Sinking Floor Does Not Meet Strict Definition of Collapse
August 17, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined that the sinking of the insured's floor caused by termites and rot deterioration did not meet the homeowners policy's definition of collapse. Stewart v. Metro. Lloyds Ins. Co., 2020 U.S. Dist. LEXIS 111527 (S.D. Tex. June 24, 2020).
Beatrice Stewart, the homeowner, heard a loud bang one night as she lay in bed. The next day, she found that the floor near her bathroom and hallway had sunk and the house was sitting lower. She admitted the house never completely fell down. Upon investigation, Lloyds found that rot in the floor joists and subfloor decking were caused by a combination of termite damage and exposure to moisture. Lloyds denied the claim.
Stewart sued. Lloyds argued the policy required an "entire collapse" of the building or any part of a building, which did not occur here. The policy defined "collapse" as "an abrupt falling down or caving in of a building or any part of a building." The record did not show that any part of Stewart's floor caved in.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Business Interruption Claim Upheld
April 01, 2015 —
Tred R. Eyerly – Insurance Law HawaiiA business interruption claim survived an appeal after it was determined the claim was satisfactorily presented to the trial court. Citadel Broadcasting Corp. v. Axis U.S. Ins. Co., 2015 La. App. LEXIS 274 (La. Ct. App. Feb. 11, 2015).
When Hurricane Katrina hit on August 29, 2005, the insured owned three radio stations that broadcast in and around New Orleans. All three stations suffered property damage and were off the air for varying periods of time.
The insured's policy with Axis covered both physical damage and business interruption (BI) losses. The policy also insured contingent business interruption income (CBI). Both ordinary BI and CBI losses were covered under a 365 day extended period of indemnity (EPI).
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Subprime Bonds Are Back With Different Name Seven Years After U.S. Crisis
January 28, 2015 —
Jody Shenn – Bloomberg(Bloomberg) -- The business of bundling riskier U.S. mortgages into bonds without government backing is gearing up for a comeback. Just don’t call it subprime.
Hedge fund Seer Capital Management, money manager Angel Oak Capital and Sydney-based bank Macquarie Group Ltd. are among firms buying up loans to borrowers who can’t qualify for conventional mortgages because of issues such as low credit scores, foreclosures or hard-to-document income. They each plan to pool the mortgages into securities of varying risk and sell some to investors this year. JPMorgan Chase & Co. analysts predict as much as $5 billion of deals could get done, while Nomura Holdings Inc. forecasts $1 billion to $2 billion.
Read the court decisionRead the full story...Reprinted courtesy of
Jody Shenn, BloombergMs. Shenn may be contacted at
jshenn@bloomberg.net
Hawaii Federal Court Grants Insured's Motion for Remand
January 12, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe federal district court, district of Hawaii, recently granted the insured's motion for remand. Catholic Foreign Mission Society of Am., Inc. v. Arrowood Indem. Co., Civ. No. 14-00420, Order Granting Plaintiff's Motion for Remand and Denying Defendants' Motion to Dismiss or Transfer (D. Haw. Dec. 30, 2014) [Order here]. [Full disclosure - our office represents the insured, Maryknoll].
Maryknoll was sued in several lawsuits filed in Hawaii state court by victims of alleged sexual abuse occurring as far back as the 1950s by members of the clergy. Maryknoll was insured during these periods under liability policies issued by various carriers. The successor of Royal Globe Insurance Company, Arrowood Indemnity Company, agreed to defend some of the underlying lawsuits, but declined to defend others. The Travelers Companies, Inc. refused to defend.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
New Defendant Added to Morrison Bridge Decking Lawsuit
March 26, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Morrison Bridge in Multnomah County, Oregon, has added a new company to their lawsuit regarding problems with the slip-resistant FRP decking, according to The Oregonian. The county has already named the installer, the supplier, and the manufacturer. Now, they have added Hardesty & Hanover, LLP, the company “that contracted with the decking manufacturer to provide engineering and design for the project.”
The Oregonian reported that “the county has identified a construction design professional who can testify that Hardesty & Hanover made errors that contributed to the Morrison Bridge's damage,” according to the amended complaint.
First, Conway construction (the deck installer) filed suit against the decking manufacturer and supplier. Then, the “county inserted itself into the suit last fall,” stated The Oregonian, and “is seeking more than $2 million to repair or replace the decking, plus damages.” A trial is scheduled for February 2015.
Read the court decisionRead the full story...Reprinted courtesy of
No Coverage for Installation of Defective Steel Framing
June 26, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe California Court of Appeal affirmed the trial court's holding that the insurer had no duty to defend claims arising out of the insureds' installation of defective steel framing in an apartment building. Regional Steel Corp. v. Liberty Surplus Ins. Corp., No. B245961(Cal. Ct. App. May 16, 2014) [decision here].
Regional Steel was a subcontractor for providing reinforced steel to the columns, walls, and floors of an apartment building under construction. Regional used 90 degree and 135 degree seismic hooks as approved by the general contractor, JSM Construction, Inc. The City building inspector issued a correction notice, however, requiring the exclusive use of the 135 degree hooks. Levels one through three had defective tie hooks and required repair. JSM refused to pay Regional's invoices and withheld $545,000. JSM had to make repairs that required opening up numerous locations in the concrete walls, welding reinforcements to the steel placed by Regional, and otherwise strengthening the inadequate installation.
Regional sued JSM for the withheld payment. JSM cross-claimed, asserting breach of contract and breach of express and implied warranties.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Warranties and the Statute of Repose – Southern States Chemical, Inc v. Tampa Tank & Welding Inc.
January 20, 2020 —
David R. Cook - AHC Construction and Procurement BlogIn a recent holding by the Georgia Court of Appeals, the court held that Georgia’s eight-year statute of repose applied to bar the project owner’s warranty claims. The renovation work by the contractor on the owner’s chemical tank constituted an improvement of real property, and thus, the statute of repose bared any claims eight years after substantial completion thereof. In addition, the court rejected the project owner’s claim that it qualified as a third-party beneficiary of an extended warranty contained in a report given by a subcontractor to the contractor.
Factual Background
In 2000, Southern States Phosphate and Fertilizer Company (“Southern States”) hired Tampa Tank & Welding, Inc (“Tampa Tank”) to renovate a tank to hold sulfuric acid. The parties’ written contract contained an express one-year warranty for material and workmanship from the date of completion. Two years later, in January 2002, the tank renovation was completed. Tampa Tank contracted with Corrosion Control Inc. (“CCI”) to design, assist with, and test the cathodic corrosion system. CCI provided only consultation and did not provide any onsite installation. Upon completion of installation, CCI supplied a report to Tampa Tank that the system was properly installed and fully functioning. Additionally, a post–installation report from CCI to Tampa Tank calculated an estimated life expectancy of forty-three to forty-five years.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Assessing Defective Design Liability on Federal Design-Build Projects
March 22, 2021 —
Dirk Haire, Adam Hamilton & Dana Molinari - ConsensusDocsA common misconception by many government officials is that a design-builder is always responsible for every design error or omission on a design-build project. This article examines the actual liability standard applied by the courts and boards of contract appeals when a design defect arises on a federal design-build project.
Background: Design-Build Contracts and the Spearin Doctrine
Design-build contracts combine the design and construction elements of a construction project into one contract. Design-build contracts often include two types of specifications: design and performance. Design specifications may set forth various parameters, such as precise measurements, tolerances, and materials. In doing so, the specifications create a fixed “roadmap” governing a contractor’s performance of the project. Performance specifications, on the other hand, set forth “operational characteristics” to achieve a particular objective or standard, but generally leave the details to the contractor.
Reprinted courtesy of
Dirk Haire, Fox Rothschild LLP,
Adam Hamilton, Fox Rothschild LLP and
Dana Molinari, Fox Rothschild LLP
Mr. Haire may be contacted at dhaire@foxrothschild.com
Mr. Hamilton may be contacted at ahamilton@foxrothschild.com
Ms. Molinari may be contacted at dmolinari@foxrothschild.com
Read the court decisionRead the full story...Reprinted courtesy of