeals. The clause did not contain standard provisions that would normally allow a trial court to enforce the clause as written. As a result, the trial court looked beyond the contract to determine whether the City satisfied the requirements for enforcement of the liquidated-damages clause. Below are the relevant excerpts.
City of Brookhaven v. Multiplex, LLC, A23A0843, 2023 WL 4779591 (Ga. Ct. App. July 27, 2023)
Here, the Contract provides for “Liquidated Damages at the rate of $1,000.00 per calendar day” in the last paragraph of the Scope of Work addendum. The Contract lacks, however, any language indicating that the liquidated damages were not intended to be a penalty. See Fuqua Const. Co. v. Pillar Dev., Inc., 293 Ga. App. 462, 466, 667 S.E.2d 633 (2008) (rejecting use of parol evidence where the parties “explicitly agreed” in “unambiguous contract language” that the liquidated damages were not a penalty). Absent such language, the court can look to parol evidence in the record to determine the effect the provision was intended to have. See J.P. Carey Enterprises, 361 Ga. App. at 391-392 (1) (b), 864 S.E.2d 588 (looking to “extrinsic evidence” such as emails, documents, and deposition testimony to determine whether the damages provision at issue was a penalty); see also Gwinnett Clinic, Ltd. v. Boaten, 340 Ga. App. 598, 602-603, 798 S.E.2d 110 (2017) (“Shah’s testimony also suggested that one purpose of the liquidated damages provision was to deter employees from breaching the agreement”).
Read the court decisionRead the full story...Reprinted courtesy of