Delays and Suspension of the Work Under Fixed Price Government Contract
July 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesHere is an interesting fact pattern and case decided by the Civilian Board of Contract Appeals dealing with (1) force majeure type events and epidemics (Covid-19); (2) suspension of the work; and (3) delays. These are three topics important to all contractors including federal contractors.
In Lusk Mechanical Contractors, Inc. v General Services Administration, 2024 WL 1953697, CBCA 7759 (CBCA 2024), a contractor entered into a fixed price contract with the government to repair, replace, and modernize site and building systems at a federal building. The contractor commenced work right before Covid-19. When Covid-19 hit, the government issued the contractor a two-week suspension of work notice on March 27, 2020. The suspension of work allowed off-site administrative work to continue but suspended on-site physical work. The government extended the suspension of work three more times. The contractor could resume work on the exterior on June 1, 2020, but was not permitted to resume work on the interior until July 20, 2020. On the same date that the contractor was able to commence interior work, it submitted a modification for delay caused by the suspension – 64 days for the time period the entire site shutdown, and 51 days for the interior work shutdown.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
A Networked World of Buildings
November 21, 2022 —
Pieter Pauwels - AEC BusinessBuildings are living things. Buildings change shape every day and every minute. They are used by plenty of people, endlessly. Buildings shape our context and environment, and they impact our well-being to a large extent. Buildings constantly change their behavior under the influence of external conditions and occupants. We have an interest in engineering these buildings and making them as comfortable and pleasant as possible. Instead of treating buildings as static monuments that happen to be in our environment, it makes sense to treat them as living things that change incessantly, with streams of people, streams of materials and goods, and as ever-changing ecosystems of living beings.
And so, we must engineer the knowledge and information of our buildings! We need to provide our buildings with a set of brains, brains that evolve and continuously track the state of the facility and all of its internals: systems, materials, demountable elements, furniture, and people. The brains hold a snapshot of the building at any moment and allow us to ensure that this living building responds in a useful and likable manner (comfort). And this needs efforts from us human beings, and not only from ‘the AI.’
Read the court decisionRead the full story...Reprinted courtesy of
Pieter Pauwels, AEC BusinessMr. Pauwels may be contacted at
p.pauwels@tue.nl
Three's a Trend: Second, Fourth and Ninth Circuits Uphold Broad "Related Claims" Language
February 23, 2016 —
Greg Steinberg – White and Williams LLPThe hallmark of a claims-made insurance policy is that the policy only provides coverage for claims that are “first made” during the policy period. As noted by the Texas Supreme Court, “for the insurer, the inherent benefit of a claims-made policy is the insurer's ability to close its books on a policy at its expiration and thus to attain a level of predictability unattainable under standard occurrence policies.”[1]
To ensure this “level of predictability,” claims-made insurance policies contain provisions stating that all “Related Claims” will be treated as a single claim deemed first made at the time the earliest of such claims was made. The “Related Claims” provision is an issue that comes up time and again – claims can span years, especially in the context of regulatory investigations, which often culminate in enforcement proceedings and litigation. This inevitably leads to disputes regarding whether later claims can be related back to the earlier claim, an issue that becomes even thornier when different insurers participate on different policy years.
Over time, case law on “Related Claims” has been mixed and somewhat inconsistent, with each case tending to hinge on its own unique set of facts, making it difficult to identify a clear standard for determining whether claims are related. However, three recent decisions out of the Second, Fourth and Ninth Circuits show that courts are increasingly deferring to the plain language of the policy and applying these provisions broadly.
Read the court decisionRead the full story...Reprinted courtesy of
Greg Steinberg, White and Williams LLPMr. Steinberg may be contacted at
steinbergg@whiteandwilliams.com
Legislative Update: Bid Protest Law Changes to Benefit Contractors
November 24, 2019 —
Brett M. Hill - Ahlers Cressman & Sleight PLLCA new statute became effective July 28, 2019 that benefits contractors who have bid protests in Washington. A bid protest is the only way for disappointed bidders to challenge irregularities in the public bidding process on public works projects. Bid protests ensure the integrity of the public bidding system and are the contractor’s only remedy if its bid is improperly rejected or the winning bidder has errors in its bid that render it nonresponsive.
Under the old law, a contractor was required to submit their bid protest within 2 days after the bid opening. The problem was that a contractor often does not know the basis to protest an award without seeing the other bids to determine whether the winning bid was responsive. Many owners provide copies of the bids if requested at the bid opening, but some contractors found that owners were refusing to provide copies of the other bids until after the 2-day protest period expired.
The new law, which passed this last Legislative session[1], states that a contractor has two days after the bid opening to either submit a written protest or request copies of the competing bids. If the contractor requests copies of the competing bids from the owner, the contractor then has until 2 days after the competing bids are provided by the owner before the contractor is required to submit its bid protest.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers Cressman Sleight PLLCMr. Hill may be contacted at
brett.hill@acslawyers.com
US Moves to Come Clean on PFAS in Drinking Water
September 18, 2023 —
Pam McFarland, Debra K. Rubin & Mary B. Powers - Engineering News-RecordCongress has allocated billions of dollars to address contamination caused by the ubiquitous class of “forever” chemicals known as PFAS—with billions more also earmarked in recent legal settlements with manufacturers—but drinking water managers, construction sector experts and other stakeholders say the true cost of cleanup could be much higher.
Reprinted courtesy of
Pam McFarland, Engineering News-Record,
Debra K. Rubin, Engineering News-Record and
Mary B. Powers, Engineering News-Record
Ms. McFarland may be contacted at mcfarlandp@enr.com
Ms. Rubin may be contacted at rubind@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
No Coverage for Additional Insured
December 17, 2015 —
Tred R. Eyerly – Insurance Law HawaiiTwo insurers disputed who was responsible for coverage the additional insured contractor. Endurance Am. Spec. Ins. Co. v. Century Sur. Co., 2015 U.S. App. LEXIS 19194 (2nd Cir. Nov. 4, 2015). The district court granted summary judgment to Endurance, finding there was coverage for the additional insured general contractor after being sued by an employee of a subcontractor.
Century's policy included an Action Over Exclusion clause, which excluded insurance coverage for injury to certain employees as follows:
Exclusions:
. . .
e. Employer's Liability
"Bodily injury" to:
(1) an "employee" of the
named insured arising out of and in the course of:
- (a) Employment by the named insured; or
- (b) Performing duties related to the conduct of the named insured's business.
The named insured was Pinnacle Construction & Renovation Corp.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Toronto Contractor Bondfield Wins Court Protection as Project Woes Mount
May 27, 2019 —
Scott Van Voorhis - Engineering News-RecordA Toronto area contractor at the center of a series of delays to major projects in Ontario, including a $139-million hospital expansion, has won court protection from its creditors. The Ontario Superior Court earlier this month granted Bondfield Construction Co.’s application for protection, court records show.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, ENR
No Coverage for Construction Defect Claim Only Impacting Insured's Work
January 08, 2024 —
Tred R. Eyerly - Insurance Law HawaiiIn a coverage dispute between two insurers over a claim for damages caused by faulty workmanship, the court found there was no right to equitable contribution or indemnity. Travelers Prop. Cas. Co. of Am. v. Mallcraft, Inc., 2023 Cal. Super. LEXIS 67568 (Cal. Super. Ct. Sept. 15, 2023).
Mallcraft was the general contractor for a building project and was sued for construction defects. Travelers was an additional insured under a policy issued to a subcontractor, KitCor. Travelers defended Mallcraft in an arbitration. Travelers sought equitable contribution and equitable indemnity from Hartford, Mallcraft's insurer.
Mallcraft and Travelers stiulated to a judgment agianst Mallcraft for all costs Travelers incurred in the arbitration. Travelers' insured, KitCor, was not implicated in the construction defect claims against Mallcraft. The judgment set forth findings, including the fact that the underlying plaintiff never made any claim that KitCor perfomred work on the project or casued property damage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com