Federal Miller Act Payment Bond Claim: Who Gets Paid and Who Does Not? What Are the Deadlines?
September 16, 2019 —
William L. Porter - Porter Law GroupWhen working on federal public works construction projects there are no Stop Payment Notice or Mechanics Lien remedies available to protect subcontractors’ and suppliers’ right to payment. Instead, unpaid subcontractors and suppliers must resort to making a claim for payment under a federal law known as the AMiller Act@ (40 USCS 3131 et seq.). Many claimants however, do not realize that the right to make a Miller Act claim is not available to all subcontractors and suppliers. Before committing to performing work on a federal project it is important for subcontractors and suppliers to understand whether or not a Miller Act claim will be available. For those who have no Miller Act rights, careful consideration must be given to whether it is worth the risk to take on the project. For those who have valid Miller Act claim rights, important deadlines must be considered.
Who Gets Paid Under a Miller Act and Who Does Not
For federal projects in excess of $100,000, contractors who have a contract directly with the Federal Government must obtain Miller Act Payment Bond intended for the protection of Subcontractors, laborers and material suppliers to the project.
As a general rule, every subcontractor, laborer, or material supplier who deals directly with the prime contractor and is unpaid may bring a lawsuit for payment against the Miller Act Payment Bond. Further, every unpaid subcontractor, laborer, or material supplier who has a direct contractual relationship with a first-tier subcontractor may bring such an action. The deadlines for these claims are described below.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Traub Lieberman Elects New Partners for 2020
February 24, 2020 —
Traub LiebermanTraub Lieberman is pleased to announce that
Adam P. Joffe and
Heather Fleming have been elected to the partnership effective January 1, 2020.
“Heather and Adam are terrific additions to our partnership and team. They are both effective, experienced and driven lawyers who work steadfastly on behalf of clients to meet their needs,” said Michael Knippen, firm chair.
Adam joined the firm in 2019 and is based in the firm’s Chicago office, which now includes 10 partners. He counsels and represents insurers in complex first-party and third-party coverage litigation. Adam also advises insurers on their coverage obligations under primary and excess commercial lines policies, including commercial general liability, employment practices liability, professional liability, and commercial property policies.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Claim Preclusion: The Doctrine Everyone Thinks They Know But No One Really Knows What it Means in Practice
April 25, 2023 —
Garret Murai - California Construction Law BlogGenerally, I think restraint in litigation is a good thing. Don’t go crazy on your claims, don’t go nut-so in your discovery, and don’t present your case at trial in a way that causes the judge and/or jury to raise their eyebrows or shake their heads in disbelief. But, as with nearly everything, there’s always an exception. One of which is: don’t hold back on a claim because you “think” you might be able to bring it later, because you might not be able to as the next case, 5th and LA v. Western Waterproofing Company, Inc., 87 Cal.App.5th 781 (2023), demonstrates.
The 5th and LA Case
At the outset, let me first say how much I enjoyed reading this case based on the writing alone. The case, as the 2nd District Court of Appeals states, involves “a second lawsuit about an increasingly leaky roof.”
In 2012, property owner 5th and LA hired roofing contractor Western Waterproofing Company, Inc. to remove and recoat a parking lot that served also served as the roof over retail and office space below. Western completed its work in July 2012 and almost immediately 5th and LA noticed water that the coating was failing causing water leaks to the interior of the building.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Irvine Partner Cinnamon J. Carr and Associate Brittney H. Aquino Prevail on Summary Judgment
June 17, 2024 —
Linda Carter - Kahana FeldCongratulations to Irvine Partner Cinnamon J. Carr and Associate Brittney H. Aquino for Prevailing on a Motion for Summary Judgment!
Irvine Partner Cinnamon J. Carr and Associate Brittney H. Aquino prevail on summary judgment in a slip and fall case venued in Riverside County!
Plaintiff filed a lawsuit alleging negligence against Kahana Feld’s client, a grocery store with over 50 stores throughout Southern California. Prior to Plaintiff’s fall, security cameras captured footage of a third-party customer picking up a case of water bottles near the entrance of the store. The customer tilted the case and water streamed to the floor. The customer then returned the leaky case to the pallet, picked up another case of water, and walked away. Approximately a minute and 10 seconds later, Plaintiff walked through the area, slipping on the spilled water.
Read the court decisionRead the full story...Reprinted courtesy of
Linda Carter, Kahana FeldMs. Carter may be contacted at
lcarter@kahanafeld.com
Construction Law Alert: Concrete Supplier Botches Concrete Mix, Gets Thrashed By Court of Appeal for Trying to Blame Third Party
January 21, 2015 —
Steven M. Cvitanovic and Whitney L. Stefko – Haight Brown & Bonesteel LLPOn January 8, 2015, the Second Appellate district affirmed judgment of the lower court in State Ready Mix Inc. v. Moffatt & Nichol, and barred a concrete supplier from blaming a third party consultant for the concrete supplier's failure to deliver concrete that met project specifications.
In 2012, Major Engineering Marine, Inc. was hired by a project manager to construct a harbor pier in the Channel Islands Harbor. Major hired State Ready Mix, Inc. to supply the concrete for the project. State wrote and submitted a concrete mix design and, at the request of Major, civil engineer Moffatt & Nichol reviewed and approved State's mix design at no charge.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
When to use Arbitration to Resolve Construction Disputes
February 25, 2014 —
Beverley BevenFlorez-CDJ STAFFOn the blog Construction Contractor Advisor, Craig Martin answers the question of whether arbitration is always the best choice for resolving construction claims. His answer: “Some claims may benefit from arbitration, but the benefit is not always clear.”
Martin brings forth four points to consider. First, AIA Contracts do not “push Arbitration.” Second, the cost of arbitration may be expensive: “You could well spend over $5,000 just to have the arbitrator decide your case—again, not to mention your own attorneys fees.” Third, arbitration doesn’t avoid discovery. And finally, “mediation is always an option, regardless of which way you pursue your claim.”
Read the court decisionRead the full story...Reprinted courtesy of
Pandemic Magnifies Financial Risk in Construction: What Executives Can Do to Speed up Customer Payments
August 23, 2021 —
Lori J. Drake - Construction ExecutiveConstruction businesses are waiting longer for payment in 2021, according to the newly released 2021 Construction Cash Flow and Payment Report conducted by Levelset.
According to respondents, only 10% of construction businesses get paid in full, which is a 75% drop from 2020, and only 9% get paid on time, which is a drop of 60% over last year.
The report, based on a survey of 764 construction professionals, illustrates that financial risk in the industry flowed down the payment chain. General contractors were four times more likely to get paid in 30 days, and 50% more likely to get paid in full. However, 20% of subcontractors, suppliers and other second-tier companies were kept waiting more than 60 days to collect payment.
Reprinted courtesy of
Lori J. Drake, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mediation in the Zero Sum World of Construction
October 02, 2015 —
Christopher G. Hill – Construction Law MusingsConstruction is a zero sum game. What do I mean by that? I mean that even where you, a construction professional with a great construction lawyer, have reviewed and edited a subcontract presented to you or provided a well drafted contract to the other party that contains an attorney fees provision, every dollar that you spend on litigation is a dollar less of profit.
Couple the fact that no construction company can or should bid or negotiate work with an eye toward litigation (aside from having a well written contract that will be enforced to the letter here in Virginia). Particularly on “low bid” type projects, contractors and subcontractors cannot “pad” their bids to take into account the possibility of attorney fees, arbitration, or litigation. Furthermore, the loss of productivity when your “back office” personnel are tied up dealing with discovery, phone calls, and other incidents of litigation that do nothing but rehash a bad project and increase the expense saps money from the bottom line. While the possibility of a judgment including attorney fees may soften this blow, you are still out the cash.
Read the court decisionRead the full story...Reprinted courtesy of