Congratulations to Partner Vik Nagpal on his Nomination for West Coast Casualty’s Jerrold S. Oliver Award of Excellence!
March 27, 2023 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is honored to share that Downtown San Diego and Encinitas Managing Partner Vik Nagpal is nominated for West Coast Casualty’s Jerrold S. Oliver Award of Excellence!
Every year, West Coast Casualty recognizes an individual who is committed, trustworthy, and has contributed to the betterment of the construction defect community. The award is named after the late Judge Jerrold S. Oliver who is considered a “founding father” in the alternate resolution process in construction claims and litigation. Each year, members of the construction community are asked to nominate individuals who invoke the same spirit as Judge Oliver.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
California Contractor Tests the Bounds of Job Order Contracting
March 01, 2021 —
Garret Murai - California Construction Law BlogMost contractors have heard of design-bid-build, design-build, construction manager at risk, and even public private partnerships, various project delivery methods, which, at their heart, focus on balancing the interests of the various parties involved in a construction project, from owners, to design professionals, to contractors. There’s one project delivery method you may not be as familiar with though: Job Order Contracting, also known by its acronym JOC.
JOC contracting is a project delivery method used on public works projects and has been authorized to be used by California K-12 school districts, community colleges, CalState universities, and the Judicial Council of California, which, among other things, is responsible for the construction of California state courts. It is intended to be used on smaller, independent, long-horizon project typically involving maintenance, repair and refurbishment. Think periodic maintenance of facilities.
JOC contracts are administered by public entities issuing a request for proposals. The public entity then awards a JOC contract to the lowest responsible bidder. The lowest responsible bidder then enters into a JOC contract with the public entity. JOC contracts typically have a duration of one (1) year and are limited to a total construction value of $4.9 million increased annually based on the Consumer Price Index. When entering into a JOC contract, a JOC contractor agrees to perform work at prices set forth in a Construction Task Catalog also known as a unit price book which includes current local labor, material and equipment costs. Unit prices are then adjusted by a “bid adjustment factor” based on the JOC contractor’s bid. When work is needed, the public entity will then issue a job order to the JOC contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Vacation during a Project? Time for your Construction Documents to Shine!
October 09, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaHappy Lazy Day Everyone! What’s that? You didn’t know that August 10th is considered National Lazy Day? Well, it is. And it ties nicely in with today’s theme: how to take a vacation during the thick of the construction project.
Everyone needs a break. You are no different. It can seem, however, that it is impossible to disconnect from the ongoing onslaught of questions, requests for information, change orders, pay applications, and the like. But you can. The key to taking–and enjoying–your vacation is to plan ahead. This is the time for your construction documents to shine. Make sure that your designs are on schedule; make sure that the change orders and RFIs have been processed so there is no backlog. And make sure that your second in command is familiar enough with the day to day details to step into your shoes for the duration.
Then– be sure to give everyone notice. Is it any of their business that you are taking some time off? No. However, everyone procrastinates. So, if you give the entire team advance notice that you will be “off grid” starting on X date, they will be more inclined to get pending issues to you sooner rather than later. They won’t want to be stalled on progress, and with a heads up on when you are out of pocket, they will make it a priority to get requests to you ahead of your departure date.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
Turmoil Slows Rebuilding of Puerto Rico's Power Grid
August 28, 2018 —
Associated Press - Engineering News-RecordSAN JUAN, Puerto Rico (AP) — Ten months after Hurricane Maria destroyed Puerto Rico's electric grid, the local agency responsible for rebuilding it is in chaos and more than $1 billion in federal funds meant to strengthen the rickety system has gone unspent, according to contractors and U.S. officials who are anxious to make progress before the next hurricane.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
No Bad Faith in Insurer's Denial of Collapse Claim
July 15, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Tenth Circuit affirmed the district court's grant of summary judgment to the insurer on the insured's claims for collapse and bad faith. Christopher M. Wolpert Saddletree Holding, LLC v. Evanston Ins. Co., 2024 U.S. App. LEXIS 10377 (10th Cir. April 30, 2024).
On May 7, 2019, Saddletree filed a claim with Evanston for damages sustained to its building which was used as a community events center. After a winter of heavy snowfall, Saddletree discovered that the building's steel support columns had buckled two or more inches and the roof had deflected downward approximately six inches.
Evanston retained an engineer to inspect the building. The engineer determined that the damage was the result of the building's inadequate "design and/or construction." Evanston disclaimed coverage under the policy's exclusion for damage caused by "hidden or latent defects" or "any quality in property that causes it to damage or destroy itself."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
No Coverage for Alleged Misrepresentation Claim
January 23, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe court found there was no coverage for a misrepresentation claim against the insured sellers of a residence. Am. Family Mut. Ins. Co. v. Coyne, 2022 U.S. Dist. LEXIS 186417 (E.D. Mo. Oct. 12, 2022).
Aaron and Tobi Beckman purchased a home from Denise Coyne. The Bockmans alleged in the underlying suit that Coyne represented that the property had a "2-car garage." A disclosure statement signed by Coyne stated she had disclosed all conditions which might lower the value of the property or adversely affect the Bockman's decision to buy the property. After purchasing the property, the Bockmans learned that they could not fit their two vehicles in the attached garage. The Bockmans alleged that substantial remediation was necessary to expand the depth of the garage to fit two cars within it.
The underlying suit alleged that Coyne had was engaged in fraud, misrepresentation and concealment by omitting material facts in connection with the sale of the home. Coyne allegedly engaged in negligent misrepresentation by failing to inform the Bockmans of the depth of the attached garage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Potential Construction Liabilities Contractors Need to Know
September 21, 2020 —
Manipal Dhariwal - Construction ExecutiveThe outbreak of COVID-19 started in early December 2019, gradually expanding to the other countries of the world. The spread of the pandemic did not just affect the world in terms of health, but also made industries suffer across all verticals—leading to a few unique challenges for construction contractors.
From financial imbalance to trouble retaining cash flow, the circumstances have turned to be completely unfavorable for the contractors that rely on banks for essential surety credits to sustain. To prevent loss of liquidity, the contractors are leaning toward construction accounting software and other technology to keep their accounting data in place and avoid risks with project deliveries.
But still, there are many other factors that must be considered to maintain cash flow for potential credit availability such as debt agreements and lines of credit, which involve financing of equipment and vehicles.
Nevertheless, it is completely the responsibility of the contractors to stick with the guidelines related to the line of credit and debt agreements which in most cases are covenant ratios.
Reprinted courtesy of
Manipal Dhariwal, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Nondelegable Duties
June 04, 2024 —
David Adelstein - Florida Construction Legal UpdatesHave you heard the expression “nondelegable duty”? The issue of a nondelegable duty comes into play when a party hires an independent contractor and the independent contractor commits negligence, primarily in the personal injury context. In other words, a plaintiff wants to hold a defendant liable for the injuries caused by the defendant’s independent contractor.
A nondelegable duty is one that “may be imposed by statute, contract, or the common law. In determining whether a duty is nondelegable, the question is whether the responsibility at issue is so important to the community that an employer should not be allowed to transfer it to a third party.” Garcia v. Southern Cleaning Service, Inc., 360 So.3d 1209, 1211 (Fla. 3d DCA 2023) (internal citation omitted).
When it comes to CONTRACTUAL duties:
[S]pecifically the principle that one who undertakes by contract to do for another a given thing cannot excuse himself to the other for a faulty performance by showing that he hired someone else to perform the task and that other person was the one at fault. In other words, where the contracting party makes it her or his duty to perform a task, that party cannot escape liability for the damage caused to the other contracting party by the negligence of independent contractors hired to carry out the task.
Gordon v. Sanders, 692 So.2d 939, 941 (Fla. 3d DCA 1997).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at