CDJ STAFFConstruction defect claims can be an avoidable headache, if builders apply some forethought. Mark J. Peschel of Johnson & Lindberg, a Bloomington, Minnesota law firm, points out that simply says that windows should be weatherproofed by appropriate flashing, without any guidance on accomplishing that. He notes that “builders tend not to know the weatherproofing code provisions as well as they should.” Another lawyer, Eric S. Hayes of Brown and Carlson in St. Louis Park extends this, “it’s not just the building codes that need to be followed, but also the standards in the industry.”
Hayes notes that another way builders can avoid headaches is by being proactive. “I often hear, once things have gone sour and moved toward litigation, that the homeowner contacted the contractor a dozen times about a leaking basement and nothing was done, so they were forced to sue.” His advice for builders: “Don’t let it fester.”
Read the court decisionRead the full story...Reprinted courtesy of
Avoid Delay or Get Ready to Pay: The Risks of “Time-Is-of-The-Essence” Clauses
August 29, 2018 —
Stephen Orlando - Gordon & Rees Construction Law BlogLike death and taxes, construction delays are inevitable. Even the most cautious, diligent contractor may face subcontractor disputes, supply shortages, or inclement weather which slows down a project. Even if the contractor avoids unexpected problems, the sheer complexity of a job may cause a contractor to exceed the deadlines proposed in a contract.
Fortunately, courts recognize the practical reality of construction projects and the unavoidable delays which may arise. Therefore, as a general rule, a contractor is only liable for delayed completion of a project if the delay resulted from the contractor’s unreasonable performance of his or her work. Reasonable performance will typically serve as a defense to a claim of delayed completion. This defense is a vital asset when a contractor surpasses the project’s expected timeframe.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen Orlando, Gordon & Rees Scully Mansukhani
Can a Receiver Prime and Strip Liens Against Real Property?
September 20, 2021 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogCourts overseeing receivers generally enjoy broad discretion in directing and approving a receiver’s proposed actions. But does that authority extend to a receiver not only granting a super-priority lien ahead of existing liens, but also selling the real property free and clear of all liens? In County of Sonoma v. Quail, 56 Cal.App.5th 657 (Ct. App. 2020), the California Court of Appeals answered that question in the affirmative.
Quail involved a 47,480 square-foot lot with two houses, a few garages, several outbuildings, and numerous trailers surrounded by a veritable junk yard. Despite many of these structures being uninhabitable, unsanitary, and dangerous, multiple families resided on the lot. Although Sonoma County (the “County”) ordered the owner to remediate the property several times, he failed and refused to do so. After several years of these violations going unabated, the County ultimately sought and obtained the appointment of a receiver over the real property.
To obtain funds necessary to repair the property, the receiver asked the court for permission to borrow money through the issuance of a receivership certificate to be secured by a super-priority lien—i.e., a lien ahead of all other liens—against the real property. Although the trial court initially declined to prime existing liens, when the receiver could find no one to lend money (since the land lacked equity), the trial court relented and approved a super-priority lien despite the senior secured lender’s objection (the “lender”).
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
Claim Against Broker for Failure to Procure Adequate Coverage Survives Summary Judgment
April 15, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe broker's motion for summary judgment, seeking to dismiss negligence claims for failure to obtain adequate coverage, was denied by the court in Voss v. The Netherlands Ins. Co., 2014 N.Y. LEXIS 384 (N.Y. Ct. App. Feb. 25, 2014).
The insured met with a representative of CH Insurance Brokerage Services Co., Inc. (CHI) to discuss coverage for the premises and her two companies. At CHI's request, the insured shared information on sales figures for calculating business interruption coverage. The broker represented that CHI would reassess and revisit the coverage needs as her business grew.
CHI recommended $75,000 per incident in coverage for business interruption losses. The insured questioned whether the $75,000 limit was adequate, but the broker assured her that it was sufficient. The insured then accepted the recommendation. Subsequently, the insured's business grew, but CHI renewed the policy with the same $75,000 business interruption limit.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
What to do about California’s Defect-Ridden Board of Equalization Building
October 01, 2014 —
Beverley BevenFlorez-CDJ STAFFJerry Brown recently signed into law a bill requiring the state of California “to assess its properties in the Sacramento area and develop long-term plans for renovating, replacing or selling the most troublesome buildings,” according to SF Gate. Some say the Board of Equalization building, which was built for $80 million and then repaired for $60 million has construction defects, is “jeopardizing the health and safety of public employees.”
Current problems include “[f]looding, mold, falling windows and free-falling elevators,” reported SF Gate. Furthermore, recently, “three employees filed a $75 million lawsuit against the state, alleging toxic mold in the building is causing extreme fatigue, skin rashes, persistent flu-like symptoms, respiratory illnesses, frequent headaches, memory lapses and fears of cancer.”
“This is a disaster,” Assemblyman Roger Dickinson, D-Sacramento, who authored the bill regarding assessing state capitol buildings, told SF Gate. “It endangers the health and safety of employees and the public alike. And it is costing state taxpayers tens of millions of dollars.”
Read the court decisionRead the full story...Reprinted courtesy of
Should CGL Insurer have Duty to Defend Insured During Chapter 558 Notice of Construction Defects Process???
September 01, 2016 —
David Adelstein – Florida Construction Legal UpdatesDoes a CGL insurer have a duty to defend its insured-contractor during Florida Statutes Chapter 558 notice of construction defects pre-suit process? This answer is currently undecided and will be up to the Florida Supreme Court to decide. (It is on appeal stemming from a federal district court saying that an insurer does not have a duty to defend its insured-contractor in the 558 process based on the definition of the word “suit” in the CGL policy.)
Why is this an important issue?
The 558 pre-suit notice of construction defects process is designed to facilitate an avenue for construction defect lawsuits to get resolved without having to file a lawsuit or, at least, have issues narrowed before a lawsuit needs to be filed. (Check here for a summary of the 558 process.) It requires pre-suit notifications so that implicated parties can become aware of the defects and have an opportunity to inspect the defects / damage, test the defects / damage, and respond to the notice of construction defects; it provides an avenue for beneficial pre-suit discovery. Through participating in the 558 process, the contractor and/or design professional (and those downstream from them) can: (i) offer to remedy the defect, (ii) settle the defect, whether through money or a combination of money and repairs, (iii) dispute the defect, or (iv) advise that available insurance proceeds will be determined by its liability insurer. See Fla. Stat. s. 558.004.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
New York’s Highest Court Weighs in on N.Y. Labor Law
September 23, 2024 —
Bill Wilson - Construction Law ZoneN.Y. Labor Law § 241(6) requires owners and contractors to provide reasonable and adequate protection and safety to persons employed at or lawfully frequenting a construction site. If a worker is injured on a construction site and establishes a violation of a specific and applicable Industrial Code regulation, both the owner and contractor will be held vicariously liable for the worker’s injury, without regard to their fault and even in the absence of control or supervision of the worksite. The Court of Appeals of New York recently addressed the broad scope of the Labor Law in the context of slipping hazards.
In Bazdaric v. Almah Partners, LLC, 41 N.Y.3d 310 (2024), the plaintiff, an injured painter, slipped and fell on a plastic covering placed over an escalator in an area he was assigned to paint. The plaintiff claimed that the plastic covering was a foreign substance for purposes of Industrial Code 12 NYCRR 23-1.7(d) because it was not part of the escalator. Industrial Code 12 NYCRR 23-1.7(d) states:
Slipping hazards. Employers shall not suffer or permit any employee to use a floor, passageway, walkway, scaffold, platform or other elevated working surface which is in a slippery condition. Ice, snow, water, grease and any other foreign substance which may cause slippery footing shall be removed, sanded or covered to provide safe footing.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
UPDATE: Texas Federal Court Permanently Enjoins U.S. Department of Labor “Persuader Rule” Requiring Law Firms and Other Consultants to Disclose Work Performed for Employers on Union Organization Efforts
December 08, 2016 —
Aaron C. Schlesinger & Gregory R. Begg – Peckar & Abramson, P.C.As an update to our prior alert, on November 16, 2016, a federal judge in Texas issued a permanent injunction blocking the U.S. Department of Labor’s (“DOL”) “persuader rule” – a preliminary injunction had been granted this past June.
In rendering the permanent injunction, the court adopted the reasoning of its prior June 27, 2016 decision that granted a nationwide preliminary injunction on the rule. In the earlier decision, the court held that a temporary injunction was appropriate because the parties challenging the rule were likely to succeed on the merits of their claim […].
Reprinted courtesy of
Aaron C. Schlesinger, Peckar & Abramson, P.C. and
Gregory R. Begg, Peckar & Abramson, P.C.
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Mr. Begg may be contacted at gbegg@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of