General Partner Is Not Additional Insured For Construction Defect Claim
August 26, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court determined that the project owner's general partner was not an additional insured entitled to a defense and indemnity against claims for construction defects. St. Paul Fire & Marine Ins. Co. v,. Cypress Fairway Condo. Ass'n, 2015 U.S. Dist. LEXIS 94012 (M.D. Fla. July 20, 2015).
Construction of the Cypress Fairway Condominium project took place in 1999 and 2000. Cypress Fairway Ltd. ("Cypress") was the owner and Vineland Partners , LLC ("Vineland") was its general partner. The general contractor was Winter Park Construction Company ("WPC"). Water intrusion and property damage occurred, but it was unclear when or whether the damage was known. Cypress' expert indicated that the damage began shortly after the end of construction.
In 2004, the complex was sold to Cypress Madison Ownership Company. In 2010, the Cypress Fairway Condominium Association sued Cypress and Vineland. Count V of the underlying complaint asserted there were construction defects that Cypress and Vineland were responsible for when they owned and managed the project. Count VI alleged that Cypress and Vineland negligently supplied information which the Association relied on for the purchase of the condominiums.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
A Win for Policyholders: California Court of Appeals Applies Vertical Exhaustion for Continuous Injury Claims
August 24, 2020 —
Celia B. Waters - Saxe Doernberger & VitaFresh off the heels of the California Supreme Court’s landmark decision in Montrose Chemical Corp. v. Super. Ct. of L.A. Cty. (“Montrose III”),1 policyholders scored another victory as another California court rejected horizontal exhaustion in the context of continuous injury cases. The Court of Appeal of the State of California, First Appellate District, Division Four, in SantaFe Braun Inc. v. Ins. Co. of N. Am., adopted a rule of vertical exhaustion, holding that “[absent an explicit policy provision to the contrary] the insured becomes entitled to the coverage it purchased from the excess carriers once the primary policies specified in the excess policy have been exhausted.”2
The dispute in SantaFe Braun began in 1992 when asbestos-related claims were first filed against Braun. In 1998, Braun’s three primary insurers agreed in writing to defend and settle the underlying claims against Braun while resolving allocation among themselves. In 2004, Braun filed the current suit against its excess insurers, seeking a declaration that the excess insurers were obligated to help cover the costs of the underlying asbestos-related lawsuits.
Read the court decisionRead the full story...Reprinted courtesy of
Celia B. Waters, Saxe Doernberger & VitaMs. Waters may be contacted at
cbw@sdvlaw.com
Newmeyer & Dillion’s Alan Packer Selected to 2018 Northern California Super Lawyers List
July 18, 2018 —
Newmeyer & DillionWALNUT CREEK, Calif. – JULY 10, 2018 – Prominent business and real estate law firm Newmeyer & Dillion LLP is pleased to announce that litigation attorney Alan Packer has been selected to the 2018 Northern California Super Lawyers list. No more than five percent of the lawyers in the state are selected by Super Lawyers each year.
Packer is a partner in the firm's expanding Walnut Creek office. He has practiced law in California for over 30 years, mostly representing parties involved in real estate, home building, commercial construction, and insurance matters. He represents business clients, homebuilders, property owners, and others in a broad range of legal matters.
Packer is a frequent speaker at seminars and in-house training sessions for clients on issues relating to risk management, construction litigation, and insurance.
Earlier this year, Newmeyer & Dillion attorneys in Newport Beach and Las Vegas were also selected to Super Lawyers lists. Packer brings its total to 19 Newmeyer & Dillion attorneys recognized.
Super Lawyers is a rating service of outstanding lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The patented selection process includes independent research, peer nominations and peer evaluations, resulting in a comprehensive and diverse listing of exceptional attorneys.
Alan Packer
Partner
Walnut Creek
Contact
925.988.3200
alan.packer@ndlf.com
Practices
Business Litigation
Construction Litigation
Insurance Law
Real Estate Litigation
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client's needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.ndlf.com.
Read the court decision
Read the full story...
Reprinted courtesy of
Repair of Part May Necessitate Replacement of Whole
February 10, 2012 — CDJ STAFF
Judge Gleuda E. Edmonds, a magistrate judge in the United States District Court of Arizona issued a ruling in Guadiana v. State Farm on January 25, 2012. Judge Edmonds recommended a partial summary judgment in favor of the plaintiff.
Ms. Guandiana’s home had water damage due to pluming leaks in September 2004. She was informed that polybutylene pluming in her house could not be repaired in parts “it must be completely replaced.” She had had the plumbing replaced. State Farm denied her claim, arguing that “the tear-out provision did not cover the cost of accessing and replacing those pipes that were not leaking.”
In September 2007, State Farm filed a motion to dismiss. The court rejected this motion, stating that “If Guadiana can establish as a matter of fact that the system that caused the covered loss included all the pipes in her house and it was necessary to replace all the pipes to repair that system, State Farm is obligated to pay the tear-out costs necessary to replace all the pipes, even those not leaking.”
In March 2009, State Farm filed for summary judgment, which the court granted. State Farm argued that “the tear-out provision only applied to ‘repair’ and not ‘replace’ the system that caused the covered leak.” As for the rest of the piping, State Farm argued that “the policy does not cover defective materials.”
In December 2011, Ms. Guadiana filed for summary judgment, asking the court to determine that “the policy ‘covers tear-out costs necessary to adequately repair the plumbing system, even if an adequate repair requires replacing all or part of the system.”
In her ruling, Judge Edmonds noted that Ms. Guadiana’s claim is that “the water damage is a covered loss and she is entitled to tear-out costs necessary to repair the pluming system that caused that covered loss.” She rejected State Farm’s claim that it was not obligated to replace presumably defective pipes. Further, she rejected State Farm’s argument that they were only responsible for the leaking portion, noting “Guadiana intends to prove at trial that this is an unusual case where repair of her plumbing system requires replacement of all the PB plumbing.”
Judge Edmonds concluded by directing the District Court to interpret the tear out issue as “the tear-out provision in State Farm’s policy requires State Farm to pay all tear-out costs necessary to repair the plumbing system (that caused the covered loss) even if repair of the system requires accessing more than the leaking portion of the system.”
Read the court’s decision…
Read the court decision
Read the full story...
Reprinted courtesy of
Wildfire Insurance Coverage Series, Part 7: How to Successfully Prepare, Submit and Negotiate the Claim
August 22, 2022 — Scott P. DeVries & Yosef Itkin - Hunton Insurance Recovery Blog
Prior posts in this series have discussed insurance coverage issues that pertain directly to wildfire claims, but we have not yet addressed how one proceeds following a loss. In this post in the Blog’s Wildfire Insurance Coverage Series, we discuss the preparation, submission and negotiation of the insurance claim.
Preparing a Claim
As different policies provide different timelines, where possible, it is advisable to submit the claim as soon as reasonably possible. Insurers commonly cite late submission as a basis for denial with jurisdictions varying on the import of “late” submission.
Insurers have a right to reasonable documentation of a claim before paying. Often, they will decline to consider a claim on its merits until such documentation is provided. The policy will specify whether to submit a hard copy or file online, but either way it is advisable to maintain a copy online or in a remote geographic location.
Reprinted courtesy of Scott P. DeVries, Hunton Andrews Kurth and Yosef Itkin, Hunton Andrews Kurth
Mr. DeVries may be contacted at sdevries@HuntonAK.com
Mr. Itkin may be contacted at yitkin@HuntonAK.com
Read the court decision
Read the full story...
Reprinted courtesy of
Planes, Trains and Prevailing Wages. Ok, No Planes, But Trains and Prevailing Wages Yes
October 25, 2021 — Garret Murai - California Construction Law Blog
The California Supreme Court doesn’t often delve into construction-related issues, but this year we’ve got two cases, both related to the payment of prevailing wages on California public works projects.
The first, Mendoza v. Fonseca McElroy Grinding Co., Inc. (2021) 11 Cal.5th 1118 which we discussed in our last blog post, concerned whether mobilization work qualifies as a “public work” and in turn requires the payment of prevailing wages. On the same day that the Supreme Court issued its decision in Mendoza, it issued a decision in Busker v. Wabtec Corporation, et al. , Case No. S251135 (August 16, 2021). This is the equivalent of being struck by lightning twice.
In Busker, the California Supreme Court considered whether on a public transportation project “field work” (e.g., building and outfitting radio towers on land adjacent to train tracks) and “onboard work” (e.g., installing electronic components on train cars and locomotives”) requires the payment of prevailing wage. Read the court decision
Read the full story...
Reprinted courtesy of Garret Murai, Nomos LLP
Mr. Murai may be contacted at gmurai@nomosllp.com
New York Public Library’s “Most Comprehensive Renovation” In Its History
May 13, 2014 — Beverley BevenFlorez-CDJ STAFF
Manhattan’s New York Public Library’s renovation plans have been revised after being “the subject of at least three lawsuits and repeated protests by academics, activists, writers and historians,” according to Construction Digital. The previous $300 million plan by Foster & Partners would have required the circulation collections to be relocated during the renovation process. Now, that plan has been abandoned for one that New York Public Library President Anthony Marx calls “the most comprehensive renovation in its history.”
“Instead of removing the central stacks and placing the Mid-Manhattan Library in that space, we are proposing to renovate Mid-Manhattan Library at its current site,” Marx told Construction Digital. “This renovation will add much-needed computer labs and an adult education center, and an inspiring, comfortable space for browsing our largest circulating collection.” Read the court decision
Read the full story...
Reprinted courtesy of
More thoughts on Virginia Mechanic’s Liens
January 28, 2019 — Christopher G. Hill - Construction Law Musings
As we settled yet another construction case on the courthouse steps today, I began to think about what I should post to begin 2009. Of course, given the construction industry slowdown that is predicted, and the trend at construction projects around the Commonwealth of Virginia that looks to me as if payments will be harder to come by from Owners less willing, for financial reasons, to work with contractors, mechanic’s liens will be more useful, and necessary, now than ever.
Virginia mechanic’s liens are unusually strong because your memorandum of lien takes priority over all prior liens on the property that you have improved (including from the bank that is financing the project) except in very limited circumstances. What this means is that, should you properly file and sue to enforce your lien, you get to foreclose and have first crack at any money. By contrast, a judgment lien takes priority only over liens filed after the lien is recorded. Read the court decision
Read the full story...
Reprinted courtesy of The Law Office of Christopher G. Hill
Mr. Hill may be contacted at chrisghill@constructionlawva.com