Miorelli Doctrine’s Sovereign Immunity in Public Construction Contracts — Not the Be-All and End-All
March 21, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn the Florida commercial contract public arena, there is a sovereign immunity doctrine known as the Miorelli doctrine after 1997 Florida Supreme Court decision, County of Brevard v. Miorelli Eng’g, Inc., 703 So.2d 1049 (Fla. 1997). This doctrine would apply to construction contracts between a contractor and a public body.
Through the years, the Miorelli doctrine stands for the proposition in commercial transactions with a Florida public body “that the doctrine of sovereign immunity precludes recovery of the cost of extra work where claims for that extra work are ‘totally outside’ the terms of the contract.” Monroe County v. Ashbritt, Inc., 47 Fla.L.Weekly D594a (Fla. 3d DCA 2022). See also Asbritt, n.2 quoting Posen Construction v. Lee County, 921 F.Supp.2d 1350, 1356 (M.D.Fla. 2013) (“A claim for damages predicated on work ‘totally outside the terms of the contract‘ is barred by the doctrine of sovereign immunity, whereas damages caused by extra work done at the state’s behest and in furtherance of the contractual covenants (express or implied) are potentially recoverable.”)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
David M. McLain to Speak at the CLM Claims College - School of Construction - Scholarships Available
July 28, 2016 —
David M. McLain – Colorado Construction LitigationI am happy to have been asked to serve as an instructor at this year's CLM Claims College – School of Construction, to be held at the Marriott Baltimore Waterfront in Baltimore, Maryland on Wednesday, September 7, 2016 through Saturday, September 10, 2016.
Overview of the 2016 School of Construction
Construction claims present myriad complexities in claim handling. Construction defect lawsuits are often multi-party cases with cross claims and third-party claims between and among the numerous defendants. Insurance coverage is intertwined and complex due to the interplay of primary, excess, wrap, and additional insurers for the numerous defendants. All this is further complicated by statutes and regulations, inconsistent case law and procedural peculiarities throughout the United States. The economic stakes are high as the damages claims can be in the multi-millions.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Are You Satisfying WISHA Standards?
October 23, 2018 —
Ceslie Blass - Ahlers Cressman & Sleight PLLC BlogMany general contractors and property management companies hand over project sites to subcontractors and have little, if anything, to do with the construction work that occurs. However, under RCW 49.17, the Washington Industrial Safety and Health Act (WISHA), general contractors and some property management companies/owners are still responsible for workplace safety for the employees of their subcontractors and independent contractors.
The Washington Supreme Court held in Stute v. PBMC that a general contractor could be held liable for injury to a subcontractor’s employee sustained as a result of a WISHA violation.[1] The Stute decision changed the landscape of workplace safety, imposing an expansive, per se liability on general contractors for workplace injuries. Stated differently, general contractors have a specific, non-delegable duty to ensure compliance with WISHA regulations, which extends to all employees on the project site.[2] Washington courts have held that such “expansive liability is justified because ‘a general contractor’s supervisory authority is per se control over the workplace.’”[3] Thus, the non-delegable duty requires general contractors to ensure care is exercised by anyone, even an independent contractor to whom the performance of the duty is entrusted.
Read the court decisionRead the full story...Reprinted courtesy of
Ceslie Blass, Ahlers Cressman & Sleight PLLCMs. Blass may be contacted at
ceslie.blass@acslawyers.com
Mortenson Subcontractor Fires Worker Over Meta Data Center Noose
April 19, 2022 —
James Leggate - Engineering News-RecordA worker on a data center project for Facebook parent company Meta in Utah was fired after admitting to tying a noose at the worksite where racist graffiti had also been found months earlier.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Appellate Team Secures Victory in North Carolina Governmental Immunity Personal Injury Matter
January 23, 2023 —
Sam Friedman & Christopher Meeks - Lewis BrisboisAtlanta, Ga. (January 12, 2023) - Atlanta Appellate Partners Seth M. Friedman and Christopher Meeks obtained a significant appellate win on behalf of a city in North Carolina when the North Carolina Court of Appeals reversed the trial court’s denial of the city’s motion for summary judgment.
In the underlying case, Lewis Brisbois’ client was sued for injuries that occurred during the construction of a dog park. The city moved for summary judgment on the grounds that it was immune from suit under the doctrine of governmental immunity. The trial court denied the motion and held that the city waived its governmental immunity through the purchase of a liability insurance policy. Lewis Brisbois was subsequently retained to handle the appeal.
Before the North Carolina Court of Appeals, Lewis Brisbois argued, on behalf of its client, that well-established North Carolina law, along with a particular provision in the city’s insurance policy, rendered the city immune from the plaintiff’s claims. The appellate court agreed, holding that the city was immune from all liability and entitled to summary judgment on all of the plaintiff’s claims. The court's full opinion can be read
here.
Reprinted courtesy of
Sam Friedman, Lewis Brisbois and
Christopher Meeks, Lewis Brisbois
Mr. Friedman may be contacted at Seth.Friedman@lewisbrisbois.com
Mr. Meeks may be contacted at Christopher.Meeks@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Public Contract Code 9204 – A New Mandatory Claims Process for Contractors and Subcontractors – and a Possible Trap for the Unwary
March 22, 2017 —
Alex R. Baghdassarian & Joseph S. Sestay – Peckar & Abramson, P.C.New California legislation affecting public works contractors was adopted pursuant to Assembly Bill 626, sponsored by the Union Trade Contractors Association of California and endorsed by various trade and contractor associations including the AGC. AB 626, which was intended to assist contractors in presenting claims against public agencies, affords new opportunities, and some potential pitfalls, to contractors and subcontractors submitting claims to public owners.
The legislation, codified at California Public Contract Code (PCC) section 9204, is effective for public works contracts entered into after January 1, 2017. All public entities (including the CSUS and the UC system), other than certain Departments of the State (CalTrans, High-Speed Rail Authority, Water Resources, Parks and Recreation, Corrections and Rehabilitation, General Services and the Military) are bound by the provisions of PCC Section 9204. PCC 9204 establishes a mandatory pre-litigation process for all claims by contractors on a public works project. It is an attempt to address the reluctance of public owners to promptly and fairly negotiate change orders on projects, putting some teeth to the mandate of existing law under PCC Section 7104, which precludes public owners from shifting to the contractor the risk of addressing differing subsurface and/or concealed hazardous site conditions.
Reprinted courtesy of
Alex R. Baghdassarian, Peckar & Abramson, P.C. and
Joseph S. Sestay, Peckar & Abramson, P.C.
Mr. Baghdassarian may be contacted at abaghdassarian@pecklaw.com
Mr. Sestay may be contacted at jsestay@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
What Counts as Adequate Opportunity to Cure?
June 13, 2022 —
Christopher G. Hill - Construction Law Musingsqimono @ PixabayHere at Musings, we like to discuss (likely more than readers would like) the fact that in Virginia, the contract is king and its terms will be looked at carefully by the courts. One of those provisions that will be looked at carefully is the so-called “cure period.” The “cure period” is the time that a subcontractor has to fix any non-compliant construction after receiving notice of any deviation from the contract documents that must be fixed.
In United States ex rel Allan Myers VA, Inc. v. Ocean Construction Services, Inc. the federal court for the Eastern District of Virginia examined what it means to grant a proper opportunity to cure. The Ocean Construction Services case arises from a contractual dispute between Allan Myers VA Inc. and Ocean Construction Services Inc., or OCS, involving renovation work performed in sections of Arlington National Cemetery. Presently before the court is Myers’ motion for partial summary judgment, arguing that the undisputed facts demonstrate that it was not provided with a three-day cure period, a contractual prerequisite to OCS terminating the subcontract for default.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
9th Circuit Closes the Door on “Open Shop” Contractor
September 04, 2018 —
Garret Murai - California Construction Law BlogAt the height of the Great Depression nearly one-quarter of Americans were unemployed. In response, Congress enacted a series of laws including the Smoot-Hawley Tariffs Act, which raised tariffs on foreign goods in an effort to spur domestic investment and to increase the number of jobs. Sound familiar?
Background
The Davis-Bacon Act
Among the new laws enacted by Congress was the Davis-Bacon Act which required contractors on federal works projects to pay their workers the wages prevailing in the area where a project was located, also known as “prevailing wages,” in an effort to stem the practice of employers bringing in lower-wage workers from outside the area. The same year that the Davis-Bacon Act was enacted, California enacted its own prevailing wage law modeled after the Davis-Bacon Act and applicable to state and local public works projects.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com