Road to Record $199 Million Award Began With Hunch on Guardrails
June 17, 2015 —
Patrick G. Lee – BloombergIt started with a hunch about malfunctioning highway guardrails. It led to the biggest known whistle-blower award in U.S. history.
Joshua Harman, a Virginian with two small highway safety companies, made a discovery in late 2011 that perhaps only a guardrail maker could: A big competitor had changed the dimensions of its roadside safety device by as much as an inch here and there, he said, without telling federal regulators.
As designed, Trinity Industries Inc.’s ET-Plus system was meant to turn the end of a guardrail into a de facto shock absorber. The altered units, as Harman saw it, were locking up when hit, spearing cars and their occupants.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick G. Lee, Bloomberg
Harmon Tower Demolition on Hold
December 11, 2013 —
CDJ STAFFCityCenter has raised a scenario out of a blockbuster movie in which an earthquake causes the tower to fall onto the Cosmopolitan or the Crystals mall, leading to lawsuits, investigations, and “plummeting stock prices.” But that didn’t sway Clark County District Judge Elizabeth Gonzales from putting a hold on the demolition of the tower. FM Global, CityCenter’s insurer, has requested more time to examine the building’s problems in order to determine how to act on CityCenter’s claim of total loss.
Tutor Perini, the company that built the tower, agrees with the delay, since any monies from FM Global would reduce Tutor Perini’s liability. If FM Global denies the claim, the price for the builder would go up, should they fail at trial. That trial is now scheduled for April.
Read the court decisionRead the full story...Reprinted courtesy of
Fifth Circuit Requires Causal Distinction for Ensuing Loss Exception to Faulty Work Exclusion
August 29, 2022 —
Avery J. Cantor & William S. Bennett - Saxe Doernberger & VitaIn Balfour Beatty v. Liberty Mutual Ins. Co., the 5th Circuit Court of Appeals provided valuable insight on coverage available through ensuing loss exceptions to faulty work and design exclusions in builder’s risk insurance policies. In Balfour Beatty, the Court held that, in order to establish coverage through an ensuing loss exception, the ensuing loss must be causally distinct from the original excluded loss.1
Balfour Beatty, serving as general contractor for construction of a commercial office building in Houston, Texas, subcontracted with Milestone for steelwork on the project. As part of this work, Milestone welded a 2-inch metal plate to external tubing on the eighteenth floor of the building. While welding the plate in place, welding slag fell down the side of the building, damaging exterior glass windows on the floors below.
Balfour Beatty and Milestone, along with the developer, sought coverage for the damage to the windows under their builder’s risk policy, issued by Liberty Mutual. Liberty Mutual denied coverage, claiming that the damage was excluded by the policy’s “Defects, Errors, and Omissions” exclusion. The insureds sued, arguing that the ensuing loss exception to this exclusion would carve back coverage because the damage to the windows constituted an “ensuing loss.”
Reprinted courtesy of
Avery J. Cantor, Saxe Doernberger & Vita and
William S. Bennett, Saxe Doernberger & Vita
Mr. Cantor may be contacted at ACantor@sdvlaw.com
Mr. Bennett may be contacted at WBennett@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Back Posting with Thoughts on Lien Waivers
May 20, 2015 —
Christopher G. Hill – Construction Law MusingsAfter a week of being unable to post due to the rigors of my solo construction practice, I’m back on the blogging train. For those of you that missed my new musings this past week, I hope that you had a chance to look through some of the past Guest Post Friday posts for some good stuff to read.
During the course of my busy week last week, a question came up regarding the mechanic’s lien waivers that commercial construction companies routinely execute as part of the payment process. The waiver forms vary, but each essentially states that in exchange for payment the payee, whether a subcontractor or supplier (or even general contractor) waives its future rights to record a mechanic’s lien for the work that is covered by the payment received. Most if not all of these forms further require a certification that the funds paid will either be used to pay suppliers or that suppliers have already been paid. This general description is not the reason for this post.
As is always the case in the Commonwealth of Virginia where the contract is king and a court is unlikely to reinterpret any written contractual document, the devil is in how that waiver is worded. Some waivers are worded in such a way that they essentially require a payee to certify receipt of the funds prior to payment being received. These same forms require the same pre-payment certification that all suppliers and subcontractors of the payee have already been paid. In short they require a payee to both place complete trust in the payor that the check will be paid and that the check will not bounce while in many cases (often with an unstated “wink and nod”) claiming payment was already made when all know the likelihood is that it has not.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Risk of A Fixed Price Contract Is The Market
August 03, 2022 —
David Adelstein - Florida Construction Legal UpdatesWhen performing work on a fixed price or unit, there is risk that is being assumed on your end. One risk is the market. You are ultimately banking on the fact that the market is not going to make your fixed prices unprofitable. That’s not an unforeseeable occurrence because the market shifts and that shift can have a negative ripple effect.
In a recent case out of the Federal Circuit, U.S. Aeroteam, Inc. v. U.S., 2022 WL 243176 (Fed.Cir. 2022), this market risk played a role in a fixed price contract. Here, a contractor was hired by the federal government to produce ground support trailers. A key component of these trailers was a running gear. The contractor relied on a vendor for these running gears. Due to financial difficulties, the vendor had to raise its unit price for the running gears. Based on the increased price, the contractor elected to manufacture the running gears itself. The contractor asked the government if this was ok and the government approved the request. Once the contractor started manufacturing these running gears, it had an “awe” moment – the manufacturing costs were higher than anticipated. The contractor submitted a request for equitable adjustment which the government denied. The Contractor than sued the government raising three arguments to support its entitlement to additional costs: (1) constructive change; (2) cardinal change; and (3) commercial impracticability. The contractor lost on all arguments. It probably should have lost on all arguments.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Pay Loss Provision Does Not Preclude Assignment of Post-Loss Claim
July 30, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court determined that a policy's loss payment provision did not bar a post-loss assignment. One Call Prop. Servs. v. Sec. First Ins. Co., 2015 Fl. App. LEXIS 7643 (Fla. Ct. App. May 20, 2015).
After One Cell performed emergency water removal for the insured, the insured assigned his rights to policy proceeds as payment. One Cell alleged that Security First refused to reimburse the insured adequately for the services provided. One Cell filed suit, and Security First moved to dismiss. The trial court granted the motion based upon the policy's non-assignment provision.
One Cell appealed. One Cell argued post-loss assignments were valid under Florida law even when the policy contained an anti-assignment provision, and the right to payment accrued on the date of the loss.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Continuing Breach Doctrine
May 28, 2024 —
David Adelstein - Florida Construction Legal UpdatesHave you ever heard of the “continuing breach” doctrine? Probably not. It is not a doctrine commonly discussed. It’s a doctrine used to try to argue around the statute of limitations.
In an older Southern District Court of Florida case, Allapattah Services, Inc. v. Exxon Corp., 188 F.R.Ed. 667, 679 (S.D.Fla. 1999), the court explained: “Under this [continuing breach] doctrine, a cause of action for breach of a contract does not begin to accrue upon the initial breach; rather, on contracts providing serial performance by the parties, accrual of a breach of contract cause of action commences upon the occurrence of the last breach or upon termination of the contract.”
Recently, this doctrine came up in an opinion by Florida’s Fifth District Court of Appeal. In Hernando County, Florida v. Hernando County Fair Association, Inc., 49 Fla.L.Weekly D947b (Fla. 5th DCA 2024), a plaintiff appealed the trial court’s dismissal with prejudice of its breach of contract claim based on the statute of limitations. The plaintiff claimed the defendant breached the contract by its failure to substantially redevelop property. The trial court dismissed based on the statute of limitations. However, the complaint alleged the defendant’s failure to comply “with numerous other intertwined, ongoing, and continuing contractual duties and obligations.” Hernando County, supra. The Fifth District reversed based on the continuing breach doctrine: “Where the nature of the contract is continuous, statutes of limitations do not typically begin to run until termination of the entire contract.” Id. quoting and citing Allapattah Servs., Inc.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Spreading Cracks On FIU Bridge Failed to Alarm Project Team
May 20, 2019 —
Scott Judy & Richard Korman - Engineering News-RecordOn the morning of last year’s Florida International University pedestrian bridge collapse, when the engineer of record assured project team members that there were no safety risks related to cracks propagating across a part of the unusual single-truss structure, other project team members voiced mild concern, but no alarm. In hindsight, considering that the bridge had no inherent structural redundancy as it sat, incomplete, straddling a busy highway—and would suffer a sudden, catastrophic and deadly collapse just hours later—the team’s lack of urgency remains puzzling, say engineering experts contacted by ENR for comment.
Reprinted courtesy of
Scott Judy, ENR and
Richard Korman, ENR
Mr. Judy may be contacted at mailto:judys@enr.com
Mr. Korman may be contacted at kormanr@enr.com
Read the court decisionRead the full story...Reprinted courtesy of