Fourth Circuit Rejects Application of Wrap-Up Exclusion to Additional Insured
December 11, 2018 —
K. Alexandra Byrd & Samantha M. Oliveira - Saxe Doernberger & Vita, P.C.Utilizing an owner-controlled or contractor-controlled insurance program (collectively known as “wrap-ups”) can reduce claims, save costs, and give owners and general contractors comfort in knowing their project is adequately insured. However, problems often arise when a subcontractor doesn’t enroll in the wrap-up and, instead, agrees to provide additional insured coverage to the owner and general contractor on the subcontractor’s own general liability policy. One of those problems is the prevalence of wrap-up exclusions on subcontractors’ general liability policies. If the wrap-up exclusion is too broadly drafted, the exclusion can eliminate coverage for the general contractor and owner even when the subcontractor is not enrolled in the wrap-up.
Reprinted courtesy of
K. Alexandra Byrd, Saxe Doernberger & Vita, P.C. and
Samantha M. Oliveira, Saxe Doernberger & Vita, P.C.
Ms. Byrd may be contacted at kab@sdvlaw.com
Mr. Oliveira may be contacted at smm@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Statute of Limitations Bars Lender’s Subsequent Action to Quiet Title Against Junior Lienholder Mistakenly Omitted from Initial Judicial Foreclosure Action
October 19, 2020 —
Lyndsey Torp - Snell & Wilmer Real Estate Litigation BlogA recently issued opinion by the Court of Appeal, Fifth Appellate District tells a cautionary tale regarding a lender’s failure to name a junior lienholder in its initial judicial foreclosure action.
In Cathleen Robin v. Al Crowell, — Cal.Rptr.3d —-, 2020 WL 5951506, plaintiffs sued defendant, a junior lienholder, for quiet title, having failed to name him in the initial judicial foreclosure action. Defendant raised the statute of limitations defense, but the trial court found in favor of plaintiffs. The court of appeal reversed, holding that the 60-year statute of limitations which the trial court applied only applied to a nonjudicial trustee’s sale, and the trial court could not exercise the trustee’s power of sale after the expiration of the statute of limitations on a judicial action to foreclose.
In 2006, plaintiffs loaned Steve and Marta Weinstein (the “Weinsteins”) $450,000, secured by a deed of trust on one parcel of the Weinstein’s property. In 2007, the Weinsteins and defendant Al Crowell (“Crowell”) recorded a second deed of trust on the property, securing a promissory note executed by the Weinsteins in 2004.
Read the court decisionRead the full story...Reprinted courtesy of
Lyndsey Torp, Snell & WilmerMs. Torp may be contacted at
ltorp@swlaw.com
Sources of Insurance Recovery for Emerging PFAS Claims
December 17, 2024 —
Jasjeet K. Sahani - Saxe Doernberger & Vita, P.C.This year, the Environmental Protection Agency (“EPA”) issued its first-ever national, legally enforceable drinking water standard to protect communities from exposure to harmful per-and polyfluoroalkyl substances (“PFAS”), also known as “forever chemicals.”
[1] In addition, the Food and Drug Administration announced that grease-proofing materials containing PFAS are no longer being sold for use in food packaging in the United States.
[2] These are likely the first in a line of many PFAS regulations that will emerge as the harmful effects of PFAS are further understood. With this increasing regulatory focus on PFAS and their harmful effects, companies whose operations might involve these substances should be aware of what they are and potential sources of recovery for claims that arise from their omnipresence.
PFAS Background
According to the EPA, PFAS are widely used, long-lasting chemicals which break down slowly over time.
[3] PFAS can be found in thousands of items, including, but not limited to: pots and pans, cleaning products, fabric and leather coatings, firefighting foam, carpeting, roofing materials, paints, sealants, caulks, and adhesives.
[4] Additionally, manufacturing processes, waste storage, and treatment sites commonly release PFAS into the air, soil, and water.
[5] Read the court decisionRead the full story...Reprinted courtesy of
Jasjeet K. Sahani, Saxe Doernberger & Vita, P.C.Ms. Sahani may be contacted at
JSahani@sdvlaw.com
Texas City Pulls Plug on Fossil Fuels With Shift to Solar
March 19, 2015 —
Christopher Martin – Bloomberg(Bloomberg) -- A city in the heart of the oil state of Texas is set to become one of the first communities in the U.S. to wean its residents off fossil fuels.
The municipal utility in Georgetown, with about 50,000 residents, will get all of its power from renewable resources when SunEdison Inc. completes 150 megawatts of solar farms in West Texas next year. The change was announced Wednesday.
It will be the first city to completely embrace clean power in the state, which is the biggest U.S. producer and user of natural gas. More will follow as municipalities seek to insulate themselves from unpredictable prices for fossil fuels, said Paul Gaynor, SunEdison’s executive vice president of North America. Burlington, Vermont, made a similar move with its purchase of a hydroelectric plant last year.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher Martin, BloombergMr. Martin may be contacted at
cmartin11@bloomberg.net
Disappearing Data: Avoid Losing Electronic Information to Avoid Losing the Case
February 01, 2022 —
Daniel C. Wennogle & Jennifer Knight Lang - Construction ExecutiveIt happens: A contractor on a delayed project ends up in litigation over liquidated damages, but the key communications regarding delays and approvals were sent and received by the project manager on a mobile device using text messages and personal email accounts. Unfortunately, the project manager left the company a year ago on bad terms and has changed phones. The information that would serve to mitigate the contractor’s liability has disappeared. With better awareness and policies for capturing and managing electronic information, this is avoidable.
Proactive and effective management of electronically stored information on construction projects can not only reduce costs and discovery disputes should litigation arise but can also provide critical evidence in reducing liability exposure in such disputes. The Federal Rules of Civil Procedure (as well as most state rules, which often mirror federal rules), provide for sanctions if a party fails to preserve electronically stored information (ESI) that should have been preserved in anticipation of litigation but is lost due to the failure to take reasonable steps to preserve it.
Even in arbitration, where discovery and disclosure obligations are often more limited than in the court setting, preservation of ESI can help strengthen claims and defenses, avoiding accusations of spoliation that can derail a case. Arbitrators can also fashion appropriate sanctions for destruction of relevant evidence, not to mention the impact that apparent spoliation can have on a party’s credibility.
Reprinted courtesy of
Daniel C. Wennogle & Jennifer Knight Lang, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Ms. Lang may be contacted at jennifer.lang@moyewhite.com
Mr. Wennogle may be contacted at daniel.wennogle@moyewhite.com
Read the court decisionRead the full story...Reprinted courtesy of
The Firm Hits the 9 Year Mark!
July 22, 2019 —
Christopher G. Hill - Construction Law MusingsIt was 9 years ago today that I announced the formation and start of my solo practice, The Law Office of Christopher G. Hill, PC. Back then, my children were in elementary and middle school. Now I have two college students, one at Appalachian State University (with a budding photography talent that has provided some photos for this blog (including that on this post)) and the other at West Virginia University, and a rising high school junior. In just the past year I began a tenure on the Section Council Virginia Bar Association Construction and Public Contracts Law section and chair of its Legislative Committee where I assisted in the drafting of the change in the mechanic’s lien form that takes effect today..
I was named to both the Virginia Business Magazine Legal Elite in Construction Law and for a 3rd consecutive year to Virginia Super Lawyers in Construction Litigation. I spoke on how to deal with a DPOR complaint this past November at the 39th Annual Construction Law and Public Contracts seminar (one I highly recommend for any lawyer interested in construction).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Chicago Developer and Trade Group Sue City Over Affordable Housing Requirements
September 03, 2015 —
Beverley BevenFlorez-CDJ STAFFThe Chicago Tribune reported that Hoyne Development and Home Builders Association of Greater Chicago are suing the city of Chicago, claiming that the “Affordable Requirements Ordinance is unconstitutional because it involves the taking of private party without ‘just compensation,’ violating the Fifth Amendment.”
Shannon Breymaier, spokeswoman for Chicago Mayor Rahm Emanuel, however, disputes the claims, and told the Chicago Tribune in an email that the city planned to “defend the ordinance vigorously.”
Read the court decisionRead the full story...Reprinted courtesy of
Want More Transit (and Federal Funding)? Build Housing That Supports It
January 08, 2024 —
M. Nolan Gray - BloombergAfter
decades of planning (and $2.1 billion spent), Los Angeles’ newest light rail line opened in October 2022. Joined by geeky rail obsessives and chaperoned children, I rode the K Line on opening day. A blend of underground, elevated and at-grade track, it’s a route only a politician could love. Stations were lavished with public art, and when the train wasn’t stuck in traffic, it glided through the sprawl.
Yet one year later, it is Los Angeles’ least-used line, averaging
just over 2,000 riders on an average weekday this fall.
It isn’t hard to see why: The line begins at a vacant patch in Crenshaw and ends in a low-slung industrial park about six miles away, lined by strip malls the entire way. Walk one block east or west from any given station, and you’ll find yourself amid single-story postwar bungalows on 7,500-square-foot lots — all illegal to redevelop into apartments, thanks to local zoning. The Hyde Park Station deposits riders into a cluster of gas stations and drive-thru fast-food joints.
Read the court decisionRead the full story...Reprinted courtesy of
M. Nolan Gray, Bloomberg