Design and Construction Defects Not a Breach of Contract
February 14, 2013 —
CDJ STAFFThe California Court of Appeals tossed out a breach of contract award in Altman v. John Mourier Construction. The decision, which was issued on January 10, 2013, sent the construction defect case back to a lower court to calculate damages based on the conclusions of the appeals court.
The case involved both design issues and construction issues. According to the plaintiffs’ expert, the design plans did not make the buildings sufficiently stiff to resist the wind, and that the framing was improperly constructed, further weakening the structures, and leading to the stucco cracking. Additionally, it was alleged that the roofs were improperly installed, leading to water intrusion. The contractor’s expert “agreed the roofs needed repair, but disputed what needed to be done to repair the roofs and the cost.”
The jury rejected the plaintiffs’ claims of product liability and breach of warranty, but found in their favor on the claims of breach of contract and negligence. The plaintiffs were awarded differing amounts based on the jury’s conclusions about their particular properties.
Both sides sought new trials. JMC, the contractor, claimed that the jury’s verdicts were “inconsistent in that the relieved JMC of liability for strict products liability and breach of warranty, but found JMC liable for breach of contract and negligence.” The plaintiffs “opposed the setoff motion on the ground that the jury heard evidence only of damages not covered by the settlements.” Both motions were denied. After this, the plaintiffs sought and received investigative costs as damages. JMC appealed this amended judgment.
The appeals court rejected JMC’s claims that evidence was improperly excluded. JMC sought to introduce evidence concerning errors made by the stucco subcontractor. Earlier in the trial, JMC had insisted that the plaintiffs not be allowed to present evidence concerning the stucco, as that had been separately settled. When they wished to introduce it themselves, they noted that the settlement only precluded the plaintiffs from introducing stucco evidence, but the trial court did not find this persuasive, and the appeals court upheld the actions of the trial court. Nor did the appeals court find grounds for reversal based on claims that the jury saw excluded evidence, as JMC did not establish that the evidence went into the jury room. Further, this did not reach, according to the court, a “miscarriage of justice.”
The court rejected two more of JMC’s arguments, concluding that the negligence award did not violate the economic loss rule. The court also noted that JMC failed to prove its contention that the plaintiffs were awarded damages for items that were covered in settlements with the subcontractors.
The appeals court did accept JMC’s argument that the award for breach of contract was not supported by evidence. As the ruling notes, “plaintiffs did not submit the contracts into evidence or justify their absence; nor did plaintiffs provide any evidence regarding contract terms allegedly breached.”
The court also did not allow the plaintiffs to claim the full amount of the investigative costs. Noting that the trial court had rational grounds for its decision, the appeals court noted that “the jury rejected most of the damages claimed by plaintiffs, and the trial court found that more than $86,000 of the costs itemized in plaintiffs’ invoices ‘appear questionable’ as ‘investigation’ costs/damages and appeared to the trial court to be litigation costs nonrecoverable under section 1033.5.”
Read the court decisionRead the full story...Reprinted courtesy of
Court of Appeals Invalidates Lien under Dormancy Clause
January 05, 2017 —
Chadd Reynolds – Autry, Hanrahan, Hall & Cook, LLPOn October 27, 2016, the Georgia Court of Appeals determined whether the Dormancy Statute, which bars the enforcement of judgments after seven years, applied to a lienholder’s action to foreclose its lien.
A property owner (“Owner”), contracted with a contractor Contractor (“Contractor”) to build a home in January 2006. Contractor purchased building materials from a supplier (“Supplier”). In September 2006, Contractor failed to pay for the materials, and Supplier filed a lien on Owner’s property in November 2006. Supplier filed a claim of lien and instituted a lien action against Contractor. In March 2007, a default judgment was entered in favor of Supplier for the lien amount.
It was not until November 2014 that Supplier sued Owner, seeking a declaration of a special lien in the amount of $14,655.65. The trial court granted Supplier’s motion for summary judgment and awarded Supplier a special lien in the amount of $14,655.65 plus $8,305 in accrued interest. Owner appealed, arguing that the lien was rendered unenforceable by the Dormancy Statute.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at
reynolds@ahclaw.com
You May Be Able to Dodge a Bullet, But Not a Gatling Gun
November 16, 2020 —
Garret Murai - California Construction Law BlogIn the days before cable, and long before Netflix, I watched my fair share of spaghetti westerns on lazy weekend afternoons. Bullets zinging past cowboys, knocking off hats, and ricocheting off rocks. But while you might get lucky and dodge a bullet, not so with a Gatling gun.*
In the next case, C. W. Johnson & Sons, Inc. v. Carpenter, Case No. B300187 (August 7, 2020), a contractor who was unlicensed during a portion of a project dodged a bullet. However, I’m not so sure that he’s going to be able to dodge the hail of bullets that are coming after.
The C. W. Johnson & Sons Case
As cases go, the C. W. Johnson & Sons case is pretty straightforward. In March 2016, Contractor C. W. Johnson & Sons, a family owned flooring company, was contracted to install flooring at Randall Carpenter’s house for a total contract price of $68,343. Work was performed between March and September 2016 including some warranty, repair and corrective work after September 2016.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
July 1, 2015 Statutory Changes Affecting Virginia Contractors and Subcontractors
June 10, 2015 —
Christopher G. Hill – Construction Law MusingsAs always seems to be the case, this year, as in others, the Virginia General Assembly has seen fit to “tweak” a few construction related statutes. All of these changes will go into effect on July 1, 2015.
The big one, and one that I posted about a while back is the change to the Virginia mechanic’s lien statute to prohibit contractual waiver of lien, payment bond or claims for additional costs prior to the furnishing of labor or materials. This one is big because it relieves a bit of the angst in the pre-contract negotiations between subcontractors and general contractors.
Another significant change, this one to the wording of Virginia Code 2.2-4309, found in House Bill 1628, clarifies the fact that this Virginia statute does not limit the amount a government contractor may claim or recover against a public body under a contract dispute. This is a big one considering the ruling in the Carnell Construction Corp. v. Danville Redevelopment Housing Authority LLC limiting such claims.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Value in Recording Lien within Effective Notice of Commencement
August 03, 2020 —
David Adelstein - Florida Construction Legal UpdatesConstruction lien priority is no joke! This is why a lienor wants to record its construction lien within an effective notice of commencement. A lien recorded within an effective notice of commencement relates back in time from a priority standpoint to the date the notice of commencement was recorded. A lienor that records a lien wants to ensure its lien is superior, and not inferior, to other encumbrances. An inferior lien or encumbrance may not provide much value if there is not sufficient equity in the property. Plus, an inferior lien or encumbrance can be foreclosed.
An example of the importance of lien priority can be found in the recent decision of Edward Taylor Corp. v. Mortgage Electronic Registration Systems, Inc., 45 Fla.L.Weekly D1447b (Fla. 2d DCA 2020). In this case, a contractor recorded a notice of commencement for an owner. While an owner is required to sign the notice of commencement that the contractor usually records, in this case, the owner did not sign the notice of commencement. Shortly after, the owner’s lender recorded a mortgage and then had the owner sign a notice of commencement and this notice of commencement was also recorded. When there is a construction lender, the lender always wants to make sure its mortgage is recorded first—before any notice of commencement—for purposes of priority and has the responsibility to ensure the notice of commencement is recorded. Here, the lender apparently did not realize the contractor had already recorded a notice of commencement at the time it recorded its mortgage.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Contractor Underpaid Workers, Pocketed the Difference
February 10, 2012 —
CDJ STAFFProperty Casualty 360 reports that the owner of a construction company in California’s Bay Area has been arraigned in San Francisco Superior Court. The fifty-seven felony counts include charges of payroll theft and insurance fraud.
San Francisco District Attorney, George Gascon is quoted as saying that Doherty’s actions “hurts the honest businesses that were unable to successfully compete for these projects which the defendant was able to underbid and win as a result of this scheme.”
Frances Ann Doherty, owner of Doherty Painting & Construction has been charged with submitting false documentation as to what wages she paid her workers. It is alleged that over three years she pocketed $600,000. Additionally, she is charged with underpaying her insurer by more than $100,000 by submitting to them the fake payroll information.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
California Homeowners Can Release Future, Unknown Claims Against Builders
June 10, 2015 —
Edward A. Jaeger, Jr. and William L. Doerler – White and Williams LLPIn Belasco v. Wells, 183 Cal. Rptr.3d 840, 234 Cal. App. 4th 409 (2015), the California Court of Appeals for the Second District addressed the question of whether a homeowner, when settling an administrative complaint against a licensed homebuilder, can release future, unknown claims. Despite the presence of a California statute, Cal. Civ. Code § 1542, stating that a general release does not extend to claims that the releasor does not know about, the court held that the homeowner’s express release of future claims was enforceable. Thus, the homeowner’s release - signed as part of a 2006 settlement of the homeowner’s construction defect claims against the defendant, a homebuilder - barred the homeowner’s 2012 claims against the builder based on latent defects in the roof of the home that the homeowner discovered in 2011.
Background
The plaintiff, David Belasco, a patent attorney, bought a newly-constructed home from the defendant-builder, Gary Wells, in 2004. Wells holds a Class B General Building Contractor license issued by the Contractors State License Board (the Board). In 2006, Belasco filed a complaint against Wells with the Board based on alleged construction defects in the home.
As a result of Belasco’s complaint to the Board, the parties engaged in arbitration. At the arbitration, both parties were represented by counsel. Wells offered to settle the dispute for the sum of $25,000 and Belasco accepted Wells’ offer.
Reprinted courtesy of
Edward A. Jaeger, Jr., White and Williams LLP and
William L. Doerler, White and Williams LLP
Mr. Jaeger may be contacted at jaegere@whiteandwilliams.com; Mr. Doerler may be contacted at doerlerw@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Patriarch Partners Decision Confirms Government Subpoenas May Constitute a “Claim” Under D&O Policy; Warns Policyholders to Think Broadly When Representing Facts and Circumstances to Insurers
January 08, 2019 —
Michael S. Levine, Sergio F. Oehninger, & Joshua S. Paster - Hunton Andrews KurthThe Second Circuit recently confirmed in Patriarch Partners, LLC v. Axis Insurance Co. that a warranty letter accompanying the policyholder’s insurance application barred coverage for a lengthy SEC investigation, which ripened into a “Claim” prior to the policy’s inception date. The opinion left intact the lower court’s finding that the SEC subpoena constituted a “demand for non-monetary relief” and thus qualified as a “Claim” under the directors and officers (D&O) insurance policy.
Reprinted courtesy of Hunton Andrews Kurth attorneys
Michael S. Levine,
Sergio F. Oehninger and
Joshua S. Paster
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Oehninger may be contacted at soehninger@HuntonAK.com
Mr. Paster may be contacted at jpaster@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of