Developer’s Failure to Plead Amount of Damages in Cross-Complaint Fatal to Direct Action Against Subcontractor’s Insurers Based on Default Judgment
January 21, 2019 —
Christopher Kendrick & Valerie A. Moore - Haight Brown & Bonesteel LLPIn Yu v. Liberty Surplus Ins. Corp. (No. G054522, filed 12/11/18), a California appeals court held that a developer’s failure to allege the amounts of damages sought in its cross-complaint rendered default judgments against a subcontractor void and, therefore, unenforceable against the subcontractor’s insurers in a direct action under Insurance Code section 11580(b)(2).
Yu, the owner, hired ATMI to develop a hotel. ATMI subcontracted with Fitch to perform stucco and paint work. Yu sued ATMI for construction defects and the developer cross-complained against its subcontractors, including Fitch, for breach of contract; warranty; indemnity, etc. Yu’s operative complaint prayed for damages “in an amount not less than $10,000,000, according to proof.” ATMI’s cross-complaint stated that it incorporated the allegations of Yu’s complaint “for identification and informational purposes only,” but “does not admit the truth of any allegations contained therein.” The cross-complaint also prayed for damages with respect to the various causes of action “in an amount according to proof.”
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Can Businesses Resolve Construction Disputes Outside of Court?
August 19, 2024 —
Scott L. Baker - Los Angeles Litigation BlogTime is of the essence in any construction project. So, if a dispute arises at any point, business owners generally wish to avoid the chance of a time-consuming case going to court.
Can California construction businesses
manage these disputes effectively outside of court? It is possible in some cases. Business owners should carefully consider these three steps.
1. Go Back to the Contract
Even if the contract is at the center of the dispute, it is important to refer to any details regarding dispute resolution included within the document. It is common for contracts to have some form of a dispute resolution clause. In such a case, both parties should follow the steps outlined in that agreement.
Read the court decisionRead the full story...Reprinted courtesy of
Scott L. Baker, Baker & AssociatesMr. Baker may be contacted at
slb@bakerslaw.com
New York Court Rules on Architect's Duty Under Contract and Tort Principles
November 05, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Traub Lieberman Straus & Shrewsberry LLP's blog, in a recent case, "which involved a five story expansion/conversion of an existing one story commercial building located in Brooklyn, New York," the architect was retained with obligations among five construction phases. Later, the condominium board alleged that construction defects existed and filed suit against contractors, engineers, and the architect.
The Court granted the Architect's motion to dismiss the complaint, holding "that the allegations of negligence under the circumstances were based on construction defects and 'as such, sound in breach of contract rather than tort.' This was so, even though plaintiff alleged 'breach of a duty of care,' a traditional tort liability concept. The Court dismissed the breach of contract claim as well, holding that a 'successor in interest' argument should not be permitted to erode the firmly established privity requirement for an architect’s contract-based liability."
Read the court decisionRead the full story...Reprinted courtesy of
Nerves of Steel Needed as Firms Face Volatile Prices, Broken Contracts and Price-Gouging
December 06, 2021 —
Richard Korman, Jonathan Barnes, & Greg Aragon - Engineering News-RecordWhen Elmhurst Group, a Pittsburgh-area developer, started collecting bids for a new mixed-use building last November, the price of the steel frame, roof and cladding panels for the $14-million project came in $382,000 higher than expected—a big enough disappointment to give Elmhurst pause. Overall material costs for the project were running more than $650,000 above what was originally calculated.
Reprinted courtesy of
Richard Korman, Engineering News-Record,
Jonathan Barnes, Engineering News-Record and
Greg Aragon, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: Waters, Walls and Pipelines
August 03, 2020 —
Anthony B. Cavender - Gravel2GavelSeveral interesting decisions have recently been made by federal and state courts.
FEDERAL APPELLATE COURTS
The U.S. Seventh Circuit Court of Appeals – ARCO Shifts from State to Federal and No Vigor for VIM
On June 18, 2020, the court decided the case of Baker, et al. v. ARCO, holding that the revised federal removal statutes authorize the removal to federal court of a state-filed complaint against several defendants by the former residents of an Indiana housing complex who contended that the defendants were responsible for the industrial pollution attributed to the operations of a now-closed industrial plant. The housing complex was constructed at the site of the former U.S. Smelter and Lead Refinery. During the Second World War, the plant produced products for the use of the government war effort, thus triggering the applicability of the federal removal statutes.
On June 25, 2020, the court decided the case of Greene, et al. v. Westfield Insurance Company. As the court notes, this is a matter that “began as a case about environmental pollution and evolved into a joint garnishment action.” An Indiana wood recycling facility, VIM Recycling, was the subject of many complaints by nearby residents that its operations and waste disposal activities exposed then to dust and odors in violation of federal law and triggered state tort law claims. VIM was sued in state court, but neglected to notify its insurer, as required by its insurance policy with Westfield Insurance. One thing led to another, and a default judgment in the amount of $ 50 million was entered against VIM. Since VIM at that point had no assets, the plaintiffs and later VIM sought recovery from Westfield. When this dispute landed in federal court, the court, after reviewing the policy, concluded that there was a provision excluding coverage when the insured knew it had these liabilities when it purchased the insurance. As a result, the lower court dismissed the lawsuit, and this decision has been affirmed by the Seventh Circuit.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
The Show Must Go On: Navigating Arbitration in the Wake of the COVID-19 Outbreak
July 20, 2020 —
Justin K. Fortescue, Zachery B. Roth & Marianne Bradley - White and Williams LLPThe recent COVID-19 outbreak has altered life for all of us, in ways both big and small. Unprecedented restrictions relating to the pandemic have forced individuals across the globe to change the ways in which they live and work. Perhaps not surprisingly, these restrictions have also changed the way we resolve disputes. Just as virtual conferencing has become the “new normal” for family gatherings and social events, it has also become the “new normal” for everything from mediation, to oral argument, to full-blown hearings.
To be sure, there are a number of advantages to conducting adversarial proceedings virtually. First and foremost, it results in substantial cost savings for the parties involved. In-person proceedings typically require significant travel expenses, including airline tickets, hotel reservations, and food and beverage stipends. The use of a virtual forum essentially eliminates these expenses, cutting costs dramatically for attorneys, clients, judges, and arbitrators alike.
Virtual conferencing also affords the opportunity for increased participation from party representatives living across the country, or even across the world. While demanding work schedules often make it impossible for multiple party representatives to attend a deposition, or even a hearing, in person, virtual proceedings require much less of a time commitment. Because these virtual proceedings require participants to spend less time away from other work-related obligations, party representatives are able to attend proceedings that they may otherwise have had to miss.
Reprinted courtesy of White and Williams LLP attorneys
Justin K. Fortescue,
Zachery B. Roth and
Marianne Bradley
Mr. Fortescue may be contacted at fortescuej@whiteandwilliams.com
Mr. Roth may be contacted at rothz@whiteandwilliams.com
Ms. Bradley may be contacted at bradleym@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Record-Setting Construction in Fargo
November 07, 2012 —
CDJ STAFFPrairie Business reports that Fargo is experiencing the most new construction it has ever seen, totaling $434 million in value, which exceeds the previous high in 2006 of $428 million. Many of the construction starts are for single family homes, although there is also an increase in construction of apartments and townhomes.
The Home Builders Association of Fargo-Moorhead also noted that there was also a large of remodeling projects. Terry Becker, the president of the HBA, said that “remodeling is just huge right now.”
Read the court decisionRead the full story...Reprinted courtesy of
Recovering Unabsorbed Home Office Overhead Due to Delay
May 30, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn the
preceding article, I discussed the use of a retrospective as-built delay analysis in a case before the Civilian Board of Contract Appeals (CBCA). This case also discussed a damages component in certain delay claims known as unabsorbed home office overhead—a challenging damages component to recover because this deals with indirect costs as opposed to direct costs.
Unabsorbed home office overhead is a damages component when the contractor is on standby, but this is NOT as easy as just claiming standby thereby you are automatically entitled to unabsorbed home office overhead. There are requirements that MUST be met.
To obtain an equitable adjustment for unabsorbed home office overhead as compensation for being on standby, [the contractor] must initially show “[1] a government-caused delay of uncertain duration,” that “[2] the delay extended the original time for performance” or precluded the contractor from finishing earlier than scheduled, and that “[3] the contractor [was] on standby and unable to take on other work during the delay period.
CTA I, LLC v. Department of Veteran Affairs, CBCA 5826, 2022 WL 884710 (CBCA 2022) quoting Nicon, Inc. v. U.S., 331 F.3d 878, 883 (Fed. Cir. 2003).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com