California Precludes Surety from Asserting Pay-When-Paid Provision as Defense to Payment Bond Claim
December 21, 2020 —
Nicholas Korst - Ahlers Cressman & Sleight PLLCIn a recent case in California, the Court of Appeals held that a surety who had issued a public works payment bond cannot rely on the “Pay-When-Paid” provision in the subcontract as a defense against the subcontractor’s claim against the payment bond.[1] The case was a public works project in Kern County, CA where the North Edwards Water District (the “District”) hired Clark Bros., Inc. (“Clark”) as the general contractor to build an arsenic removal water treatment plant. Clark hired subcontractor Crosno Construction (“Crosno”) to build and coat two steel reservoir tanks. The subcontract included the following “pay-when-paid” provision, which provided a definition of “reasonable time”:
If the Owner or other responsible party delays in making any payment to the Contractor from which payment to Subcontractor is made, Contractor and its sureties shall have a reasonable time to make payment. “Reasonable time” shall be determined according to the relevant circumstances, but in no event shall be less than the time Contractor and Subcontractor require to pursue to conclusion their legal remedies against the Owner or other responsible party to obtain payment, including (but not limited to) mechanics lien remedies. (emphasis added).
Read the court decisionRead the full story...Reprinted courtesy of
Nick Korst, Ahlers Cressman & Sleight PLLCMr. Korst may be contacted at
nicholas.korst@acslawyers.com
Washington Court Denies Subcontractor’s Claim Based on Contractual Change and Notice Provisions
January 29, 2024 —
Wendy Rosenstein - Ahlers Cressman & Sleight PLLCThe recent unpublished case, Cascade Civil Construction, LLC v. Jackson Dean Construction, Inc., et al.,[1] provides a legal justification for contractors to require a directive or change order in advance of performing changed work—thereby preventing the party who requested the changed work from later arguing that notice provisions were not complied with.
In the case, Jackson Dean, the prime contractor, hired Cascade to perform excavation work on a project to build a new Costco Corporate headquarters. Due to the Covid-19 pandemic and other issues, Jackson Dean directed resequencing, which required Cascade to perform excavation concurrent to dewatering. Jackson Dean also required deeper-than-planned excavation under one of the buildings.
Read the court decisionRead the full story...Reprinted courtesy of
Wendy Rosenstein, Ahlers Cressman & Sleight PLLCMs. Rosenstein may be contacted at
wendy.rosenstein@acslawyers.com
California Court of Appeal Makes Short Work Trial Court Order Preventing Party From Supplementing Experts
August 06, 2019 —
Garret Murai - California Construction Law BlogYears ago I recommended to a client that we hire a construction defect expert in a case. The client, a thrifty fellow, responded, “But I thought you were the construction expert. Why do I need to hire another expert? A fair question and one that caught me flat footed.
Whether I’m an “expert” or not can be debated, but I explained to the client that while I was an attorney whose practice focused on construction law, I was not someone who he would want to take the stand and testify about the engineering design and seismic stability of pilings. For that, he needed an expert.
In construction litigation it’s not uncommon for parties and their attorneys to hire “experts.” There are even special rules set forth in the California Code of Civil Procedure for disclosing, supplementing and deposing experts, which basically provide as follows:
1. Demand for Exchange of Expert Information: After the court sets a trial date in a case, any party may demand that each party exchange information concerning the experts they intend to have testify at trial;
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Town Concerned Over Sinkhole at Condo Complex
September 24, 2013 —
CDJ STAFFDespite the assurances of their engineering firm, the township of Old Bridge, New Jersey has yet to release the performance bond to the construction of Plaza Grande, a condominium complex for residents over 55. One resident summarized the problem for the Suburban, a newspaper for towns in the area. “Our major concern is a sinkhole near Building 4 that has come back several times.”
D.R. Horton, the developer on the project, has dug out the sinkhole, then backfilled and compacted it. However , one member of the Old Bridge Township Council said that she noticed that the area was beginning to sink again. The council member, Mary Sohor, said that Horton “should’ve dug a little deeper and did a little more.”
D.R. Horton said that the issues do not affect the safety of the residents and attribute them to seasonal wear and tear.
Read the court decisionRead the full story...Reprinted courtesy of
Charles Eppolito Appointed Vice-Chair of the PBA Judicial Evaluation Commission and Receives Prestigious “President’s Award”
November 30, 2020 —
Charles Eppolito, III - White and Williams LLPPartner Charles (Chuck) Eppolito, III has been appointed as a Vice-Chair of the Pennsylvania Bar Association (PBA) Judicial Evaluation Commission. His three-year term begins immediately and will expire September 30, 2023. The PBA Judicial Evaluation Commission is responsible for developing and implementing a judicial evaluation process for appellate judicial candidates in the Commonwealth of Pennsylvania. As Vice-Chair, Chuck will oversee reviewing the investigative panel's report, interviewing each candidate, discussing qualifications and reaching an agreement upon and issuing a rating for each candidate for appellate judicial office.
Chuck has a long history of involvement with the 25,000-member organization, serving as PBA Secretary from 2007 to 2010, Chair of the House of Delegates from 2011 to 2013 and President from 2018 to 2019. Most recently, it was announced that Chuck is a recipient of a PBA “President’s Award” for his dedication and commitment to fulfilling the mission of the PBA COVID-19 Task Force. The award will be presented during the virtual PBA Awards Luncheon on Thursday, November 19, 2020.
Read the court decisionRead the full story...Reprinted courtesy of
Charles Eppolito, III, White and Williams LLPMr. Eppolito may be contacted at
eppolitoc@whiteandwilliams.com
New OSHA Fall Rules to Start Early in Minnesota
June 14, 2011 —
CDJ STAFFMinnesota has elected to implement the new OSHA rules concerning fall prevention in residential construction on June 20, well before OSHA’s September 15 deadline. Brian Johnson, reporting in Finance and Commerce, quotes Pam Perri, the executive vice president of the Builders Association of Minnesota, “this is the worst time to implement a new rule.” Ms. Perri notes “In Minnesota, education time for the residential construction industry is between November and March 1, not in the middle of the construction season.”
Mike Swanson of Rottlund Homes estimated that the new regulations would add between $200 to $500 to the cost of a house and that he felt the current safety regulations were adequate. OSHA officials are quoted that there continues “to be a high number of fall-related deaths in construction.”
Read the fully story…
Read the court decisionRead the full story...Reprinted courtesy of
"Ongoing Storm" Rules for the Northeast (Connecticut, Massachusetts, New Jersey, New York & Rhode Island)
February 22, 2021 —
Angeline Ioannou, Kenneth Walton, Colin Hackett, Gregory Katz & Lauren Motola-Davis - Lewis BrisboisThe winter storm that recently brought several feet of snow to the Northeast signaled that we are, indeed, in the middle of winter. Moreover, our nation’s favorite groundhog, Punxsutawney Phil, saw his shadow on Groundhog Day this year, indicating that winter will be with us for six more weeks. As we move through the remainder of this snowy season, it is important for businesses to understand their legal obligations concerning snow removal and the defenses that are available to them in the event that an injury occurs on their premises. This alert summarizes the ongoing storm rules in Connecticut, Massachusetts, New Jersey, New York, and Rhode Island, and analyzes property owners’ snow removal responsibilities as well as related premises liability issues under these states’ laws.
Connecticut
It is well settled in Connecticut that, in the absence of unusual circumstances, in fulfilling their duty to invitees on their property, property owners may wait a reasonable time after the conclusion of a storm to perform ice and snow removal from outside walkways and steps. Kraus v. Newton, 211 Conn. 191, 197-198 (1989). A property owner’s duty to perform reasonable snow and ice removal of outside walkways does not arise until after a reasonable period of time has passed after a storm ends. Umsteadt v. G.R. Realty, 123 Conn. App. 73, 83 (2010). The ongoing storm doctrine does not apply, however, if the defective condition arises from preexisting ice or snow, and not from the ongoing storm. Whether the alleged defective condition was caused by preexisting ice or snow and whether a storm has concluded are both questions of fact that may be decided by a jury. Kraus at 197-198.
Reprinted courtesy of
Angeline Ioannou, Lewis Brisbois,
Kenneth Walton, Lewis Brisbois,
Colin Hackett, Lewis Brisbois,
Gregory Katz, Lewis Brisbois and
Lauren Motola-Davis, Lewis Brisbois
Ms. Ioannou may be contacted at Angeline.Ioannou@lewisbrisbois.com
Mr. Walton may be contacted at Ken.Walton@lewisbrisbois.com
Mr. Hackett may be contacted at Colin.Hackett@lewisbrisbois.com
Mr. Katz may be contacted at Greg.Katz@lewisbrisbois.com
Ms. Motola-Davis may be contacted at Lauren.MotolaDavis@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Coverage Denied for Faulty Blasting and Improper Fill
October 08, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe court found coverage was properly denied based on the subcontractor's failure to follow contract specifications in blasting at the job site. Westfield Ins. Co. v. Carpenter Reclamation, Inc., 2014 U.S. Dist. LEXIS 130752 (S.D. W. Va. Sept. 18, 2014).
Carpenter was hired by the Board of Education (BOE) to perform preliminary site clearing, demolition, rock excavation, and establishment of sub-grade for a building. Carpenter was to excavate to 3.5 feet below the floor subgrade so that plumbing and other utilities could be installed.
Carpenter, however, blasted to depths deeper than required, including some areas that were up to nine feet. The BOE sued, alleging over-blasting and having to pay the cost of remediating the problem, along with breach of contract issues.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com