Partner Bradley T. Guldalian Secures Summary Judgment Win for National Hotel Chain
August 26, 2019 —
Bradley T. Guldalian - Traub LiebermanOn June 26, 2019, Traub Lieberman Straus & Shrewsberry LLP Partner Bradley T. Guldalian secured summary judgment on behalf of a national hotel chain in a slip and fall accident filed in Osceola County Circuit Court in Kissimmee, Florida. The underlying loss occurred when the Plaintiff slipped and fell in a puddle of water allegedly existing in the hotel’s laundry room and suffered a partial thickness rotator cuff tear involving the distal infraspinatus tendon for which he underwent surgery and incurred over $70,000 in medical bills. The Plaintiff filed a premises liability action against the hotel claiming the hotel had failed to maintain its premises in a reasonably safe condition proximately causing the Plaintiff’s fall and resulting injuries.
After discovery closed, Mr. Guldalian filed a motion for summary judgment on behalf of the hotel arguing that to prevail in a negligence claim involving a “transitory foreign substance”, such as water on a floor, an injured party must plead and prove pursuant to Florida Statute 768.0755 that the business establishment had actual or constructive knowledge of the dangerous condition and should have taken action to remedy it prior to the time of the alleged fall. Constructive knowledge may be proven by circumstantial evidence showing that (1) the dangerous condition existed for such a length of time that, in the exercise of ordinary care, the business establishment should have known of the condition or (2) that the condition occurred with such regularity that it was foreseeable that the condition would be present on the day the injury occurred.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley T. Guldalian, Traub LiebermanMr. Guldalian may be contacted at
bguldalian@tlsslaw.com
Unintended Consequences of New Building Products and Services
April 19, 2022 —
David S. Jaffe – National Association of Home BuildersAs home builders throughout the United States are grappling with building material price surges, and shortages or delays for certain orders, many are exploring alternatives products to complete or start projects. For example, according to a recent article, some builders are constructing homes from natural materials such as rammed earth, adobe brick, and volcanic rock. In addition to being readily available on site there may be heating and cooling benefits due to the natural insulation provided by these materials. The article cautions, however, that using these alternative materials may come with added challenges such as higher costs due to a need for skilled labor, delays by home inspectors who may be unfamiliar with the techniques and methods of construction, and energy consultants who might have difficulty calculating the value of homes with these materials. See Home Builders Are Turning to Natural Materials to Get Around Supply Chain Problems; There are advantages to buying homes made with natural materials, but expect to pay a premium, Alanna Schubach, Mansion Global (March 25, 2022).
Another caution, not addressed in the article, however, but one that should be heeded by builders considering alternative materials, is the unintended consequences that might result from using alternative products, whether they are natural products or any others. The long-term effects of material use should not be ignored.
For instance, it has been reported that earthen materials are known to contain numerous organic substances and can also harbor mold. It was not too long ago that mold was a high liability issue for builders and property owners. Similarly, the use of rapidly renewable materials - products that can be produced naturally and quickly from nature - is a key component of green building. They are also cellulose or carbohydrate-based products and as such are typically optimal food sources for mold in the presence of moisture.
To avoid mold, it is important to understand the relationship between construction materials and their susceptibility to mold in the presence of moisture. “Buildings will never be designed, built, maintained, or utilized perfectly; and weather and natural disasters cannot be predicted. The one thing we can have complete control over, the materials within the building, should be selected wisely.” See Mold Susceptibility of Rapidly Renewable Building Materials Used in Wall Construction, AM Cooper, Master's thesis, Texas A&M University (2007) (Samples of wool, cork, straw, and cotton-- rapidly renewable materials used as exterior wall insulation products--were exposed to different moisture amounts in an encapsulated environment, representing the environment within a wall cavity when exposed to water from pipes, leaks, condensation and absorption, or from initial construction. The samples were monitored over time for mold growth).
Mold-related issues are just one example of the potential for unintended consequences from the use of alternative materials. Carefully reviewing building material choices in advance may help eliminate non-conforming building materials, returns and possibly disputes. NAHB has developed a guide,
Assessing Building Materials, for builders who may not have their own review process for gathering information from manufacturers and distributors when considering the selection of new building materials.
The guide is intended to arm members with the most important factor when evaluating new materials or products: information. Use the guide to step through the information collection process to make an informed decision on deploying new products or materials. The guide is not intended to be exhaustive or all-inclusive, but it will help builders ask the right questions and seek the most relevant information.
Copyright © 2022 by the National Association of Home Builders of the United States. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
David S. Jaffe, NAHBMr. Jaffe may be contacted at
DJaffe@nahb.org
As Evidence Grows, Regions Prepare for Sea Level Rise
July 02, 2018 —
Pam Radtke Russell - Engineering News RecordCities, states and regions are taking steps to prepare their buildings, infrastructure and homes for the impacts of climate change as bad news continues to mount about rising sea levels.
Read the court decisionRead the full story...Reprinted courtesy of
Pam Radtke Russell, ENRMs. Russell may be contacted at
Russellp@bnpmedia.com
Traub Lieberman Partner Lisa M. Rolle Obtains Pre-Answer Motion to Dismiss in Favor of Defendant
August 16, 2021 —
Lisa M. Rolle - Traub LiebermanTraub Lieberman Partner Lisa M. Rolle obtained a motion to dismiss in favor of an international hotel chain. In the case brought before the U.S. District Court, Southern District of New York, the Plaintiff sustained a slip and fall injury in a Portuguese hotel (“Hotel”), which was allegedly caused by violations of building codes and New York and Portuguese negligence laws. The Plaintiff notes that the Hotel utilized the branding affiliated with the international hotel chain, and the named corporate entities are subsidiaries of the parent company of the international hotel chain. Further, Plaintiff alleged that the named corporate entities “owned, operated, maintained, and controlled” the Hotel where the accident occurred, as the international hotel had previously acquired the entity which owned the spa branding utilized.
In moving for pre-answer dismissal, Traub Lieberman acknowledged purchase of the managing agent of the Hotel, which became a subsidiary of their operations. However, Traub Lieberman asserted that the international hotel chain had not owned, operated, maintained, or managed the Hotel. Under New York law, parent corporations cannot be held liable for the actions of their subsidiaries, except in cases that support piercing the corporate veil. Traub Lieberman argued that the motion should be granted as a parent company cannot be held liable for acts committed by its subsidiary and further claimed that the parent company has never owned or operated the Hotel.
Read the court decisionRead the full story...Reprinted courtesy of
Lisa M. Rolle, Traub LiebermanMs. Rolle may be contacted at
lrolle@tlsslaw.com
The Right to Repair Act (Civ.C §895 et seq.) Applies and is the Exclusive Remedy for a Homeowner Alleging Construction Defects
February 07, 2018 —
Craig Wallace – Smith Currie McMillin Albany LLC v. Superior Court (01.18.18) ____ Cal.4th _____ (2018 WL 456728)
The California Supreme Court confirmed that the Right to Repair Act (CA Civil Code § 895, et seq. and often referred to by its legislative nomenclature as “SB800”) applies broadly to any action by a residential owner seeking recovery of damages for construction defects, regardless of whether such defects caused property damages or only economic losses. This includes the right in the Act of the builder to attempt repairs prior to the owner filing a lawsuit.
Background
Homeowners sued builder for construction defects. Included in their causes of action was a cause of action for violation of the Right To Repair Act. The Act requires that before filing litigation, a homeowner must give the builder notice and engage in a nonadversarial prelitigation process which gives the builder a right to repair the defects. The builder asked the court to stay the homeowners’ action so the prelitigaiton process could be undertaken. Rather than give the builder the repair right, the homeowners dismissed the particular cause of action from their case, leaving only other so-called common law and warranty causes of action. The common law claims sought recovery for property damage caused by the defects. The builder nonetheless asked to the Court to stay the action so it could exercise its right to repair.
The trial court, relying on
Liberty Mutual Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98, denied builder’s request to stay the action. The
Liberty Mutual Court concluded that certain common law construction defect claims fell outside the purview of the Act. Builder appealed. The Court of Appeal disagreed with
Liberty Mutual, so did not follow it, granted the builder’s request for a stay, and directed that the homeowners afford the builder the right to repair the claimed defects as provided under the Act.
The California Supreme Court affirmed, disapproving
Liberty Mutual and the subsequent cases relying on it.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Wallace, Smith CurrieMr. Wallace may be contacted at
swwallace@smithcurrie.com
Walkability Increases Real Estate Values
June 18, 2014 —
Beverley BevenFlorez-CDJ STAFFCNBC reported that environmentally-conscious Millennials are looking for homes that are within walking or biking distance to stores and work. The “areas that offer so-called walkability should see more home buyers and renters than those that don't.”
"Cities that want to thrive in our new economic and demographic realities will need to find ways to create and support more of these dynamic, productive walkable districts that are in high demand," Geoff Anderson, CEO of Smart Growth America, told CNBC. Anderson, “in conjunction with George Washington University School of Business, released a new report ranking the walkability of the nation's 30 largest metropolitan areas.”
Read the court decisionRead the full story...Reprinted courtesy of
Being the Bearer of Bad News (Sounding the Alarm on Construction Issues Early and Often) (Law Note)
October 02, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaOur recent look into termination brings up another issue important to architects and engineers– how to sound the alarm about construction or building code violations. Sometimes, a project owner may be so focused on project completion that they want to overlook the sub-par work that may be occurring in an effort to get project open “on time.” In such cases, only if a life safety violation is reported to the authority having jurisdiction will the owner finally terminate a faulty contractor from a construction project.
Even if the work is not a life/safety issue, it is important that when delivering bad news about the quality of work that your notice be early, loud, and frequent. Basically, everyone involved should be aware, through written communications, that there is an issue that needs to be addressed on site, the contractor is messing up the construction, and what needs to be done to fix the issue(s). If the owner is willing to live with the faulty work (and it is not a life/safety matter), then at least you’ve provided notice and warned them of the issue.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
Bank of America’s Countrywide Ordered to Pay $1.3 Billion
July 30, 2014 —
Patricia Hurtado – BloombergBank of America Corp.’s Countrywide unit was ordered to pay $1.3 billion in penalties for defective mortgage loans it sold to Fannie Mae (FNMA) and Freddie Mac in the run-up to the 2008 financial crisis, a little more than half of what the U.S. had requested.
U.S. District Judge Jed Rakoff in Manhattan issued the civil penalty against the Charlotte, North Carolina-based bank today in the first mortgage-fraud case brought by the federal government to go to trial.
Countrywide and Rebecca Mairone, a former executive with the mortgage lender, were found liable in October for selling thousands of bad loans to the two government-sponsored enterprises. Mairone was ordered today to pay $1 million.
Read the court decisionRead the full story...Reprinted courtesy of
Patricia Hurtado, BloombergMs. Hurtado may be contacted at