Excess Policy Triggered Once Retention Paid, Even if Loss Not Covered By Excess
July 23, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Fifth Circuit determined that the Umbrella policies took effect once the primary insurance was exhausted by claims not covered by the Umbrella policies. Indem. Ins. Co. of N. Am. v. W&T Offshore, 2014 U.S. App. LEXIS 11775 (5th Cir. June 23, 2014).
W&T had primary and Umbrella/Excess coverage to protect its offshore oil rigs from hurricane damage. The primary policies covered property damage and third party claims. The Umbrella policies only covered third-party claims. All policies covered Removal of Debris (ROD).
In September 2008, Hurricane Ike caused damage to 150 offshore platforms in which W&T had an interest. W&T submitted over $150 million in claims for property damage to the primary carriers. The primary policies had a $10 million self-insured retention (SIR). The primary policies covered $150 million in coverage over the $10 million SIR. Anticipating that W&T would submit all of its ROD claims, which were estimated to exceed $50 million, the Umbrella carriers filed suit for a declaratory judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Sixth Circuit Lifts Stay on OSHA’s COVID-19 Temporary Emergency Standards. Supreme Court to Review
January 10, 2022 —
Garret Murai - California Construction Law BlogAs we round out the year, here’s a bit of news, with more likely to come, regarding the U.S. Department of Occupational Safety and Health Administration’s (OSHA) COVID-19 Temporary Emergency Standards (ETS).
As we
wrote earlier, on November 4, 2021, OSHA issued its ETS which applies to private employers with 100 or more employees (Covered Employers). Among other things, the ETS requires Covered Employers to have a COVID-19 vaccination policy requiring all employees to be fully vaccinated with certain exceptions, to provide for weekly testing of non-fully vaccinated employees, and to require face coverings. Under the ETS, Covered Employers were required to comply with the ETS other than the testing requirements by December 6, 2021 and to comply with the testing requirements beginning January 4, 2022.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
In Search of Cement Replacements
October 19, 2017 —
Aarni Heiskanen - AEC BusinessCould we replace cement as the vital element in concrete some day? We look at two alternative answers to this question.
The Problems with Cement
Portland cement dominates in the construction and road building industries. From an environmental point of view, cement is not the perfect solution. The cement industry accounts up to 7% of the world’s carbon dioxide emissions. For every 600 kg of cement, approximately 400 kg of CO2 is released into the atmosphere.
It is possible to recycle concrete by crushing it and using the gravel e.g. in road construction. However, the demand for new concrete is huge and increasing. According to The Washington Post, China used more cement between 2011 and 2013 than the U.S. used in the entire 20th Century. The worldwide production of cement has increased from 3.3 billion tons in 2010 to 4.2 in 2016. Even that is not enough; shortage of cement is a real problem in some countries.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi
New Orleans Reviews System After Storm Swamps Pumps
August 17, 2017 —
Pam Radtke Russell - Engineering News-RecordThe city of New Orleans will hire an independent team of engineers to evaluate the problems that led to severe flooding following an Aug. 5 rainfall of up to 10 in. The decision followed the revelation that 16 of the city’s pumps were not working, despite claims the system was at capacity. Further, the power system that operates those pumps was severely crippled.
Read the court decisionRead the full story...Reprinted courtesy of
Pam Radtke Russell, ENRMs. Russell may be contacted at
Russellp@bnpmedia.com
Emotional Distress Damages Not Distinct from “Annoyance and Discomfort” Damages in Case Arising from 2007 California Wildfires
November 21, 2017 —
Kirsten Lee Price & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPOriginally published by CDJ on February 16, 2017
In Hensley v. San Diego Gas & Elec. Co., (No. D070259, filed 1/31/17), the California Court of Appeal for the Fourth Appellate District held that emotional distress damages are available on claims for trespass and nuisance as part of “annoyance and discomfort” damages.
In Hensley, plaintiffs sustained fire damage to their home and property during the 2007 California wildfires. The Hensleys were forced to evacuate as the fires advanced. Although their home was not completely destroyed, it sustained significant damage and they were not able to return home permanently for nearly two months. Thereafter, the Hensleys filed suit against San Diego Gas and Electric Company (“SDG&E”) asserting causes of action for trespass and nuisance, among others. Mr. Hensley, who had suffered from Crohn’s disease since 1991, further claimed that as a result of the stress from the fire, he experienced a substantial increase in his symptoms and his treating physician opined that “beyond a measure of reasonable medical certainty... the stress created by the 2007 San Diego fires caused an increase of [Mr. Hensley’s] disease activity, necessitating frequent visits, numerous therapies, and at least two surgeries since the incident.” SDGE moved, in limine, to exclude evidence of Mr. Hensley’s asserted emotional distress damages arguing he was not legally entitled to recover them under theories of trespass and nuisance. The trial court agreed and excluded all evidence of such damages.
Reprinted courtesy of
Kirsten Lee Price, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker, Haight Brown & Bonesteel LLP
Ms. Price may be contacted at kprice@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Unlocking the Potential of AI and Chat GBT in Construction Management
September 11, 2023 —
Matthew DeVries - Best Practices Construction LawThe construction industry is one of the most complex and challenging sectors. Projects can be highly demanding and require a significant amount of planning and coordination to complete successfully. However, with advancements in technology, specifically the use of artificial intelligence (AI) and chat GBT, the construction industry can experience a transformation in how it operates.
One of the significant challenges in construction projects is the management of data. Information is collected from various sources and needs to be organized and analyzed to make informed decisions. AI can play a significant role in data analysis by providing real-time insights into the project’s progress. This can help in predicting potential delays, identifying areas where cost savings can be made, and even improve safety measures.
Chat GBT, a natural language processing tool, can assist in project management by acting as a virtual assistant to construction managers. The software can be programmed to answer questions about the project, provide updates on the progress, and even suggest solutions to potential problems. This can help in reducing the workload of the project manager and allow them to focus on other critical tasks.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew DeVries, Burr & Forman LLPMr. DeVries may be contacted at
mdevries@burr.com
Traub Lieberman Attorneys Named 2019 Super Lawyers
November 04, 2019 —
Traub LiebermanRelated Attorneys:
Jonathan R. Harwood,
Michael K. Kiernan,
Michael S. Knippen,
Meryl R. Lieberman,
Christopher Russo,
Scot E. Samis,
Lisa L. Shrewsberry,
Stephen D. Straus,
Richard K. Traub,
Cheryl P. Vollweiler,
Brian C. Bassett,
Jessica N. Kull,
Jeremy S. Macklin,
Dana A. Rice,
Burks A. Smith, III,
Jason Taylor
Ten Traub Lieberman attorneys have been named 2019 Super Lawyers and seven named 2019 Rising Stars. The honored attorneys represent five of the firm's seven offices and nearly all of its service areas.
Super Lawyers, a Thomson Reuters business, is a rating service of outstanding lawyers from more than 70 practice areas, who have attained a high degree of peer recognition and professional achievement. The annual selections are made using a patented multiphase process that includes a statewide survey of lawyers, an independent research evaluation of candidates and peer reviews by practice area.
Read the court decisionRead the full story...Reprinted courtesy of
Sometimes You Get Away with Default (but don’t count on it)
July 27, 2020 —
Christopher G. Hill - Construction Law MusingsAs an almost universal rule here in Virginia, failing to show up for court or respond to a lawsuit is a bad idea. Consequences include default judgment against you without the right to defend or make your case. Courts simply enter judgment and the consequences of that judgment will follow.
However, and as is often the case around here, there are small exceptions where the courts of Virginia allow the defaulting party off the hook. Sullivan Mechanical Contractors, Inc. v. KBE Building Corporation is just such a case. In Sullivan Mechanical, the Federal District Court for the Western District of Virginia was faced with a Motion to Vacate Default Judgment from KBE. The facts are laid out in the opinion, but basically come down to the usual subcontractor not paid by the general contractor and general contractor has reasons for non-payment. Subcontractor, Sullivan Mechanical, sued KBE and KBE failed to respond in a timely manner. One day after the deadline for response had passed, Sullivan moved for entry of default and the clerk entered the default that same day. KBE moved to vacate the default a mere 6 days after entry of default.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at