Panama Weighs Another Canal Expansion at Centennial Mark
August 20, 2014 —
Michael McDonald – BloombergA century after the U.S. steamship Ancon first sailed through the Panama Canal, a $5.3 billion expansion delayed by bickering contractors and angry workers is nearing completion. The problem is it might not be big enough.
With the expansion 16 months behind schedule, canal administrator Jorge Quijano said officials are studying whether to dig a fourth set of locks to handle a growing fleet of super-sized ships. Those include the 400-meter-long “Triple E” vessels capable of carrying more than 18,000 containers, four times more than current ships passing through the canal.
“We are always analyzing the market and as soon as we can economically justify it we will begin,” said Manuel Benitez, deputy administrator of the Panama Canal Authority, adding that he thinks the current expansion is sufficient for now. “If that changes and the demand exists we are ready to begin.”
Read the court decisionRead the full story...Reprinted courtesy of
Michael McDonald, BloombergMr. McDonald may be contacted at
mmcdonald87@bloomberg.net
Part I: Key Provisions of School Facility Construction & Design Contracts
May 16, 2018 —
David R. Cook Jr. - Autry, Hall & Cook, LLPWe all expect our school construction projects will go smoothly, on time and under budget. But despite our best efforts, some projects will encounter speed bumps, detours or outright roadblocks. While there are many precautions a school facility manager may take, one of the best precautions is to have solid construction and design contracts.
A good contract will account for the known risks and specify an outcome in favor of the school authority. School construction risks can be categorized into a few categories: performance risk, time risk, cost risk and political risk. Some risks are typical to all construction projects, while others are peculiar to the unique needs of school authorities.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
North Carolina Exclusion j(6) “That Particular Part”
February 10, 2012 —
CDCoverage.comIn Alliance Mutual Insurance Co. v. Dove, 714 S.E.2d 782 (N.C. Ct. App. 2011), claimant Murphy-Brown hired insured Dove to repair a broken elevator belt in a grain elevator in Murphy-Brown’s feed mill. The elevator was inside a metal duct and, to access the broken belt, Dove had to cut out a section of the duct. After replacing the belt, Dove welded the metal section back to the duct. Immediately after Dove completed the welding, dust inside the duct ignited, causing an explosion in the elevator, resulting in property damage to the elevator and other property. Murphy-Brown sued Dove for negligence seeking damages for the repair and replacement of the elevator, repair and replacement of the other property, increased grain handling costs during the repairs, and loss of use.
Read the full story…
Reprinted courtesy of CDCoverage.com
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Senior Trial Counsel Timothy McNamara Wins Affirmation of Summary Judgment Denial
August 28, 2023 —
Timothy G. McNamara - Traub LiebermanIn this appeal brought before the State of New York Appellate Division, Second Judicial Department, the court ruled in favor of Traub Lieberman’s client, a housing complex owner, affirming the denial of co-defendant landscaping company’s summary judgment motion seeking dismissal of the cross-claims asserted by the complex owner against the co-defendant.
In the underlying case, the plaintiff was allegedly injured when she slipped and fell on ice on the exterior stairs of the housing complex where she lived. The complex owner had contracted with the co-defendant to provide snow removal services for the complex. The plaintiff commenced action against both the complex owner and the landscaping company to recover damages for personal injuries. The complex owner asserted cross-claims against the landscaping company for contribution, common-law indemnification, and contractual indemnification. The landscaping company sought summary judgment dismissing the complaint and all cross-claims asserted against it, but the branch of the motion seeking dismissal of the cross-claims was denied. In the appeal brought before the Appellate Division, the court ruled in favor of Traub Lieberman’s client, the complex owner, affirming the denial of summary judgment for the cross-claims.
Read the court decisionRead the full story...Reprinted courtesy of
Timothy G. McNamara, Traub LiebermanMr. McNamara may be contacted at
tmcnamara@tlsslaw.com
Back to Basics – Differing Site Conditions
December 19, 2018 —
Tracey W. Pruiett - Smith CurrieEncountering an unexpected site condition is one of the more common risks on a construction project. A “differing site condition”, or it is sometimes called a “changed condition”, is generally understood to be a physical condition that is discovered while performing work and that was not visible or otherwise expected at the time of bidding. Often, the condition could not have been discovered by a reasonable site investigation. Examples of common differing site conditions include: soil with inadequate bearing capacity to support the building being constructed, soil that cannot be reused as structural fill, unanticipated groundwater, quicksand, mud, rock formations, or other artificial subsurface obstructions. Differing site conditions may also occur within the walls or ceilings of a renovation project such as the renovation of a hospital or historic building.
Read the court decisionRead the full story...Reprinted courtesy of
Tracey W. Pruiett, Smith CurrieMs. Pruiett may be contacted at
twpruiett@smithcurrie.com
Wildfire Threats Make Utilities Uninsurable in US West
August 12, 2024 —
Mark Chediak - BloombergTrinity Public Utilities District’s power lines snake through the lower reaches of the Cascade Range, a rugged, remote and densely forested terrain in Northern California that has some of the highest wildfire risk in the country. But for several years, the company has been without insurance to protect it from such a threat.
Trinity’s equipment was blamed for causing a 2017 wildfire that destroyed 72 homes and three years later its insurer, a California public agency called the Special District Risk Management Authority, told the utility that it would no longer cover it for fires started by its electrical lines. Trinity could find no other takers.
The utility’s exposure comes as wildfires are already flaring up across the US West in what could be a dangerous and prolonged fire season.
“If a fire were to start now that involved one of our power lines, it would likely bankrupt the utility,” said Paul Hauser, general manager of the local government-owned utility that serves about 13,000 rural customers in Trinity County, 200 miles (322 kilometers) north of Sacramento. That’s because without insurance, a lawsuit could put the utility on the hook to pay for damages to private homes and businesses, which could easily top the utility’s annual revenue of about $16 million.
Read the court decisionRead the full story...Reprinted courtesy of
Mark Chediak, Bloomberg
Five Actions Construction and Energy Risk Managers Can Take to Avoid the Catastrophic Consequences of a Cyber Attack
June 27, 2022 —
Eve-Lynn Gisonni - Saxe Doernberger & VitaWith the ever-increasing usage of technology in the construction and energy industries, risks to business operations have also increased. Property developers and construction contractors rely on electronic data and communications more than ever to streamline projects, ensure efficient and timely supply chain delivery, and facilitate immediate communications between parties. However, with this dependence upon technology comes the heightened risk of cyber criminals frustrating construction operations and driving up costs.
Similarly, as the energy sector has grown more dependent upon online networks for deliverables, vulnerabilities have become more pronounced in trades dependent upon electrical grids. When an entire electricity network must be taken offline in defense of a cyber-attack, this impacts countless industries such as hospitals and health care operations, manufacturers and suppliers, and local and interstate traffic systems.
Read the court decisionRead the full story...Reprinted courtesy of
Eve-Lynn Gisonni, Saxe Doernberger & VitaMr. Gisonni may be contacted at
EGisonni@sdvlaw.com
Hunton Insurance Team Wins Summary Judgment on Firm’s Own Hurricane Harvey Business Income Loss
March 23, 2020 —
Michael S. Levine & Michelle M. Spatz - Hunton Insurance Recovery BlogA Texas judge has ruled that Hunton Andrews Kurth is entitled to coverage from Great Northern Insurance Co., a unit of Chubb, Ltd. (“Chubb”), for losses its predecessor firm suffered when Hurricane Harvey closed its Houston office and disrupted business in 2017.
The court agreed with Hunton’s position that the policy, written specifically for a law firm, covered its business income loss until the firm’s operations were restored to their pre-loss levels. The court rejected in its entirety Chubb’s argument that coverage lasted only until the physical damage that closed the building had been repaired. Rather, siding with Hunton, the court found that the policy language affords, in addition to ordinary business income coverage during the damage period, “extended period” coverage that commences after the damaged property is repaired and after the firm’s operations resume.
From August 27 to August 31, 2017, the firm was forced to close its Houston office due to flooding and damage caused by Hurricane Harvey. While employees were permitted to return to the office on August 31, income did not return to its pre-loss level until September 14, 2017. The firm submitted a claim to Chubb for the loss sustained from August 27 to September 14, but Chubb paid only for income loss suffered during the 3-day closure period, and refused to cover the loss suffered after the building reopened.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Michelle M. Spatz, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Spatz may be contacted at mspatz@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of