Will the Hidden Cracks in the Bay Bridge Cause Problems During an Earthquake?
June 26, 2014 —
Beverley BevenFlorez-CDJ STAFFDespite a “no cracks” welding code and contract provision for the San Francisco-Oakland Bay Bridge, in 2008 Caltrans proceeded with the project despite welding cracks created by the Chinese firm hired to build the roadway, according to the Sacramento Bee. By the time the cracks had been discovered, the costs were at $6.5 billion and climbing, and fixing the cracks would be time-consuming and expensive.
However, there is some dispute as to rather the welding “cracks represent a hazard to the traveling public.”
“Examine history,” Brian Maroney, Caltrans’ chief engineer for the bridge, said in a recent interview by the Sacramento Bee. “… Caltrans reviewed major quakes around the globe and never found a case in which weld cracks caused bridge-roadway fractures.”
However, the Sacramento Bee reported that there was a case where welding cracks led to fractures. For instance, after the southern California earthquake in 1994 centered in Northridge, the Santa Clara River Bridge “suffered several fractures in steel girders. The breaks were traced to tiny cracks in welds, likely present before the quake, and worsened by vibrations of heavy trucks passing overhead. When the quake struck, the girders fractured.”
The Santa Clara bridge did not collapse. Sacramento Bee claimed it remained standing because the I-beam-shaped girders were “not fracture-critical.” However, the Bay Bridge’s “roadway consists of box-girder segments welded together. In effect, they create one contiguous, fracture-critical girder,” Abolhassan Astaneh-Asl, UC Berkeley engineering professor told the Sacramento Bee. “If welds crack and grow rapidly during a large quake, the entire roadway could fail.”
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: A Poultry Defense, a Houston Highway and a CERCLA Consent Decree that Won’t Budge
March 22, 2021 —
Anthony B. Cavender - Gravel2GavelFebruary saw the usual array of significant environmental decisions and federal regulatory notices.
THE FEDERAL COURTS
U.S. Court of Appeals for the District of Columbia
Luminant Generation v. EPA
The court will be grappling with a difficult venue case governed by the Clean Air Act (42 USC Section 7607(b)). In 2013, the U.S. Court of Appeals for the Fifth Circuit decided the case of Luminant Generation v. EPA (714 F. 3d 841), in which the court upheld the affirmative defenses that were made part of the Texas State Implementation Plan (SIP) and which applied to certain unpermitted emissions from regulated sources during periods of startup, shutdown or malfunction. These defenses were challenged in the Fifth Circuit and were rejected. On the national stage, EPA has been involved in litigation over these affirmative defenses and recently excluded from a “SIP Call” the Texas program, which was carved out. This EPA decision is being challenged in the DC Circuit (see Case number 20-1115),with the State of Texas arguing as an intervenor that any issues involving Texas belong in the Fifth Circuit, and not in the DC Circuit because the Act allows regional issues to be decided in the regional federal courts.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Real Estate & Construction News Roundup (05/23/23) – Distressed Prices, Carbon Removal and Climate Change
June 05, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn this week’s roundup, we consider distressed property bonds and loans, cities that are sinking under their own skyscrapers, efforts to lower carbon emissions, the unexpected potential of dirty diapers as a building material, and so much more.
Globally, more than $190 billion of property bonds and loans are
trading at distressed prices, a result of China’s real estate woes. (
Alice Huang and
Erin Hudson, Bloomberg)
PacWest Bancorp sees a stock market boost as it announces the sale of its
real estate loans, valued at around $2.6 billion. (
Jaiveer Shekhawat and
Chibuike Oguh, Reuters)
New construction home sales
exceeded expectations for April while existing home sales dropped. (
Anna Bahney, CNN)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
“Wait! Do You Have All Your Ducks in a Row?” Filing of a Certificate of Merit in Conjunction With a Complaint
January 13, 2020 —
Rahul Gogineni - The Subrogation StrategistIn Barrett v. Berry Contr. L.P., No. 13-18-00498-CV, 2019 Tex. LEXIS 8811, the Thirteenth District Court of Appeals of Texas considered, among other things, the procedural timing requirements of filing a certificate of merit in conjunction with a complaint. The court concluded that the proper reading of the statute requires a plaintiff to file a certificate of merit with the first complaint naming the defendant as a party.
In Barrett, after sustaining injuries while working at a refinery, David Barrett (Barrett) filed suit against Berry Contracting, LP and Elite Piping & Civil, Ltd. on July 6, 2016. In Barrett’s first amended complaint, which he filed on August 23, 2016, Barrett added Govind Development, LLC (Govind) as another defendant. Barrett subsequently filed a second amended complaint (omitting Govind) and, on December 27, 2017, shortly before the statute of limitations ran, a third amended complaint (reasserting claims against Govind). On January 28, 2018, after the statute of limitations period ran, Barrett filed a certificate of merit. Govind filed a motion to dismiss the claim, asserting that Barrett violated the statute that required a certificate of merit to be filed with the complaint, Tex. Civ. Prac & Rem. Code §150.002.
Tex. Civ. Prac. & Rem. Code §150.002(a) states,
In any action or arbitration proceeding for damages arising out of the provision of professional services by a licensed or registered professional, a claimant shall be required to file with the complaint an affidavit of a third-party licensed architect, licensed professional engineer, registered landscape architect or registered professional land surveyor…
Read the court decisionRead the full story...Reprinted courtesy of
Rahul Gogineni, White and Williams LLPMr. Gogineni may be contacted at
goginenir@whiteandwilliams.com
Construction Law Advisory: Mechanical Contractor Scores Victory in Prevailing Wage Dispute
September 03, 2014 —
Steven M. Cvitanovic & Jessica M. Lassere Ryland - Haight Brown & Bonesteel LLPOn August 27, 2014, the First District Court of Appeal weighed in on whether prevailing wages are required for public contracts in situations where work is performed in furtherance of the project but at a permanent offsite manufacturing facility that is not exclusively dedicated to the project. In Sheet Metal Workers' International Association, Local 401 v. John C. Duncan and Russ Will Mechanical, the project at issue was for a community college district where Russ Will was the HVAC subcontractor. The contract documents required contractors to pay prevailing wages but they did not limit where or how Russ Will would fabricate sheet metal required for the job. Russ Will used its existing fabrication facility to form the sheet metal.
An employee of Russ Will filed a complaint with the DIR alleging he should have been paid prevailing wages for work related to the project. The worker fabricated sheet metal for the project but at Russ Will’s Hayward facility, not at the site. The DIR issued a coverage determination in which it concluded that Russ Will was required to pay prevailing wages for the offsite fabrication work associated with the project. The DIR's determination turned on whether Russ Will was exempt from the prevailing wage law as a material supplier. To qualify for the material supplier exemption, the employer must sell supplies to the general public and its fabrication or manufacturing facility must not be established for the particular public works contract or be located at the site of the public work.
Following the DIR determination, Rush Will filed an administrative appeal. The department reversed its initial coverage determination, concluding that the offsite fabrication performed by Russ Will was not subject to the prevailing wage law.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Jessica M. Lassere Ryland, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Ryland may be contacted at jlassere@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Appropriation Bill Cuts Military Construction Spending
June 15, 2011 —
CDJ STAFFThe Hill reports that HR 2055, the Military Construction, Veterans Affairs (VA) and Related Agencies bill, has passed with only five votes in opposition. The bill cuts the budget for military construction spending by $2.6 billion due to anticipated base closures.
The bill includes $186 million for family housing construction by the Army, $100 million for family housing construction by the Navy and Marines, and $84 million for family construction by the Air Force, with an additional $50 million allocated for the DOD outside the military branches. By the act, these funds will remain available until September 30, 2016.
Read the full story…
Read HR 2055
Read the court decisionRead the full story...Reprinted courtesy of
Wilke Fleury Celebrates the Addition of Two New Partners
February 18, 2019 —
Wilke FleuryWilke Fleury celebrates the addition of two new partners – Shannon Smith-Crowley and Daniel J. Foster – who complement the firm’s shifting generations of leadership. Shannon and Danny bring unique perspective and excellent capability to Wilke Fleury’s partnership effective January 1, 2019.
Shannon has been a registered lobbyist in California for 20 years. After a career in managed care, she started lobbying with the California Medical Association before founding her own firm, Partners In Advocacy to specialize in medical and reproductive health advocacy. At Wilke Fleury, her areas of practice include health care, women’s equity, life sciences, the biomedical industry, new family formation and emerging technologies in green energy. After a four year tenure with the firm, she has been elevated to the partnership.
Click here to read more about Shannon Smith-Crowley.
Daniel Foster’s litigation practice is composed of matters involving complex construction defect litigation, mechanics liens claims, stop notice actions and Miller Act claims. He represents clients before the Contractors State License Board and handles matters involving breach of warranty, the Song-Beverly Consumer Warranty Act, indemnity agreements and liability insurance coverage.
Click here to read more about Daniel J. Foster Read the court decisionRead the full story...Reprinted courtesy of
Wilke Fleury
Albert Reichmann, Builder of NY, London Finance Hubs, Dies at 93
January 17, 2023 —
Laurence Arnold - BloombergAlbert Reichmann, the longtime president of his family’s Olympia & York Developments Ltd., builder of the World Financial Center in New York and the first phase of Canary Wharf in London, has died. He was 93.
He died on Dec. 17, according to the National Post and a notice on the website of Steeles Memorial Chapel, a Toronto-area funeral home.
As the eldest of the three Orthodox Jewish brothers behind Olympia & York, Reichmann held the title of president. In practice, his brother Paul — who died in 2013 — was the company’s “idea man and deal-doer,” in the words of Anthony Bianco, a former Businessweek writer whose book on the family called Olympia & York “the greatest property development company in Western history.”
Before its 1992 bankruptcy, it was the largest private owner of commercial property in New York City.
Forbes magazine calculated the brothers’ cumulative net worth at $9.2 billion at its height in 1988, making them among the world’s richest people.
Read the court decisionRead the full story...Reprinted courtesy of
Laurence Arnold, Bloomberg