Tick Tock: Don’t Let the Statute of Repose or Limitations Time Periods Run on Your Construction Claims
February 28, 2022 —
Gus Sara - The Subrogation StrategistIn Wascher v. ABC Ins. Co., No. 2020AP1961, 2022 Wisc. App. LEXIS 110 (Feb. 9, 2022), the Court of Appeals of Wisconsin considered whether the plaintiffs were barred — by Wisconsin’s 10-year statute of repose for improvements to real property claims and the six-year statute of limitations for breach of contract claims — from bringing a lawsuit against the original builders of their home. The plaintiffs alleged negligence and breach of contract against the masonry subcontractors, asserting that they improperly installed the exterior stone cladding. The court found that the plaintiffs’ claims against the original builders were time-barred.
In 2005, the plaintiffs, Thomas and Pamela Wascher (the Waschers) retained Mathwig Builders (Mathwig) as the general contractor for the construction of their home in Greenville, Wisconsin. Mathwig subcontracted defendants Natural Surfaces, LLC (Natural Surfaces) and Carved Stone Creations (CSC) to install the stone cladding on the exterior walls and patio for the home. On November 3, 2008, the Township of Greenville inspected the home and granted the Waschers permission to occupy the residence. The Waschers moved into the home within the next few weeks. In early 2009, the Waschers discovered efflorescence on the stone cladding for the patio. In 2010, the Waschers hired CSC to repair the stone cladding. CSC removed some stone, which revealed that flashing had not been installed behind the stone, which caused water to infiltrate the stone and patio.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Construction Contract’s Scope of Work Should Be Written With Clarity
March 06, 2023 —
David Adelstein - Florida Construction Legal UpdatesThe scope of work section in your construction contract should never be overlooked. In numerous instances, it is overlooked which leads to a dispute as to the precise nature of the scope of work. This dispute could be the result of an ambiguity in the scope of work section. Or it could be the result of an omission. Or it could be the result of a lack of clarification. Or it could be the result of not properly reviewing and vetting the scope of work section. This is a section—whether included in the body of your contract or attached as an exhibit—you absolutely, positively want clarity. Otherwise, you are potentially setting yourself up for a future dispute that could include (i) an additional work / change order dispute, (ii) an incomplete work dispute, or (iii) a failure to properly perform your work dispute. These are all disputes you want to avoid, and many times can avoid, by going through and negotiating the scope of work section to bring clarity to this section. Remember, clarity is a positive. Ambiguity or uncertainty is a negative.
An example of such an avoidable scope of work dispute can be found in All Year Cooling and Heating, Inc. v. Burkett Properties, Inc., 2023 WL 2000991 (Fla. 4th DCA 2023). Here, an air conditioning contractor was hired to install six new split air conditioning systems. The scope of work provided that there were currently “two split systems that are currently existing, working perfectly and are not to be replaced as part of this contract.” The property manager claimed the air conditioning contractor was required to bring these two existing split air conditioning systems up to code as the contract provided that notwithstanding anything to the contrary, the contractor “will certify and shall ensure that all split systems in the building, upon completion of all the work, will be fully compliant with all codes and regulations and shall be responsible for any costs relates to the implementation and/or remediation of same.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Could You Be More Specific . . . About My Excess AI Coverage?
February 23, 2017 —
Yas Omidi - California Construction Law BlogAre you a general contractor who is pretty sure that you have additional insured coverage for some stuff under your sub-subcontractor’s excess policy? Advent, Inc. v. National Union Fire Ins. Co. of Pittsburgh, PA, Case No. H041934 (December 6, 2016) warns you to be a little more specific.
Johnson Western Gunite was the shotcrete sub-subcontractor on a job. One of its employees—specifically, Jerry Kielty—tumbled down a stairwell, sustaining severe bodily injury thereby. Kielty filed suit against the general contractor in charge of the job—Advent, Inc.—amongst others. Kielty did not name his employer Johnson in the suit. In terms of insurance:
Advent was insured under a primary insurance policy issued by Landmark American Insurance Company and an excess policy issued by Topa Insurance Company.
Read the court decisionRead the full story...Reprinted courtesy of
Yas Omidi, Wendel Rosen Black & Dean LLPMs. Omidi may be contacted at
yomidi@wendel.com
Texas Legislative Update
July 19, 2017 —
Matthew S.C. Moore & Justin (JD) D. Holzeauser – Peckar & Abramson, P.C.The marquee fight between Lt. Governor Patrick and Speaker Straus, otherwise known as the 85th Regular Legislative Session, concluded on May 29, 2017. While the political clash over the controversial “bathroom bill” will continue during the special legislative session, this article is intended to provide a brief summary of the construction-related bills that passed during the regular session and a few notable ones that did not pass. A special session has been called by Governor Abbott, but no construction-related bills were included on the agenda.
What Passed?
HB 2121 – Attorney’s fees for state breach of contract claims. A contractor who prevails on a state breach of contract claim pursuant to Chapter 2260 of the Government Code, that is also valued at less than $250,000.00, may recover attorney’s fees. By using the word “may”, the bill implies that the award of attorney’s fees will be at the discretion of the administrative law judge. This bill became law on June 15, 2017.
HB 1463 – Right to cure ADA violations. A person with a disability may assert a claim for discrimination based on a violation of the building and architectural standards established in Chapter 469 of the Government Code. However, this bill requires the claimant to provide the respondent written notice at least sixty (60) days before filing an action for the violation and further gives the respondent an opportunity to cure the alleged violation within the sixty (60) day period. The obvious benefit of this bill is that it allows the respondent, e.g., the owner or potentially the contractor, an opportunity to remediate the violation without incurring litigation costs. This bill becomes effective law on September 1, 2017.
Reprinted courtesy of
Matthew S.C. Moore, Peckar & Abramson, P.C. and
Justin (JD) D. Holzeauser, Peckar & Abramson, P.C.
Mr. Moore may be contacted at mmoore@pecklaw.com
Mr. Holzheauser may be contacted at jdholzheauser@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Best Lawyers Honors Hundreds of Lewis Brisbois Attorneys, Names Four Partners ‘Lawyers of the Year’
September 16, 2024 —
Lewis Brisbois Newsroom(August 15, 2024) - Best Lawyers has selected 171 Lewis Brisbois attorneys across 47 offices for its 31st edition of The Best Lawyers in America. It has also recognized four Lewis Brisbois partners on its "Lawyers of the Year" list: San Diego Partner Gary K. Brucker Jr. (Litigation - Real Estate); Weirton Managing Partner Michelle L. Gorman (Mass Tort Litigation/Class Actions - Defendants); Roanoke Partner Paul C. Kuhnel (Medical Malpractice Law - Defendants); and Los Angeles Co-Administrative Partner Steven R. Lewis (Product Liability Litigation - Defendants).
Please join us in congratulating the following attorneys on their Best Lawyers recognition! You can see the full list of attorneys named to Best Lawyers' Ones to Watch in America
here.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Final Furnishing Date is a Question of Fact
November 10, 2016 —
David Adelstein – Florida Construction Legal UpdatesConstruction liens need to be recorded within 90 days from the lienor’s final furnishing date on the project. This date is exclusive of punchlist or warranty work. The final furnishing date needs to be proven at trial to establish that the construction lien was timely recorded. If there is an evidentiary dispute as the final furnishing date (the contractor claims the date was “x” to establish the lien was timely and the owner claims the date was “y” to establish the lien was untimely), then the date is a question of fact to be determined by the jury.
For instance, in Best Drywall Services, Inc. v. Blasczyk, 2016 WL 6246701 (Fla. 2d DCA 2016), a contractor and owner entered into an oral agreement for a residential renovation project. The contractor recorded a construction lien after its final two invoices went unpaid. During trial, the contractor offered conflicting evidence as to when its final furnishing date on the project was. Numerous dates were offered in the record including dates that were more than 90 days prior to the date the contractor recorded its lien, meaning the lien was arguably untimely. As a result, the trial judge entered a directed verdict in favor of the owner and against the contractor on the contractor’s lien claim finding the lien was untimely recorded.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at
dma@katzbarron.com
How to Lose Your Contractor’s License in 90 Days (or Less): California and Louisiana
November 15, 2021 —
Rafael Boza - Gravel2Gavel Construction & Real Estate Law BlogHaving your Contractor’s License up and running to perform work when needed, where needed, is an indispensable compliance matter that contractors face every year. However, this indispensable process may also be cumbersome and time consuming. Knowing the regulations applicable to your business in each state and what to do, how to do it, and when to do it, is of critical importance to maintain compliance and your ability to work in different states.
In this post we will do a high-level review of reporting obligations in California and Louisiana.
California’s
Contractors’ State License Law, Bus. & Prof. Code §§ 7000 et seq., requires licensees to report various information to the Contractors State License Board (CSLB) “within 90 days” of the effective date or event. Louisiana State
Licensing Laws and Regulations, R.S. §§ 37:24 et seq. and La. Admin. Code tit. 46, XXIX, §§ 101 et seq. also require similar reporting to the Louisiana State Licensing Board for Contractors (LSLBC), sometimes “within 15 days” of the event.
Read the court decisionRead the full story...Reprinted courtesy of
Rafael Boza, PillsburyMr. Boza may be contacted at
rafael.boza@pillsburylaw.com
Massachusetts Federal Court Rejects Adria Towers, Finds Construction Defects Not an “Occurrence”
July 03, 2022 —
Eric B. Hermanson & Austin D. Moody - White and WilliamsIn an important ruling for insurers, U.S. District Court Judge Patti Saris found that Massachusetts does not follow the position taken in Cypress Point Condo Association v. Adria Towers, LLC, 226 N.J. 403, 418 (2016), i.e., it does not hold that "faulty workmanship claims [should be recognized] as ... an 'occurrence,' thus triggering coverage, 'so long as the allegedly defective work [was] performed by a subcontractor rather than the policyholder itself."
[1]
Instead, Judge Saris reaffirmed earlier Massachusetts authority holding faulty work is not an "occurrence" for coverage purposes,
[2] and found this authority applied whether or not the work in question was subcontracted.
In the alternative, Judge Saris found, even if a contractor's faulty work could be deemed an an "occurrence," such work did not constitute covered "property damage," because none of the alleged damage was "outside the scope of the work that Tocci was contractually required to fulfill as general contractor."
[3]
Reprinted courtesy of
Eric B. Hermanson, White and Williams and
Austin D. Moody, White and Williams
Mr. Hermanson may be contacted at hermansone@whiteandwilliams.com
Mr. Moody may be contacted at moodya@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of