Commencing of the Statute of Repose for Construction Defects
November 08, 2021 —
David Adelstein - Florida Construction Legal UpdatesFlorida has a ten-year statute of repose which applies predominantly to construction defect claims. This can be found in Florida Statute s. 95.11(3)(c). After ten years, any rights relative to a construction defect claim are time-barred. However, the statute of repose date has been watered down and can be made to be more of a factual question due to the lack of objectivity as to the date that starts the ten-year repose clock. The watering down of the statute of repose date benefits parties asserting construction defect claims provided they strategically appreciate the question of fact that can be created when up against the statute of repose. Stated differently, when up against the clock to assert a construction defect claim, strategically develop those facts, evidence, and arguments to maximize creating a question of fact as to when the statute of repose clock commenced. Conversely, as a defendant sued for construction defects, you want to maximize the facts, evidence, and arguments to fully establish the date the statute of repose clock had to commence for purposes of a statute of repose defense.
The recent opinion in Spring Isle Community Association, Inc. v. Herme Enterprises, Inc., 46 Fla. L. Weekly D2306b (Fla. 5th DCA 2021) demonstrates the factual question associated with the clock that starts the statute of repose date. This factual question is created by Florida Statute s. 95.11(3)(c) that provides:
[T]he action [founded on the design, planning, or construction of an improvement to real property] must be commenced within 10 years after the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion or termination of the contract between the professional engineer, registered architect, or licensed contractor and his or her employer, whichever date is latest.
Spring Isle Community Association, supra. (Note, see also current s. 95.11(3)(c) version in effect per hyperlink above.)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
The Problem with One Year Warranties
June 10, 2015 —
Craig Martin – Construction Contractor AdvisorContractors often ask if they should include a one year warranty in their subcontracts. I tell them that they can, but it may be more effective to include a one-year correction period. If a contractor does include a warranty in the contract, it may actually extend the time in which a contractor may be sued. I recommend instead a Correction Period.
Typical Construction Warranties
Form construction contracts, like the AIA forms, often times contain warranty language. The AIA A201, General Conditions, contains a warranty section that covers materials, but it does not address how long the work is warranted:
“3.5 WARRANTY
The Contractor warrants to the Owner and Architect that materials and equipment furnished under the Contract will be of good quality and new unless the Contract Documents require or permit otherwise. The Contractor further warrants that the Work will conform to the requirements of the Contract Documents and will be free from defects, except for those inherent in the quality of the Work the Contract Documents require or permit.”
Instead, the AIA A201, section 13.7, limits the time by which claims must be brought to 10 years or the applicable statute of limitations.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Builder’s Be Wary of Insurance Policies that Provide No Coverage for Building: Mt. Hawley Ins. Co v. Creek Side at Parker HOA
May 01, 2014 —
David M. McLain – Higgins, Hopkins, McLain & Roswell, LLCOn the heels of a recent order regarding coverage under a Comprehensive General Insurance policy issued by Mt. Hawley Insurance Company (“Mt. Hawley”), builders should be very wary of CGL policies providing no coverage for property damage.
On January 8, 2013, District Court Judge R. Brooke Jackson granted a motion for declaratory judgment filed by Mt. Hawley. The order states that the subject insurance policies issued by Mt. Hawley to Mountain View Homes II, LLC (“MV Homes”), the builder developer of the Creek Side at Parker development (the “Project”), did not provide coverage for any of the work performed by MV Homes or its subcontractors on the Project.
MV Homes originally began construction on the Project in 2002 and completed construction in 2005. MV Homes was insured by National Fire and Marine Insurance Company (“National Fire”) and Mt. Hawley. In December 2008, Creek Side at Parker Homeowners Association, Inc. (“the HOA”) served notice on MV Homes. The HOA then instituted a construction defect lawsuit on June 1, 2009 against MV Homes and others. MV Homes initially demanded a defense and indemnity from National Fire, which provided a defense. Then, after two years, MV Homes demanded a defense and indemnity from Mt. Hawley in July 2011. Mt. Hawley denied coverage and did not provide a defense. The case was settled soon after, and National Fire reserved or assigned claims against Mt. Hawley.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Changes and Extra Work – Is There a Limit?
October 09, 2018 —
Joseph R. Young - Smith CurrieDesign and construction changes can be a challenge for everyone involved in a construction project. Designers and contractors endeavor to deliver a project that meets the owner’s needs, budget, and aesthetic considerations. As a project comes to fruition, the project frequently changes, and the parties must address and resolve the financial considerations of those changes and implement the changes at the project level. Often times the most critical aspect of a contractor’s financial success or failure of a construction project is its ability to manage changes. Contractors are sometimes faced with changes that are beyond the reasonable expectation of the original undertaking and have significant planning, scheduling, and cost implications that may not be considered or addressed in the contract’s changes clause. Changes of this magnitude may be considered “cardinal changes” and provide the contractor with recourse beyond restrictions imposed by the contract’s changes clause. But cardinal change is a risky basis for a contractor to refuse to perform additional or changed work. Even major changes can probably be more safely handled within the terms of the contract’s changes clause.
Read the court decisionRead the full story...Reprinted courtesy of
Joseph R. Young, Smith CurrieMr. Young may be contacted at
jryoung@smithcurrie.com
Trade Contract Revisions to Address COVID-19
August 23, 2021 —
David R. Cook Jr. - Autry, Hall & Cook, LLPMany trade contracts contain a clause that may protect trade contractors from catastrophic events like pandemics. These clauses are known as force-majeure clauses (covering acts of God). They basically say if these unavoidable events happen, the contractor is relieved of its obligations to the extent of the impact.
However, many common industry forms have not been updated to specifically address COVID-19. (They may be waiting to see how the courts treat their existing language first.) So to ensure impacts from COVID-19 are covered, a trade contractor should consider expressly adding it to the force-majeure clause. See the example below.
Notably, typical force-majeure clauses do not say the trade contractor gets more money. So an escalation clause could be added to the force-majeure clause.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Newmeyer & Dillion Appoints Partner Carol Zaist as General Counsel
June 22, 2016 —
Newmeyer & Dillion LLPNEWPORT BEACH, Calif. – June 21st, 2016 – Prominent business and real estate law firm
Newmeyer & Dillion LLP is pleased to announce that partner
Carol Zaist has been named the firm’s General Counsel. Zaist will report to the Managing Partner, Executive Committee and other senior level management as it relates to the firm’s governance and policy matters. Zaist’s appointment is effectively immediately.
“We are excited to have appointed Carol as the firm’s General Counsel,” said Jeff Dennis, Newmeyer & Dillion’s Managing Partner. “As we continue to expand across markets, this is another proactive measure to ensure our strategic growth and success.”
Zaist is a partner in the Newport Beach office of Newmeyer & Dillion, concentrating her practice on business litigation, real estate litigation, and probate litigation. She has significant experience advising clients in contract disputes, business and property torts, and trademark and trade secret disputes in both federal and state jurisdictions. Zaist also serves as strategic counsel, advising clients on the impact of multiple litigation matters in different jurisdictions, and integrating strategy and tasks efficiently and cohesively. She will lend this variety of experience to her new role as General Counsel for the firm.
“I am honored and thrilled to work with our managing partner and Executive Committee to assist the firm in its strategic growth and development,” said Zaist.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Blockbuster Breakwater: Alternative Construction Method Put to the Test in Tampa Bay
August 14, 2023 —
Scott Judy - Engineering News-RecordOn June 7, 2023, Tampa Bay news reporters trekked to the Sunshine Skyway bridge for a Florida Dept. of Transportation press conference that would explain the mystery behind the hundreds of curiously shaped concrete structures lining nearly the entire length of the span’s mile-plus-long south fishing pier access road.
Reprinted courtesy of
Scott Judy, Engineering News-Record
Mr. Judy may be contacted at judys@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Anchoring Abuse: Evolution & Eradication
October 09, 2023 —
Tim Capowski & Chris Theobalt - Kahana FeldOver the past few years, the plaintiff bar has expanded its use of improper anchoring tactics. Historically, improper anchoring was seen as a risky tactic in which a plaintiff’s counsel would suggest an outrageous figure for pain and suffering during summation in the hope that the lay jury would either award it or split the difference (cut the suggested figure by half) and, either way, return an excessive or runaway verdict. Plaintiff counsel deployed the tactic infrequently through the turn of the century for fear of alienating the jury by appearing greedy.
Two interrelated factors happened to change this dynamic. First, the plaintiff bar worked extremely hard in the intervening years with great success to shed its “ambulance chaser” stereotype by marketing itself as the “protector of the vulnerable”. Second, with the rise in Reptile and punitive tactics spawned in part by the publication of the Reptile handbook, the plaintiff bar also discovered that juries were not alienated by outrageous anchors as long as they were preceded by Reptile commentary essentially to “prime” the jury to punish the defendant rather than compensate the plaintiff with its award.
This is not speculation. I recall sitting outside a courtroom with one of New York’s top plaintiff attorneys in 2006 during deliberations on a catastrophic personal injury trial, during which he conceded to me that he was worried he had asked the jury for too large a figure (it was not even eight figures). A decade later in 2016, that same attorney felt no trepidation in requesting nearly $100 million for a comparable injury. He fed the jurors a steady diet of Reptile tactics from start to finish and they dutifully awarded the requested figure. Our research confirms that this two-step strategy (Reptile + improper anchor) preceded every New York nuclear verdict returned from 2010-2022. The same is almost certainly true of most nuclear verdicts in other jurisdictions.
Reprinted courtesy of
Tim Capowski, Kahana Feld and
Chris Theobalt, Kahana Feld
Mr. Capowski may be contacted at tcapowski@kahanafeld.com
Mr. Theobalt may be contacted at ctheobalt@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of