Texas Court of Appeals Conditionally Grant Petition for Writ of Mandamus to Anderson
April 25, 2011 —
Beverley BevenFlorez CDJ STAFFThe Texas Court of Appeals conditionally grant mandamus relief to Anderson Construction Company and Ronnie Anderson (collectively “Anderson”)… from the trial court in a construction defect lawsuit filed by Brent L. Mainwaring and Tatayana Mainwaring. See Tex. Prop. Code Ann. 27.001-.007 (West 2000 & Supp. 2010). Relators contend the trial court abused its discretion by compelling discovery while the case was abated by operation of law.
The Court of Appeals opinion describes what led up to the proceedings: “The Mainwarings’ original petition identified certain defects in their Anderson-constructed home. Those defects concerned the roof trusses and framing, air conditioning, mortar and masonry, exterior doors and windows, and weep holes. With respect to the five areas of defects identified in their original petition, the Mainwarings gave Anderson the statutorily required notice on January 13, 2010. After implementing agreed extensions, Anderson made an offer of settlement for the defects the Mainwarings identified in their notice. Almost eight months later, the Mainwarings filed an amended petition adding defects they had not included in their original petition and notice. The additional defects the Mainwarings included in their amended petition had not been addressed by Anderson’s offer of settlement.”
Following these events, Anderson claimed the Mainwarings did not respond in writing to their settlement offer. “Anderson filed a verified plea in abatement on December 2, 2010. In the trial court, Anderson claimed that the Mainwarings failed to respond in writing to Anderson’s settlement offer, as required by Section 27.004(b) of the RCLA. See Tex. Prop. Code Ann. 27.004(b)(1). The Mainwarings moved to compel discovery responses from Anderson. The Mainwarings alleged that they rejected Anderson’s settlement offer, and that if their response was insufficient, they contend that Anderson’s offer was rejected by operation of law on the twenty-fifth day after the Mainwarings received it. See Tex. Prop. Code Ann. 27.004(i). The Mainwarings’ motion to compel was not supported by affidavit. See Tex. Prop. Code Ann. 27.004(d)(2). On January 13, 2011, Anderson filed a verified supplemental plea in abatement. Anderson alleged that the Mainwarings failed to provide written notice concerning the newly alleged defects and complained the Mainwarings were attempting to circumvent the inspection and resolution procedure of the RCLA. Over Anderson’s objection that the lawsuit had been abated, the trial court granted the Mainwarings’ motion to compel discovery.”
After listening to both sides, the Court of Appeals offered this reasoning for their opinion: “The parties do not dispute that Anderson inspected the property before the Mainwarings alleged the existence of additional defects in their amended pleading, nor do the Mainwarings claim that Anderson has been given an opportunity to inspect the additional defects the Mainwarings identified in their amended pleadings. We conclude the trial court did not have the discretion to deny or lift the abatement until the Mainwarings established their compliance with the statute. In other words, the Mainwarings are required to provide Anderson a reasonable opportunity to inspect the additional defects identified by their amended pleading, which will allow Anderson the opportunity to cure or settle with respect to the newly identified defects.”
The Court of Appeals spoke directly on the issue of mandamus relief: “The Mainwarings contend that mandamus relief is not available because the trial court’s ruling does not prevent Anderson from making settlement offers during the discovery process. ‘An appellate remedy is “adequate” when any benefits to mandamus review are outweighed by the detriments.’ In re Prudential Ins. Co. of Am., 148 S.W.3d 124, 136 (Tex. 2004). The failure to abate a case is typically not subject to mandamus. See In re Allstate Cnty. Mut. Ins. Co., 85 S.W.3d 193, 196 (Tex. 2002) (citing Abor v. Black, 695 S.W.2d 564, 567 (Tex. 1985)). In this case, however, the case was abated by operation of law. By ignoring the statutory abatement, the trial court interfered with the statutory procedure for developing and resolving construction defect claims. See In re Kimball Hill Homes Tex., Inc., 969 S.W.2d 522, 525 (Tex. App. Houston [14th Dist.] 1998, orig. proceeding) (An appeal provides an inadequate remedy for the trial court’s failure to observe automatic abatement pursuant to the RCLA.). The benefits of mandamus review are not outweighed by the detriments of mandamus review in this case.“
In conclusion, “The trial court had no discretion to compel discovery while the case was abated, and Anderson, who has been compelled to respond to discovery during a period the case was under an automatic abatement, has no adequate remedy on appeal. Accordingly, we conditionally grant the petition for writ of mandamus. The writ will issue only if the trial court fails to vacate its order of February 3, 2011, and fails to refrain from proceeding with the case until a motion to reinstate is filed that establishes compliance with the notice and inspection requirements of the Residential Construction Liability Act.”
Read the trial court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Boston Team Secures Summary Judgment Dismissal on Client’s Behalf in Serious Personal Injury Case
October 21, 2024 —
Lewis Brisbois NewsroomBoston, Mass. (October 14, 2024) - Boston Managing Partner Kenneth B. Walton and Partner Matthew M. O' Leary recently secured summary judgment on behalf of a civil engineering firm in a serious personal injury matter arising from a trip-and-fall incident in a mall parking lot.
The client was retained to provide site civil engineering design for the parking lot of a local mall. The design included multiple bioretention areas known as rain gardens. In November of 2019, a woman tripped and fell while attempting to cross a rain garden to reach her car. She suffered significant bodily injuries, including a fracture of the cervical spine that resulted in partial paralysis.
The woman and her husband sued the mall's owner for negligence and loss of consortium in June 2021. The owner, in turn, impleaded Lewis Brisbois' client and the lot's builder, asserting third-party claims for contribution, contractual and common law indemnity, and breach of contract. In addition, the builder cross-claimed against Lewis Brisbois' client for contribution and common law indemnity.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Design & Construction Case Expands Florida’s Slavin Doctrine
January 21, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to Amanda Baggett of Rogers Towers, Florida’s “Fourth District Court of Appeal appears to have expanded the Slavin doctrine in the context of design professional liability” in the case McIntosh v. Progressive Design and Engineering, Inc. (Jan. 7, 2015). McIntosh, a personal injury case, involved whether the design and construction of an intersection with multiple traffic signals in close proximity created confusion for drivers.
Baggett stated that McIntosh expanded the Slavin doctrine in two ways: “first, the ruling eliminates the requirement that the ultimate owner of a project accept the project before the Slavin doctrine may be invoked. Second, the decision applies the Slavin doctrine to completed and accepted design plans without regard to the completion of the project for which they were prepared.”
Read the court decisionRead the full story...Reprinted courtesy of
Dave McLain included in the 2023 edition of The Best Lawyers in America
March 06, 2023 —
David M. McLain – Colorado Construction LitigationColleagues and friends:
I am pleased to share with you that I have been recognized in the 2023 edition of The Best Lawyers in America for my work in construction law. This honor comes as a surprise and is a testament to the dedication and hard work of my team at Higgins, Hopkins, McLain & Roswell, LLC.
As many of you know, my practice focuses on the defense of complex construction lawsuits on behalf of developers, general contractors, and other construction professionals. I have been fortunate enough to work with some of the largest home builders and general contractors in the state and country, regional and custom builders, and numerous insurance carriers over the years. Through these experiences, I have been able to gain valuable insights into the construction industry, and I am proud to be considered an expert in this field.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Scaffolding Purchase Suggests No New Building for Board of Equalization
July 30, 2014 —
Beverley BevenFlorez-CDJ STAFFEmployees at California’s Board of Equalization spoke out against the Brown administration after the state purchased new scaffolding for the defect-riddled building, rather than finding a new facility, reported the Sacramento Bee. The existing scaffolding was leased for $10,000 per month, but the lease expired, prompting the purchase of new scaffolding for about $100,000.
The board’s Chairman Jerome Horton stated “that while the change may make financial sense in the short term, it sends a signal that the Department of General Services intends to keep Equalization’s 2,200 or so employees in the troubled building,” according to the Sacramento Bee.
Building problems include “toxic mold, defective elevators, leaking windows, corroded wastewater pipes, floods, and exterior glass panels that spontaneously break or pop off.” So far, $2.3 million has been paid “in connection with building-related employee injury claims” along with $60 million in repairs. However, an additional $115 million is estimated to completely fix the defects.
Read the court decisionRead the full story...Reprinted courtesy of
Yellowstone Park Aims for Quick Reopening After Floods
July 03, 2022 —
The Associated Press (Matthew Brown & Amy Beth Hanson) - BloombergGardiner, Mont. (AP) -- Most of Yellowstone National Park should reopen within the next two weeks — much faster than originally expected after record floods pounded the region last week and knocked out major roads, federal officials said.
Yellowstone Superintendent Cam Sholly said the world-renowned park will be able to accommodate fewer visitors for the time being, and it will take more time to restore road connections with some southern Montana communities.
Park officials said Sunday they'll use $50 million in federal highway money to speed up road and bridge repairs. There’s still no timetable for repairs to routes between the park and areas of Montana where the recovery is expected to stretch for months.
Yellowstone will partially reopen at 8 a.m. Wednesday, more than a week after more than 10,000 visitors were forced out of the park when the Yellowstone and other rivers went over their banks after being swelled by melting snow and several inches of rainfall.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
Albert Reichmann, Builder of NY, London Finance Hubs, Dies at 93
January 17, 2023 —
Laurence Arnold - BloombergAlbert Reichmann, the longtime president of his family’s Olympia & York Developments Ltd., builder of the World Financial Center in New York and the first phase of Canary Wharf in London, has died. He was 93.
He died on Dec. 17, according to the National Post and a notice on the website of Steeles Memorial Chapel, a Toronto-area funeral home.
As the eldest of the three Orthodox Jewish brothers behind Olympia & York, Reichmann held the title of president. In practice, his brother Paul — who died in 2013 — was the company’s “idea man and deal-doer,” in the words of Anthony Bianco, a former Businessweek writer whose book on the family called Olympia & York “the greatest property development company in Western history.”
Before its 1992 bankruptcy, it was the largest private owner of commercial property in New York City.
Forbes magazine calculated the brothers’ cumulative net worth at $9.2 billion at its height in 1988, making them among the world’s richest people.
Read the court decisionRead the full story...Reprinted courtesy of
Laurence Arnold, Bloomberg
Substantial Completion Explained: What Contractors & Owners Should Know
January 17, 2022 —
Travis Colburn - Ahlers Cressman & SleightA project’s Substantial Completion date is a critical construction milestone for contractors and owners. Depending on the contract, the date of Substantial Completion has project-specific contractual and statutory consequences.
Substantial Completion is an “event” – there is no universal definition of the term. It is generally understood to be (1) a point in time (2) when work performed by the contractor is sufficiently complete (3) where it can be used or occupied for the owner’s intended purpose. The date of Substantial Completion is generally established at the time of contract formation (either as a negotiated or a contract set date), and that date may be adjusted over the course of a project to account for excusable delays.
As a construction professional, your attorney should review and tailor any written agreement to your project-specific needs and risk tolerances prior to execution. Savvy construction professionals often start with standard form agreements promulgated by the American Institute of Architects (“AIA”), the Design-Build Institute of America (“DBIA”), or the Engineers Joint Contract Document Committee (“EJCDC”) as the basis for their construction contracts. The AIA, DBIA, and EJCDC standard forms each contains contract provisions relating to when and what happens once Substantial Completion has occurred, subject to any agreed-to, project-specific deviations.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com