Venue for Suing Public Payment Bond
June 15, 2017 —
David Adelstein - Florida Construction Legal UpdatesPublic payment bonds (excluding FDOT payment bonds) are governed under Florida statute s. 255.05. As it pertains to venue—the location to sue a public payment bond–the statute provides in relevant portion:
(5) In addition to the provisions of chapter 47, any action authorized under this section may be brought in the county in which the public building or public work is being construction or repaired.
***
(1)(e) Any provision in a payment bond…which restricts venue of any proceeding relating to such bond…is unenforceable.
Now, what happens if a subcontractor sues only a payment bond but its subcontract with the general contractor contains a mandatory venue provision? For example, what if the general contractor is located in Lee County and the subcontract contains a venue provision for Lee County, the project is located in Collier County, the subcontractor is located in Miami-Dade County, and the surety issues bonds in Miami-Dade County? Does venue have to be in Lee County per the mandatory venue provision?
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
How Are You Dealing with Material Delays / Supply Chain Impacts?
June 07, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn a prior article I discussed a material escalation provision in your construction contract to account for the volatility of the material price market. While including such a provision may not have been much of a forethought before, it is now!
What about concerns with the actual supply chain that impacts the availability of and the lead time of materials? How are you addressing this concern in your construction contract?
The pandemic has raised awareness to this issue as certain material availability has been impacted by the pandemic. As a result, parties in construction have tried to forecast those materials where delivery issues may occur including those materials with longer than expected lead times. But equally important is how this issue is being addressed in your construction contract including how you want to negotiate this risk in future construction contracts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
What is a Subordination Agreement?
May 06, 2019 —
Bremer Whyte Brown & O'Meara LLPPut simply, a subordination agreement is a legal agreement which establishes one debt as ranking behind another debt in the priority for collecting repayment from a debtor. It is an arrangement that alters the lien position. Without a subordination clause, loans take chronological priority which means that a deed of trust recorded first will be considered senior to all deeds of trusts recorded after. As such, the oldest loan becomes the primary loan, with first call on any proceeds from a sale of a property. However, a subordination agreement acknowledges that one party’s claim or interest is inferior to that of another party in the event that the borrowing entity liquidates its assets. Further, shareholders are subordinate to all creditors.
The junior debt is referred to as a “subordinated debt”, and the debt which has a higher claim to any assets is the senior debt. Often, the borrower does not have enough funds to pay all debts, and lower priority debts may receive little or no repayment. For example, if a business has $400,000 in senior debt, $100,000 in subordinated debt, and a total asset value of $420,000, upon liquidation of the company, only the senior debtholder will be paid in full. The remaining $20,000 will be distributed among the subordinated debtholders. Subordinated debts are, therefore, riskier and lenders will require a higher interest rate as compensation.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Montreal Bridge Builders Sue Canada Over New Restrictions
April 13, 2017 —
Scott Van Voorhis - Engineering News-RecordThe consortium building the $3.2-billion Champlain Bridge in Montreal has sued Canada’s government for $93 million, claiming transportation officials gave it late notice of stricter load limits that could add to delay and make it liable for tens of millions of dollars in penalties, according to Canadian press reports and a stock analyst’s comments. A spokeswoman for the team’s lead firm, engineer-contractor SNC-Lavalin, confirms the March 28 filing in Quebec Superior Court but declined further comment.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, ENRENR may be contacted at
ENR.com@bnpmedia.com
How the California and Maui Wildfires Will Affect Future Construction Projects
October 30, 2023 —
Susan Doering - Construction ExecutiveJust like any kind of fire, wildfires are caused by the presence of fuel and a spark. In the case of the
2017 fires in the wine country of California, along with the state's 2018
Camp Fire, the fuel was dry leaf litter, branches and downed trees. And the spark, in some cases, resulted from electric utility lines and, in other cases, due to contractor’s work.
More recently, this summer's Maui fires have taken hundreds of lives—deceased and missing—and burned more than 2,500 acres. Lahaina’s historic sites cannot be replaced, and estimates of the rebuild costs are near $5 billion. In Hawaii, the fuel was the same as in California: dried forest debris. It is alleged that the spark was from a powerline downed by extreme winds from Hurricane Dora. While sparks were present, it is the increased volume of fuel that has been the true source of the disastrous recent wildfires.
The increased presence of fuel is the result of recent changes in forestry-management practices, coupled with accelerated climatic shifts in recent years toward hotter, drier weather from 2011 to 2020 in California and 2022 to 2023 in Maui, increasing both frequency and severity.
Reprinted courtesy of
Susan Doering, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Pending Sales of Existing Homes in U.S. Decline for Eighth Month
March 31, 2014 —
Shobhana Chandra – BloombergContracts to purchase previously owned U.S. homes unexpectedly fell in February for an eighth straight month, a sign of further weakness in the industry.
The index of pending home sales decreased 0.8 percent after a 0.2 percent drop the prior month that was previously reported as a gain, figures from the National Association of Realtors showed today in Washington. The median forecast of 39 economists surveyed by Bloomberg called for a 0.2 percent rise.
Colder-than-normal weather probably played a role in discouraging prospective buyers faced with rising mortgage rates, higher prices and limited supply of cheaper properties. At the same time, the Realtors group said buyer traffic is stabilizing, which may help spur demand as temperatures warm.
Read the court decisionRead the full story...Reprinted courtesy of
Shobhana Chandra, BloombergMs. Chandra may be contacted at
schandra1@bloomberg.net
Improper Classification Under Davis Bacon Can Be Costly
April 01, 2015 —
Craig Martin – Construction Contractor AdvisorThe Department of Labor announced late last year that it had recovered nearly $2 million in back wages and fringe benefits from a subcontractor that provided constructions services at the federally funded Crescent Dunes Solar Energy Project in the Nevada desert. This was not a failure to pay Davis Bacon wages, but a failure to properly classify laborers on the project. The DOL determined that the laborers should have been paid as skilled trade steelworkers, not general laborers. As the subcontractor found out, this proved very costly.
The subcontractor submitted its bid, classifying its laborers as general laborers and designating their wage at $30.00. The laborers were to assemble billboard sized mirrors on the project. There is some indication that the Department of Energy agreed with the classification, even though the Department of Labor has the final say on classifications. The Department of Labor’s investigation revealed that the laborers routinely performed duties in skilled trades, such as ironworking, electrical work, painting or bridge crane operation. Based on these activities, the Department of Labor concluded that the laborers should have been paid $60.00 per hour plus fringe benefits.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Be a Good Neighbor: Protect Against Claims by an Adjacent Landowner During Construction
November 09, 2020 —
Joshua Levy & Madeleine Bailey - Construction ExecutiveThere’s nothing like working in an office while pilings are being pounded into the ground next door, leading to crashing sounds of pile driving and the attendant afternoon headaches. Fortunately, that’s often the extent of a neighboring project’s real inconvenience. In other cases, however, construction in close quarters can mark the beginning of costly and emotional disputes, which can escalate to costly legal battles during and after construction.
NUISANCE AND STRUCTURAL DAMAGE CLAIMS
Construction claims are often based on the concept of “nuisance,” or on structural damage to adjacent property. Nuisance claims are typically based on noise and dust from construction sites, while structural damage claims are based on direct physical damage caused by neighboring demolition, vibrations, excavation and dewatering. These types of claims can result in monetary damages for neighbor plaintiffs, loss of permits for contractors and reputational damage to the developer.
In one recent case in New York City, the developer faces up to $10 million in damages in a lawsuit with a neighboring property owner. The developer was conducting excavation, dewatering and installation of steel sheet piles, which the plaintiff alleges caused its five-story building to settle and shift, rendering doors inoperable and causing extensive cracking and separation of floors and ceilings from walls and supports. The plaintiff filed its complaint on Jan. 24, 2019, and the lawsuit is ongoing, exemplifying that construction claims such as these can be time consuming and costly (Complaint, 642 East 14th St. v. 644 E. 14th Realty [N.Y. Sup. Ct. January 24, 2019]).
Reprinted courtesy of
Joshua Levy & Madeleine Bailey, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of