New WA Law Caps Retainage on Private Projects at 5%
May 29, 2023 —
Brett M. Hill & Ryanne S. Mathisen - Ahlers Cressman & Sleight PLLCThis month, Governor Jay Inslee signed into law a new statute that caps retainage on private construction projects to five percent (5%), provides a mechanism for subcontractors to get paid their retainage prior to project completion, and allows for contractors and subcontractors to post a retainage bond and get paid their retainage early. For those interested in reading the full text of this new law, the statute can be found
here.
The new statute goes into effect on July 23, 2023. Under the statute, when a contractor or subcontractor considers their work under a contract subject to retainage complete, they may notify the party they contracted to perform the work for. Within 15 days of receiving the notice of completion of work, the party receiving the notice must respond with either (1) notice of acceptance of work or (2) notice of uncompleted items to the contractor or subcontractor.
If the party receiving notice does not provide notice of uncompleted items within 15 days or fails to respond to the notice of completion entirely, the unpaid retainage will begin to accrue interest at a rate of one percent (1%) per month, 30 days after the initial 15-day period. However, this interest will not accrue against a contractor who has not been paid the retainage by an upper-tier contractor or owner until payment has been received, so long as that contractor has submitted its subcontractor’s notice of completion to the upper-tier contractor or owner within 30 days of receipt.
Reprinted courtesy of
Brett M. Hill, Ahlers Cressman & Sleight PLLC and
Ryanne S. Mathisen, Ahlers Cressman & Sleight PLLC
Mr. Hill may be contacted at brett.hill@acslawyers.com
Ms. Mathisen may be contacted at ryanne.mathisen@acslawyers.com
Read the court decisionRead the full story...Reprinted courtesy of
Rhode Island Finds Pollution Exclusion Ambiguous, Orders Coverage for Home Heating Oil Leak
March 06, 2023 —
Kayla S. O'Connor - Saxe Doernberger & Vita, P.C.The Rhode Island case of Regan Heating and Air Conditioning, Inc. v. Arbella Protection Insurance Company, Inc., et. al.1 provides much-needed guidance regarding ambiguity and the term “pollution.”
In Regan, the Rhode Island Supreme Court held that a pollution exclusion contained in the Plaintiff’s “Commercial Package Policy” was ambiguous as to whether home heating oil that escaped into a customer’s basement constituted a “pollutant” under the policy.
This case stems from a 2015 incident wherein Regan was in the process of removing an older heating system and installing a new heating system in a customer’s home when that customer discovered 170 gallons of home heating oil in his basement. The customer sued Regan, alleging negligence and demanding remediation for the property damage caused by the oil leak.
Read the court decisionRead the full story...Reprinted courtesy of
Kayla S. O'Connor, Saxe Doernberger & Vita, P.C.Ms. O'Connor may be contacted at
KOconnor@sdvlaw.com
Engineer TRC Fends Off Lawsuits After Merger
August 17, 2017 —
Scott Van Voorhis - Engineering News-RecordIn the wake of its merger with an investment fund, TRC Cos. has been busy swatting away pesky shareholder lawsuits driven by law firms who specialize in such litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, ENRENR may be contacted at
ENR.com@bnpmedia.com
Designers “Airpocalyspe” Creations
May 19, 2014 —
Beverley BevenFlorez-CDJ STAFFBlaine Brownell in Architect Magazine discussed how recently some designers have created items to deal with urban pollution, however, the creations themselves are more politically-charged than practical.
Brownell lists recent examples of architects and designers “perverse” creations: “Notable smog-inspired works include the Aegis Parka, a protective jacket created by Dutch design studio Nieuwe Heren; a palladium dichloride coat that changes color in the presence of carbon dioxide emissions and is designed by London-based artist Lauren Bowker; and R&Sie(n)’s ‘Dustyrelief’ building in Bangkok, designed to collect atmospheric dust via an electrostatically-charged facade.”
“Perhaps such proposals—and the disarming irony they conjure—will motivate the changes necessary to clean up our act,” Brownell concluded.
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Federal District Rejects Another Construction Defect Claim
November 30, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe Federal District Court, District of Hawaii, continued it long line of cases finding no coverage for claims of faulty workmanship. Nautilus Ins. Co. v. Summary Judgment RMB Enters., 2020 U.S. Dist. LEXIS 200468 (D. Haw. Oct. 28, 2020).
Property owners entered a construction contract with RMB Enterprises to develop and construct residential structures and a pond. The pond walls enclosed residential spaces, providing structural foundations for the walls of the building. After completion of the project, the pond leaked into its pump room. RMB performed remedial work by injecting epoxy into cracks. Later, water from the pondleaked into the interior of a residence near a staircase. Water also leaked into the master bedroom area causing musty odor, mood growth, and increased humidity.
The owners sued RMB asserting breach of contract, breach of warranty, misrepresentation, and negligence claims. Nautilus denied coverage. The policy provided that faulty workmanship did not constitute an "occurrence." But when faulty workmanship caused property damage to property other than "your work," then such property damage would be considered caused by an occurrence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
No Signature? Potentially No Problem for Sureties Enforcing a Bond’s Forum Selection Clause
March 21, 2022 —
Brian C. Padove - ConsensusDocsOne of the foundational tenets of contract law is that a party may only be bound by terms they agree to, or in other words, if the party did not sign a contract, that party cannot be bound by the terms thereof. While this principle is generally unwavering, there are certain situations in which a non-signatory to a contract may still be bound by the terms of a contract.
In particular, this non-signatory issue may arise when a payment bond claimant makes a bond claim, subsequently files a lawsuit, but the bond contains a forum selection clause different than the venue of the lawsuit and the surety seeks to enforce the bond’s forum selection clause. For example, the claimant may have filed its lawsuit against the surety in federal court, even though the bond provides language specifically mandating that no lawsuit shall be commenced by any claimant other than in a state court where the project is located. Thus, the question then becomes, can the surety enforce the forum selection clause against the claimant when the claimant did not sign the bond and/or never agreed to the terms thereof? The short answer, it depends (yes, that is a very lawyer-like answer). Given recent case law over the past decade, however, the surety has a strong argument in favor of enforcement of the forum selection clause.
Read the court decisionRead the full story...Reprinted courtesy of
Brian C. Padove, Watt, Tieder, Hoffar & Fitzgerald, LLP (ConsensusDocs)Mr. Padove may be contacted at
bpadove@watttieder.com
Update Regarding McMillin Albany LLC v. Super Ct.
April 28, 2016 —
Richard H. Glucksman and David A. Napper – Chapman Glucksman Dean Roeb & Barger In FocusThe construction industry continues to await the California Supreme Court's highly anticipated decision regarding McMillin Albany LLC v. Super Ct. 2015 F069370 (Cal.App.5 Dist.). The Supreme Court will attempt to resolve the conflict presented by the Fourth Appellate District Court's holding in Liberty Mut. Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98 and rejection of the same by the Fifth Appellate District Court in McMillin Albany. The issue is whether the Right to Repair Act (SB800) is the exclusive remedy for all defect claims arising out of new residential construction sold on or after January 1, 2013. CGDRB has been closely monitoring the progress of the case and understands that the real parties in interest have submitted their opening brief on the merits. The Court granted Petitioners a further and final extension to file the answer brief on the merits. The answer deadline is Monday April 25, 2016. Stay tuned.
Reprinted courtesy of
Richard H. Glucksman, Chapman Glucksman Dean Roeb & Barger and
David A. Napper, Chapman Glucksman Dean Roeb & Barger
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Federal Court of Appeals Signals an End to Project Labor Agreement Requirements Linked to Development Tax Credits
October 20, 2016 —
Gregory R. Begg & Aaron C. Schlesinger – Peckar & Abramson, P.C.What Action Should Owners, Developers and Contractors Take in Anticipation of Successful Challenges to PLA Requirements?
Recently, a federal court in New Jersey issued a decision which very well may invalidate all Project Labor Agreements (“PLA’s”) entered into as a condition to receipt of tax incentives for private development. Tax incentives utilized to promote private development are different, according to the court, than typical public works projects where PLA requirements have generally been held valid. Owners, developers, contractors and governmental entities must assess the consequences of this decision upon contracts already and to be awarded in the future where tax benefits may be linked to a PLA requirement.
In 1993, in what has become known as the Boston Harbor Case, the United States Supreme Court held that state and local governmental entities may condition the award of public works contracts on the contractor’s agreement to enter into PLA’s.
That decision has been followed nationwide since then to uphold the validity of various state and local law bidding conditions requiring successful bidders to negotiate and enter into project labor agreements as a condition to the award of public works contracts. The rationale is that when the government, like any other private party, is participating in an economic market, it may exercise its discretion in setting terms and conditions it believes best suit its interests in the efficient procurement of goods and services in that market. Therefore, a PLA requirement by a governmental entity engaged in market activity is no more or less valid than a PLA requirement on a purely private project.
Reprinted courtesy of
Gregory R. Begg, Peckar & Abramson, P.C. Aaron C. Schlesinger, Peckar & Abramson, P.C.
Mr. Begg may be contacted at gbegg@pecklaw.com
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of