Federal Miller Act Payment Bond Claim: Who Gets Paid and Who Does Not? What Are the Deadlines?
September 16, 2019 —
William L. Porter - Porter Law GroupWhen working on federal public works construction projects there are no Stop Payment Notice or Mechanics Lien remedies available to protect subcontractors’ and suppliers’ right to payment. Instead, unpaid subcontractors and suppliers must resort to making a claim for payment under a federal law known as the AMiller Act@ (40 USCS 3131 et seq.). Many claimants however, do not realize that the right to make a Miller Act claim is not available to all subcontractors and suppliers. Before committing to performing work on a federal project it is important for subcontractors and suppliers to understand whether or not a Miller Act claim will be available. For those who have no Miller Act rights, careful consideration must be given to whether it is worth the risk to take on the project. For those who have valid Miller Act claim rights, important deadlines must be considered.
Who Gets Paid Under a Miller Act and Who Does Not
For federal projects in excess of $100,000, contractors who have a contract directly with the Federal Government must obtain Miller Act Payment Bond intended for the protection of Subcontractors, laborers and material suppliers to the project.
As a general rule, every subcontractor, laborer, or material supplier who deals directly with the prime contractor and is unpaid may bring a lawsuit for payment against the Miller Act Payment Bond. Further, every unpaid subcontractor, laborer, or material supplier who has a direct contractual relationship with a first-tier subcontractor may bring such an action. The deadlines for these claims are described below.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Granting of Lodestar Multiplier in Coverage Case Affirmed
November 14, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe trial court's use of a multiplier in awarding fees to the insured was affirmed by the Florida Court of Appeal. Citizens Prop. Ins. Corp. v. Laguerre, 2018 Fla. App. LEXIS 11794 (Fla. Ct. App. Aug. 22, 2018).
Following Hurricane Wilma, the insured made a claim for wind damage to her insurer, Citizens. Citizens investigated the claim and paid $8,400.77. The insured then demanded an appraisal and submitted an appraisal estimate in the amount of $60,256.79. There was no response to the appraisal demand.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Contract Construction Smarts: Helpful Provisions for Dispute Resolution
June 03, 2019 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday, Musings welcomes back Doug Reiser (@douglasreiser), though from new digs. Doug is a construction attorney, LEED AP and the principal at Reiser Legal LLC in Seattle, WA. His office provides effective construction counsel for businesses in the construction industry. He also runs the Builders Counsel Blog, a blog focused on progressive issues in Washington construction law. Doug is a former partner/member at Wolfe Law Group LLC and former owner and director of Express Lien Inc.
There are many types of attorneys out there, but there are certainly two styles: ones looking for the fight and ones trying to prevent the fight. I take the preventative approach. Client funds do not grow on trees. That old saying “an ounce of prevention is worth a pound of cure” should say a “ton of cure.” It’s that valuable.
Sometimes the problem for prevention attorneys is trying to relay that message to a construction business. The cost of smart prevention is mainly thought of as just that – a cost. But when it buys you a cure for pennies on the dollar, it’s worth it. You will know it’s worth it when you finally become engaged in a costly three year long legal proceeding over a construction dispute.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Miller Act: More Complex than You Think
October 07, 2016 —
Beverley BevenFlorez-CDJ STAFFKeith Bremer, senior partner of Bremer Whyte Brown & O’Meara LLP, has a feature article in the Fall 2016 issue of Construction Claims Magazine, and discusses how the Miller Act has been slowly changing: “This is a complex piece of legislation that is evolving and has been decided differently depending on the federal district a case is heard in,” Bremer wrote.
Bremer explained how the courts continue to rule differently in regards to the Miller Act. “Currently it seems jurisdictions are split on the issue of whether or not subcontractors should be allowed to bring both a federal and state cause of action stemming from payment by a Miller Act bond. Therefore, any surety writing these bonds should pay strict attention to how broad or narrow the federal district that would hear the claim has interpreted the scope of a subcontractor’s remedies for Miller Act claims.”
Read the court decisionRead the full story...Reprinted courtesy of
Kahana Feld Partner Jeff Miragliotta and Senior Associate Rachael Marvin Obtain Early Dismissal of Commercial Litigation Cases in New York and New Jersey
August 26, 2024 —
Rachael Marvin - Kahana FeldKF attorneys Jeff Miragliotta and Rachael Marvin recently secured early dismissal for a commercial real estate client on pre-answer motions to dismiss for two cases involving disputes over commercial properties in Union County, New Jersey and Suffolk County, New York.
Plaintiff argued it was entitled to damages in excess of 50 million dollars, including punitive damages, for claims involving trade libel, defamation, conspiracy, and tortious interference with contract and prospective economic advantage for reports that were prepared in connection with the use of a commercial building in Union County, New Jersey. KF attorneys successfully argued that the statute of limitations had run for each of plaintiff’s claims by utilizing a decision from the Supreme Court of New Jersey in an underlying case filed against Union County.
Read the court decisionRead the full story...Reprinted courtesy of
Rachel Marvin, Kahana FeldMs. Marvin may be contacted at
rmarvin@kahanafeld.com
XL Group Pairs with America Contractor’s Insurance Group to Improve Quality of Construction
November 13, 2013 —
CDJ STAFFInsurers XL Group and America Contractor’s Insurance Group have teamed up to use “Big Data” to help their clients maintain quality in construction. “Quality is the second leading cause of subcontractor defaults, and one of the biggest areas of profit loss for a General Contractor,” said Jason LaMonica, the profit center head for XL Group’s Subcontractor Default business.
ACIG says that their methods “allow us to correlate their quality assurance programs with actual claims results.” ACIG will be adding XL Group’s data to their own, which will allow contractors to “implement best practices leading to continuous improvement in their quality assurance program.”
Read the court decisionRead the full story...Reprinted courtesy of
How Retro-Commissioning Can Extend the Life of a Building—and the Planet
July 10, 2023 —
Matthew Zweibruck - Construction ExecutiveSustainability initiatives in the built environment need not be limited to new construction or other large expenditures. Aging facilities have the potential to extend their years of service while also combating greenhouse gas emissions. But what is the best course of action? From building design initiatives such as net zero and electrification to renewables and green building certifications, it can be a complicated and overwhelming field to navigate.
Building owners and property managers may question if they are pursuing the correct programs to minimize their organization’s negative impacts on the environment. With all the initiatives, buzzwords and fancy awards surrounding these initiatives, there are energy-efficiency strategies available to buildings that cut through this noise—strategies that are cost effective, quick to implement, widely abundant and result in an immediate reduction in a building’s impact on climate change.
Reprinted courtesy of
Matthew Zweibruck, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Contractors: A Lesson on Being Friendly
April 06, 2016 —
Garret Murai – California Construction Law BlogI know.
You’re just trying to be friendly.
Don’t.
Particularly when you’re a contractor bidding on a public works project.
Those dinners at swanky restaurants, tickets to The Jersey Boys, and all expense paid trips to the Napa Valley have a way of appearing less “friendly” in hindsight, and more like bribery, or as they say, “pay to play.”
In Sweetwater Union High School District v. Gilbane Building Company, California Court of Appeals for the Fourth District, Case No. D067383 (February 24, 2016), three contractors, Gilbane Building Company (“Gilbane”), The Seville Group, Inc. (“Seville”) and Gilbane/SGI Joint Venture (“Gilbane/SGI”) (collectively “Contractors”) were sued by the Sweetwater Union School District (“District”) to void their contracts with the District and for disgorgement of all monies paid to them under Government Code section 1090 after it was discovered that the Contractors had engaged in a “pay to play” scheme involving several officials of the District.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com