Agree First or it May Cost You Later
May 08, 2023 —
Bill Wilson - Construction Law ZoneBusiness relationships often begin before parties execute a written agreement containing the terms and conditions by which the relationship will be governed. With little more than a Letter of Intent (“LOI”) or Letter of Award (“LOA”) one party is typically pressured to begin investing time and money to start preliminary work on a project. If such LOI or LOA contains nothing more than an agreement to agree later, the performing party should minimize its investment until the later agreement is executed. A recent court decision in New York confirmed the danger to the performing party under “agreement to agree” provisions.
In Permasteelia North America Corp. v. JDS Const. Group, LLC, 2022 WL 2954131 (N.Y. Sup. CT. 7/22/22), the plaintiff subcontractor allegedly performed $1.9 million worth of preliminary work under nothing more than a LOA with an agreement to agree provision. Issues arose, and the parties never entered any later written agreement. The general contractor refused to pay the plaintiff anything for its preliminary work. In response, the plaintiff filed suit against the general contractor asserting four counts: foreclosure of its lien, breach of contract, unjust enrichment, and account stated. All four counts were based on an alleged oral “handshake deal” for subcontract work for the project. The general contractor’s LOA stated that neither party would be bound “unless and until the parties actually execute a subcontract.” During discovery, the plaintiff admitted that neither party intended to enter into any contract until its potential terms were negotiated, reduced to writing, and signed. Moreover, the plaintiff only offered one set of meeting minutes and a few project agendas to support its alleged “handshake deal.” Once these necessary undisputed facts were confirmed, the defendant moved for summary judgment on all four counts.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
Environmental Regulatory Provisions Embedded in the Infrastructure Investment and Jobs Act
January 03, 2022 —
Anthony B. Cavender - Gravel2GavelWith the enactment of this important legislation, its impact on environmental regulation and policy will be carefully analyzed by the regulated community. Such a review may be hampered by the fact that the law is not only complex but also very long (over 2000 pages!). The Infrastructure Act is mostly an appropriations and authorization law, but it includes many new policy choices. This is a brief review (which can only scratch the surface of this law) of some of the many environmentally related provisions, which are part of this new law and can be located in the pdf version of the law.
The law is composed of nine separate divisions, which are further divided into separate titles and subtitles. Division A is entitled “Surface Transportation”; Division B is the “Surface Transportation Investment Act of 2021”; Division C is “Transit”; Division D is “Energy”; Division E is “Drinking Water and Wastewater”; Division F is “Broadband”; Division G is “Other Authorizations”; Division H is “Revenue Provisions”; Division I is “Other Matters”; Division J is “Appropriations”; and Division K is “Minority Business Development.”
It is somewhat bewildering on first reading, as befits a law that is expressing the manifold policy decisions made by the Congress.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
4 Steps to Take When a Worker Is Injured on Your Construction Site
March 27, 2023 —
Zachary Perecman - Construction ExecutiveThe construction industry continues to be one of the fastest-growing labor trades. According to the
Center for Construction Research and Training, since 2019, 11.4 million U.S. workers have been employed in construction, a 25% increase from 2011. Amid this growth, the industry has remained one of the most dangerous, and workers are often at higher risk of injuries and deaths due to occupational incidents. According to the U.S. Bureau of Labor Statistics, there are 150,000 injuries on construction work sites annually.
Under Occupational Health and Safety Administration (OSHA) law, employers have a responsibility to provide a safe work environment. That includes providing a workplace that is free of serious recognized hazards. Despite best efforts in implementing risk-mitigation and safety protocols, employers must be prepared with an incident procedure should an incident occur on a jobsite. Taking immediate, clear actions can impact the severity and outcome of injuries from a workplace incident. With this in mind, employers should take the lead in implementing safety procedures for injuries on construction sites and should inform all safety site managers and workers of the steps that should be taken.
Reprinted courtesy of
Zachary Perecman, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Construction defect firm Angius & Terry moves office to Roseville
January 09, 2013 —
CDJ STAFFThe law firm Angius & Terry LLP has closed its office on River Park Drive in Sacramento and opened a Roseville office that will allow for growth. The new office at 3001 Lava Ridge Court provides more usable space in a nice area for less money, said Brad Epstein, a local partner with the firm.
Five attorneys and three staff moved to the new space in Roseville on Jan. 2. “It can house three additional attorneys — and we plan to grow,” Epstein said. The firm specializes in construction defect litigation and general corporate work for community associations.
There are about 800 community associations in the Sacramento area and a handful of small firms that divvy up the work.
“Condominium developments and homeowners’ associations never die and always have legal issues,” Epstein said.
Angius & Terry has a total of 20 lawyers in six offices, four in California and two in Nevada.
Besides Roseville, the firm has offices in Walnut Creek, Manteca, Newport Beach, Reno and Las Vegas.
Read the court decisionRead the full story...Reprinted courtesy of
Developer’s Failure to Plead Amount of Damages in Cross-Complaint Fatal to Direct Action Against Subcontractor’s Insurers Based on Default Judgment
January 21, 2019 —
Christopher Kendrick & Valerie A. Moore - Haight Brown & Bonesteel LLPIn Yu v. Liberty Surplus Ins. Corp. (No. G054522, filed 12/11/18), a California appeals court held that a developer’s failure to allege the amounts of damages sought in its cross-complaint rendered default judgments against a subcontractor void and, therefore, unenforceable against the subcontractor’s insurers in a direct action under Insurance Code section 11580(b)(2).
Yu, the owner, hired ATMI to develop a hotel. ATMI subcontracted with Fitch to perform stucco and paint work. Yu sued ATMI for construction defects and the developer cross-complained against its subcontractors, including Fitch, for breach of contract; warranty; indemnity, etc. Yu’s operative complaint prayed for damages “in an amount not less than $10,000,000, according to proof.” ATMI’s cross-complaint stated that it incorporated the allegations of Yu’s complaint “for identification and informational purposes only,” but “does not admit the truth of any allegations contained therein.” The cross-complaint also prayed for damages with respect to the various causes of action “in an amount according to proof.”
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
A Few Things You Might Consider Doing Instead of Binging on Netflix
April 13, 2020 —
Garret Murai - California Construction Law BlogGovernments throughout the world have issued “shelter in place” orders requiring that residents stay at home except for “essential” purposes. As a result, in the United States, more than a third of Americans have been ordered to stay at home. This, in turn, has had a direct impact on construction projects which have slowed or have been temporarily shuttered altogether, and it will (not may) have an impact on the flow of project funds. So what can project owners and contractors do? We’ve got a few tips.
1. Read Your Contract, Paying Particular Attention to Force Majeure, No Damages for Delay and Notice Provisions
For the most part, with the exception of statutory rights and remedies which we will discuss below, your contract spells out your rights and remedies should the proverbial “S” hit the fan. It is, in other words, the rules you agreed to, and you should know what those rules provide. Three provisions you should look for, and if they’re in your contract, you should review carefully are: (1) Force majeure provisions; (2) No damages for delay provisions; and (3) notice provisions.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
New York Developers Facing Construction Defect Lawsuit
June 26, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to The Real Deal, L Lofts condominium developers are involved in an eight million dollar lawsuit for “allegedly failing to correct extensive construction defects in the” Brooklyn, New York “building, including water leaks, defective roof construction and other alleged code violations.”
The L Lofts’ board filed suit against the American Development Group on June 19th. However, Perry Finkelman, partner and managing director at American Development Group claimed that the building had been hit by a tornado, making the allegations baseless: “While there may be issues, they weren’t properly addressed at the time. That’s not a sponsor’s responsibility to handle,” as quoted by The Real Deal.
Read the court decisionRead the full story...Reprinted courtesy of
Toll Brothers Report End of Year Results
December 11, 2013 —
CDJ STAFFThe largest luxury home builder in the U.S. saw some significant gains in their final quarter for 2013. Their pre-tax income for the year was $150.2 million, up from last year’s $60.7 million, more than doubling. The firm’s revenues went up 65% to $1.04 billion, and the average price of homes was up as well. Toll Brothers is currently selling homes in 232 communities, also increasing over 2012. Due to the upcoming acquisition of Shapell, Toll Brothers projects that at the end of 2014 they will be selling in 250 to 290 communities.
Read the court decisionRead the full story...Reprinted courtesy of