David Adelstein - Florida Construction Legal UpdatesAn exculpatory clause in a contract is a clause aimed at relieving another party from certain liability. A disclaimer and insulation from liability. Obviously, if you are the party relieving the other party from liability, you want to consider this risk including the potential enforceability of this risk if something goes wrong. If you are the party asking for the insulation from liability, you do not want to create an exculpatory provision that disclaims and insulates you of all liability arising from the contract as it may create an illusory effect – that the agreement is nothing but a naked promise on your end because your promise is fully disclaimed and you are insulated from liability if you break your promise. This could result in an unenforceable contract.
The validity of such an exculpatory clause was at-issue in Pier 1 Cruise Experts v. Revelex Corp., 2019 WL 3024618 (11thCir. 2019). Although not a construction dispute, the exculpatory clause in this case was with two fairly sophisticated parties and expressly insulated one of the contracting parties from “any…damages regardless of kind or type…whether in contract, tort (including negligence), or otherwise.” Pier 1 Cruise Experts, 2019 WL at *7. This is a powerful exculpatory clause because it could be broadly construed to insulate that party from its own breaches of the contract.
In Florida:
[A]n exculpatory clause is enforceable so long as (1) the contracting parties have equal bargaining power and (2) the clause’s provisions are clear and unambiguous. With respect to the latter requirement, ‘the intention to be relieved from liability [must be] made clear and unequivocal and the wording must be so clear and understandable that an ordinary and knowledgeable person will know what he is contracting away.” In the same vein, exculpatory clauses are ‘strictly construed against the party seeking to be relieved of liability.’
Pier 1 Cruise Experts, 2019 WL at *7 (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Florida’s New Civil Remedies Act – Bulletpoints As to How It Impacts Construction
April 10, 2023 —
David Adelstein - Florida Construction Legal UpdatesThere has been much talk about Florida’s new Civil Remedies Act (
House Bill 837) that Governor DeSantis approved on March 24, 2023. As it pertains to construction, here is how I see it with key bulletpoints on the impact this new Act has on the construction industry:
- New Florida Statute s. 86.121 – This is an attorney’s fees statute for declaratory relief actions to the prevailing insured to determine insurance coverage after TOTAL COVERAGE DENIAL. (Note: A defense offered pursuant to a reservation of rights is not a total coverage denial.) This right only belongs to the insured and cannot be transferred or assigned. And the parties are entitled to the summary procedure set forth in Florida Statute s. 51.011 requiring the court to advance the cause on the calendar. The new statute does say it does NOT apply to any action arising under a residential or commercial property insurance policy. (Thus, since builder’s risk coverage is a form of property insurance, the strong presumption is this new statute would not apply to it.) Rather, the recent changes to Florida Statute s. 626.9373 would apply which provides, “In any suit arising under a residential or commercial property insurance policy, there is no right to attorney fees under this section.”
- Florida Statute s. 95.11 – The statute of limitations for negligence causes of action are two years instead of four years. This applies to “causes of action accruing after the effective date of this act.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Florida Chinese drywall, pollution exclusion, “your work” exclusion, and “sistership” exclusion.
May 26, 2011 —
CDCoverage.comIn Auto-Owners Ins. Co. v. American Building Materials, Inc., No. 8:10-CV-313-T-24-AEP (M.D. Fla. May 17, 2011), insured drywall supplier ABM was sued by general contractor KB Homes seeking damages because property damage to houses built by KB Homes using defective Chinese drywall supplied by ABM. ABM’s CGL insurer Auto-Owners defended ABM under a reservation of rights and filed suit against ABM and KB Homes seeking a judicial declaration of no to duty to defend or indemnify ABM against the KB Homes lawsuit. On cross motions for summary, the federal district trial court directed entry of judgment in favor of ABM and KB Homes and against Auto-Owners, holding that Auto-Owners had a duty to defend and indemnify ABM against the KB Homes lawsuit.
Read the full story…
Reprinted courtesy of CDCoverage.com
Read the court decisionRead the full story...Reprinted courtesy of
Indiana Federal Court Holds No Coverage for $50M Default Judgment for Lack of Timely Notice of Class Action
August 26, 2019 —
Anthony L. Miscioscia and Timothy A. Carroll - White and Williams LLPIn Greene v. Kenneth R. Will, a CGL insurer recently prevailed in a declaratory judgment action arising from an underlying class action alleging pollution and nuisance claims against the insured, VIM Recycling LLC, an Indiana-based waste-recycling facility.[1] “[T]his case has some whiskers on it,” the Indiana federal district court recounted in its exhaustive decision granting the insurer relief. The court relieved the insurer of indemnifying a $50 million default judgment against the insured, which, the court observed, “proved to be a bad neighbor” and “nuisance in both the legal and colloquial sense.” The court held that the insured failed to provide timely notice of the class action.
“The judgment against the [insured] came about when a group of nearby homeowners decided that they had had enough of VIM’s polluting behavior and brought this class action to recover damages for environmental violations, nuisance and negligence based on the impact of the waste facility on their homes and property,” the court explained. Eventually, the court entered a default judgment against the insured for $50,568,750, plus an award of $273,339.85 in attorney’s fees. Because the insured was “judgment-proof,” the class action plaintiffs “aligned” with the insured “hoping to collect on their monumental judgment” from the insured’s CGL insurer. Within a few weeks’ time, the class action plaintiffs sued the insurer seeking a declaration of coverage for the default judgment against the insured.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams LLP and
Timothy A. Carroll, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Supreme Court Oral Arguments: Maritime Charters and the Specter of a New Permitting Regime
February 24, 2020 —
Anthony B. Cavender - Gravel2GavelEarlier this month, the Supreme Court heard oral arguments in two important environmental cases—one that could change the approach to routine maritime charters and another that could introduce a potentially punishing permitting regime via a CWA citizen suit.
Cleaning the Delaware: CITGO Asphalt Refining Company v. Frescati Shipping Company
The CITGO case involves a large oil spill into the Delaware River, and who bears financial responsibility for the cleanup. CITGO chartered an oil tanker to bring Venezuelan crude oil to CITGO’s New Jersey refinery located on the Delaware River. The tanker struck a submerged and abandoned anchor within yards of the refinery, and a large and expensive oil spill resulted. In accordance with the Oil Pollution Act, both the shipper, Frescati Shipping Company, and the United States, paid for the immediate oil spill response, and CITGO was later sued for a large share of these costs based on the fact that it entered into a charter with Frescati, which obliged CITGO to provide a “safe berth.” The U.S. Court of Appeals for the Third Circuit held that CITGO was liable under the principles of maritime law, meaning that CITGO was strictly liable for the spill even if no one knew that the anchor was present on the floor of the river or lurking in the waters of the Delaware River. CITGO has argued that this result is unfair and poses a threat to the maritime shipping industry if it is held to be strictly liable for this spill. It appears that this is may well be the majority rule that is applied when interpreting these routinely entered maritime charters. The Court’s decision will be immensely important to the shipping industry.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
You’ve Been Suspended – Were You Ready?
April 20, 2020 —
Curtis W. Martin, Patrick J. Greene, Jr. & Levi W. Barrett - Peckar & Abramson“Effective tomorrow … the City is suspending all regular activity at construction sites in Boston.” This was just one of the surprises that greeted contractors last week. Contractors and owners with projects across the country are scrambling to comply with mandated governmental suspensions. Project participants should begin contingency planning for possible project shutdowns.
Reacting to Suspension
Your legal rights and remedies will be largely determined by your contract and the laws applicable to it. But some basic principles will be applicable depending on the source of the suspension.
Suspension by the Owner: An owner work suspension suggests review of the contract’s suspension of work clause. Federal contractors would look to the FAR Suspension of Work clause, FAR 52.242-14, but that is applicable if the suspension is by the Contracting Officer; the US would argue that a systemic suspension was a sovereign act and outside the FAR clause.
Contractors for private work and state or municipal work may have contractual suspension of work clauses. At least some suspension clauses provide relief for time and money.
Reprinted courtesy of Peckar & Abramson attorneys
Curtis W. Martin,
Patrick J. Greene and
Levi W. Barrett
Mr. Martin may be contacted at cmartin@pecklaw.com
Mr. Greene may be contacted at pgreene@pecklaw.com
Mr. Barrett may be contacted at lbarrett@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Continuous Injury Trigger Applied to Property Loss
January 07, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Seventh Circuit Court of Appeals predicted that the Wisconsin appellate courts would apply the continuous injury trigger to find coverage after the policy expired for damage caused by water infiltration. Strauss v. Chubb Indem. Ins. Co., 2014 U.S. App LEXIS 21794 (7th Cir. Nov. 18, 2014).
The insureds built their home in 1994. They purchased coverage for their home from Chubb. Coverage was in place from October 1994 through October 2005. The policy stated that coverage was limited "only to occurrences that take place while this policy is in effect." "Occurrence" was defined as "a loss or accident to which this insurance applies occurring within the policy period. Continuous or repeated exposure to substantially the same general conditions unless excluded is considered to be one occurrence."
In October 2010, the insureds discovered that water infiltration had been causing damage within the building envelope of the home. The infiltration was ongoing, beginning around the time of original construction and continuously occurring with each subsequent rainfall. Chubb denied coverage because the damage was not discovered during any of their policy periods.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Your Contract is a Hodgepodge of Conflicting Proposals
January 06, 2016 —
Craig Martin – Construction Contractor AdvisorOuch. That’s what a court called a contract to remediate petroleum contamination at a number of gas stations in New York. Sometimes, it’s hard to believe the contracts that get signed.
Environmental Risk hired Science Applications to remediate petroleum contamination at 47 gas stations. Environmental Risk had previously entered into a Professional Services Master Agreement with Science Applications, but also required Science Applications to sign three separate, but basically identical, subcontracts called the Project Specific Scopes of Work. So, right from the start, there were four contracts that could apply to Science Applications’ work.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com