Homebuilders Are Fighting Green Building. Homeowners Will Pay.
April 22, 2024 —
Mark Gongloff - BloombergBack in the 1990s, political guru James Carville said he wanted to be reincarnated as the bond market because it could “intimidate everybody.” Here in the 2020s, you might prefer to come back as a homebuilder. The industry has the political muscle to protect its profits at the expense of both homeowners and the climate.
In some fast-growing parts of the US, lobbyists are frustrating efforts to make new homes more efficient and compatible with clean technology, making it that much harder for the rest of us to avoid the worst effects of a heating planet. They’re doing it in the name of housing affordability, naturally — but it doesn’t hurt that they’re keeping a lid on homebuilders’ costs at the same time. Their sabotage will cost homeowners much more in the long run.
In 2021, the International Code Council, a nonprofit group that every few years suggests building codes for the whole country, released an aggressive set of proposals that could reduce residential carbon emissions and annual energy costs by 9%, according to one estimate. This was in response to a groundswell of requests from local officials to update standards that had long been stagnant.
Read the court decisionRead the full story...Reprinted courtesy of
Mark Gongloff, Bloomberg
The ARC and The Covenants
May 30, 2018 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome back Mike Collignon. Mike is a co-founder of the Green Builder Coalition. The Green Builder® Coalition amplifies the voice of green builders and professionals to drive advocacy and education for more sustainable building practices.
As we start to see signs of a housing recovery, slow as it may be, I feel the industry is in a great position. All the effort put in by so many to improve our energy codes, green building programs & rating systems will finally be able to bear fruit. We can start to build homes that are much more environmentally responsible. Sure, we can have a lengthy debate about implementation and adoption rates, but you’ve got to walk before you can run. Unfortunately, I can see that progress getting shackled by an unexpected impediment: the architectural review committee (ARC; sometimes called “architectural committee” or “architectural control authority”) and the covenants of a homeowners’ association.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Think Twice Before Hedging A Position Or Defense On A Speculative Event Or Occurrence
July 13, 2020 —
David Adelstein - Florida Construction Legal UpdatesSometimes, hedging a position on a potential occurrence is not prudent. Stated differently, hedging a position on a contingent event is not the right course of action. The reason being is that a potential occurrence or contingent event is SPECULATIVE. The occurrence or event may not take place and, even if it does take place, the impact is unknown.
An example of hedging a defense on such a potential occurrence or contingent event can be found in a construction dispute involving a federal project out of the Eastern District of Virginia, U.S. f/u/b/o Champco, Inc. v. Arch Insurance Co., 2020 WL 1644565 (E.D.Va. 2020). In this case, the prime contractor hired a subcontractor to perform electrical work, under one subcontract, and install a security system, under a separate subcontract. The subcontractor claimed it was owed money under the two subcontracts and instituted a lawsuit against the prime contractor’s Miller Act payment bond. The prime contractor had issued the subcontractor an approximate $71,000 back-charge for delays. While the subcontractor did not accept the back-charge, it moved for summary judgment claiming that the liability for the back-charge can be resolved at trial as there is still over $300,000 in contract balance that should be paid to it. The prime contractor countered that the delays caused by the subcontractor could be greater than $71,000 based on a negative evaluation in the Contractor Performance Assessment Reporting System (“CPARS”). A negative CPARS rating by the federal government due to the delays caused by the subcontractor would result in a (potential) loss of business with the federal government (i.e., lost profit) to the prime contractor. The main problem for the prime contractor: a negative CPARs rating was entirely speculative as there had not been a negative CPARs rating and, even if there was, the impact a negative rating would have on the prime contractor’s future business with the federal government was unknown. To this point, the district court stated:
In this case, [prime contractor’s] claim for damages is wholly speculative. [Prime contractor] has not produced any evidence that its stated condition precedent—a negative CPARS rating—will actually occur and will have a negative impact on its future federal contracting endeavors. Specifically, [prime contractor] has not identified any facts that indicate that it will be subject to a negative CPARS rating or any indication of the Navy’s dissatisfaction with its work as the prime contractor on the Project… Further, a CPARS rating is only one aspect taken into consideration when federal contracts are awarded. In sum, there is no evidence of the following: (1) a negative CPARS rating issued to [prime contractor]; (2) [prime contractor’s] hypothetical negative rating will be the result of the delay [prime contractor] alleges was caused by [subcontractor]; or (3) [prime contractor’s] hypothetical negative CPARS rating will result in future lost profits.
U.S. f/u/b/o Champco, Inc., supra, at *2 (internal citation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Design Firm Settles over Construction Defect Claim
July 31, 2013 —
CDJ STAFFA Pennsylvania township has announced that it has reached a settlement with the architectural firm that designed its administration building. Cee Jay Frederick Associates will be paying than $1.05 million to settle claims of defects in the design of the building.
West Whiteland’s administration building was completed in July 2007. The first leaks were noticed in November and December 2008. In response, the township stopped payments to the contractor, Magnum, Inc. Magnum sued, claiming that their work was not to blame for the leaks. Magnum joined the township in suing the design firm.
Although Cee Jay Frederick Associates will be paying the township to settle the claim, West Whiteland will be paying $75,000 of that back to the firm to settle outstanding bills that had been withheld during litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Appeals Court Reverses Summary Judgment over Defective Archway Construction
February 10, 2012 —
CDJ STAFFA judge has ruled that a plaintiff can go forward with her suit that she was injured by a defective archway during a birthday party. A three-judge panel of the California Court of Appeals issued this ruling on January 23, 2012, in the case of Trujillo v. Cosio.
Ms. Trujillo attended a birthday party at the home of Maria Cosio and Joel Verduzco. A piñata was hung between a tree and a brick archway. Ms. Trujillo went to get candy that had fallen from the piñata, during which the archway fell on her hand. Subsequent examination of the archway showed that it had not been “properly anchored to the supporting pillars to protect the arch from falling.”
Ms. Cosio and Mr. Verduzco argued that they could not have been aware of the defective nature of the archway’s construction, as it had been built at the request of the prior property owner. The structure was constructed without building permits. Mark Burns, a civil engineer testifying for the plaintiff, said that “a reasonable property owner would have thoroughly tested the archway to ensure it was capable of withstanding such horizontal forces before allowing children to enter into the area.” Mr. Burns noted that twenty rope pulls would have been sufficient to demonstrate the structure’s instability.
The trial court rejected Mr. Burn’s statements, finding that the respondents did not have any knowledge of the defect and that a visual inspection should have sufficed. The court noted that this a triable issue, whether visual inspection suffices, or whether the property owners should have done as Mr. Burns suggested and yank a rope twenty times. The court noted that “although a jury may ultimately disagree with Burn’s opinion, it was supported by sufficient foundation and was not speculative.”
The opinion was written by Judge Flier, with Judges Rubin and Grimes concurring.
Read the court’s decison…
Read the court decisionRead the full story...Reprinted courtesy of
Impact of Lis Pendens on Unrecorded Interests / Liens
September 15, 2016 —
David Adelstein – Florida Construction Legal UpdatesIn a previous article, I discussed the importance of recording a lis pendens in a construction lien foreclosure action.
There is another noteworthy point relating to the impact of lis pendens that can provide quite a bit of consternation.
Florida Statute 48.23(1)(d) provides:
Except for the interest of persons in possession or easements of use, the recording of such notice of lis pendens, provided that during the pendency of the proceeding it has not expired pursuant to subsection (2) or been withdrawn or discharged, constitutes a bar to the enforcement against the property described in the notice of all interests and liens, including, but not limited to, federal tax liens and levies, unrecorded at the time of recording the notice unless the holder of any such unrecorded interest or lien intervenes in such proceedings within 30 days after the recording of the notice. If the holder of any such unrecorded interest or lien does not intervene in the proceedings and if such proceedings are prosecuted to a judicial sale of the property described in the notice, the property shall be forever discharged from all such unrecorded interests and liens. If the notice of lis pendens expires or is withdrawn or discharged, the expiration, withdrawal, or discharge of the notice does not affect the validity of any unrecorded interest or lien.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Quick Note: Third-Party Can Bring Common Law Bad Faith Claim
July 01, 2019 —
David Adelstein - Florida Construction Legal UpdatesA third-party claimant may bring a common law bad faith claim against a defendant’s liability insurer. Mccullough v. Royal Caribbean Cruises, 2019 WL 2076192, *2 (S.D.Fla. 2019). “A bad faith claim may be brought by a third party absent an assignment from the [defendant] insured.” Id. This can only be done in the third-party bad faith context with the argument that the insurer’s “bad faith” conduct resulted in a judgment against the defendant-insured in excess of the policy limits. However, in any third-party bad faith claim (and, really, bad faith claim in general), coverage must first be determined under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Smart Contracts Poised to Impact the Future of Construction
November 12, 2019 —
Frederick D. Cruz and Seth Wamelink - Construction ExecutiveIn August 2018, the State of Ohio passed legislation making it easier for businesses in Ohio, including the construction industry, to use blockchain technology in business transactions, which can result in significant savings and increased efficiency if used correctly. Specifically, Senate Bill 220 amends the Uniform Electronic Transactions Act (Ohio Rev. Code. 1306.01, et seq.) and ensures that records (or signatures) secured through blockchain are legally binding. With the enactment of this bill, Ohio has joined several other states to allow their businesses to take advantage of this budding technology. While the implications of this enactment are widespread, the use of “smart contracts” utilizing blockchain technology is particularly helpful in the construction industry to streamline certain processes and increase efficiency.
What is Blockchain?
While blockchain technology is most commonly associated with cryptocurrency (e.g., Bitcoin), the technology has far greater applications as it can be used to “eliminate the middle-man” in a variety of transactions across a broad spectrum of industries. At its core, blockchain is a decentralized ledger that allows transacting parties to interact directly (i.e., peer-to-peer) in a secure manner. Essentially, the blockchain “ledger” is where users record transactions. These transactions are then verified, viewed, and shared with others in the network. The information is stored across a peer network and allows for approved users to view the data simultaneously. It is often analogized to using GoogleDocs, where multiple people can access and edit the same document simultaneously. While that is an easy comparison, blockchain itself is a bit more complex.
Reprinted courtesy of
Frederick D. Cruz & Seth Wamelink, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Cruz may be contacted at frederick.cruz@tuckerellis.com
Mr. Wamelink may be contacted at seth.wamelink@tuckerellis.com
Read the court decisionRead the full story...Reprinted courtesy of