What a Difference a Day Makes: Mississippi’s Discovery Rule
November 16, 2023 —
William L. Doerler - The Subrogation StrategistThe discovery rule applies to latent injuries, such that the statute of limitations does not begin to run until the plaintiff knows of or should have known of the injury. In Western World Ins. Group v. KC Welding, LLC, No. 2022-CA-00527-SCT, 2023 Miss. LEXIS 278 (KC Welding), a majority of the justices on the Supreme Court of Mississippi (Supreme Court) affirmed the trial court’s ruling that Western World Insurance Group (Insurer) filed its lawsuit one day late. Thus, the statute of limitations barred Insurer’s lawsuit.
In KC Welding, on July 12, 2018, KC Welding, LLC (KC Welding) sent an employee to Sunbelt Shavings, LLC (Sunbelt) to repair the door of a box containing wood chips. Sunbelt’s employees discovered that KC Welding employees were welding a storage bin that had not been emptied of wood chips and Sunbelt’s employees asked KC Welding’s employees to leave. After that, Sunbelt’s employees attempted to soak the area with water. Later than night, a fire started on Sunbelt’s property, apparently as the result of smoldering wood shavings, a fire that was extinguished on July 13, 2018.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Updated 3/13/20: Coronavirus is Here: What Does That Mean for Your Project and Your Business?
March 16, 2020 —
Alexander Gorelik, Joshua E. Holt, Brian N. Krulick, Shoshana E. Rothman, A. Michelle West, & Brian S. Wood - Smith CurrieThe outbreak of COVID-19 (“coronavirus”) has wreaked a considerable human toll of death, physical suffering, fear, and anxiety internationally. Much of the fear and anxiety results from a lack of information or a full understanding about the spread of the disease, protection against infection, and treatment. At Smith, Currie & Hancock, we urge our clients, friends, and colleagues to take seriously, but calmly and prudently, the threat of this disease to protect yourselves, your loved ones, and your businesses. The first step in that process is to inform yourselves with reliable information. Toward that end, we direct your attention to the Centers for Disease Control and Prevention’s Coronavirus Disease 2019 website: https://www.cdc.gov/coronavirus/2019-ncov/index.html
In addition to the human toll, coronavirus has caused substantial disruptions to economies worldwide. In that regard, the adage “a picture is worth a thousand words,” is particularly foreboding. Satellite images taken by the U.S. National Aeronautics and Space Administration (NASA) of China at the outset of the coronavirus outbreak and approximately a month later show a dramatic decline in air pollution, signifying and illustrating a sharp decline in industrial activity and transportation caused by the disease.
Reprinted courtesy of Smith Currie attorneys
Alexander Gorelik,
Joshua E. Holt,
Brian N. Krulick,
Shoshana E. Rothman,
A. Michelle West, and
Brian S. Wood
Mr. Gorelik may be contacted at agorelik@smithcurrie.com
Mr. Holt may be contacted at jeholt@smithcurrie.com
Mr. Brian may be contacted at bnkrulick@smithcurrie.com
Ms. Shoshana may be contacted at serothman@smithcurrie.com
Ms. West may be contacted at amwest@smithcurrie.com
Mr. Wood may be contacted at bswood@smithcurrie.com
Read the court decisionRead the full story...Reprinted courtesy of
California Court of Appeal Affirms Trial Court’s Denial of anti-SLAPP Motion in Dispute Over Construction of Church Facilities
March 27, 2023 —
Garrett A. Smee & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPOn February 28, 2023, the California Fourth District Court of Appeal, Division One, issued an opinion in Billauer v. Escobar-Eck (D079835), affirming the trial court’s denial of an anti-SLAPP motion stemming from a public debate over a Church construction project.
The Appellant (Billauer) ran several social media sites as a “neighborhood activist.” The Respondent (Escobar-Eck) ran a land use and strategic planning firm in San Diego. The “All People’s Church” had hired Escobar-Eck’s company in 2019 to obtain City approval for a Church campus. During a Zoom presentation by Escobar-Eck to a Church planning group on November 11, 2020, Billauer, as a participant in the meeting sent a chat to Escobar-Eck stating: “I’m going to make sure you get sent back to where you came from.” Over the span of the next six months, from November 11, 2020 to April 8, 2021, Billauer continued the onslaught through a series of five posts on Instagram and Facebook, attacking Escobar-Eck. On December 10, 2020, Escobar-Eck fired back with a Twitter post to Billauer’s employer, Wells Fargo, labeling Billauer as a cyberbullying racist.
Reprinted courtesy of
Garrett A. Smee, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Mr. Smee may be contacted at gsmee@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: Guam’s CERCLA Claim Allowed, a “Roundup” Verdict Upheld, and Judicial Process Privilege Lost
June 14, 2021 —
Anthony B. Cavender - Gravel2GavelThis is a brief account of some of the important environmental and administrative law cases recently decided.
THE U.S. SUPREME COURT
BP PLC, et al. v Mayor and City of Baltimore
The issue the court confronted was a procedural matter: Can the defendant energy companies use the federal removal statutes (see 28 USC Section 1442) to remove a state law climate change lawsuit to federal court? Here, a group of energy companies were sued by the mayor and city council of Baltimore in state court, where they alleged that the defendants had concealed the adverse environmental effects of the fossil fuel products they promoted and sold in Baltimore City. Several similar lawsuits have been filed in many state courts, where typically it is alleged that the defendants can be sued on various common law theories. Rather than defend these cases in state court, the defendants have sought to remove these cases to federal court because climate change liability appears to be an issue that should be settled at the federal level. These efforts have been unsuccessful, with most federal trial and appellate courts holding that the reasons cited for removal (oftentimes the federal officer removal statute) have not been persuasive. In this case, both the Maryland federal district court and the U.S. Court of Appeals held they had no jurisdiction to authorize removal, and thus returned the case to the state court. Noting that the U.S. Court of Appeals for the Seventh Circuit ruled that a removal action could be countenanced under Section 1442, thus creating a circuit split, the Supreme Court held that a straightforward reading of the removal statute empowers the reviewing court to examine all theories for removal that a district court has rejected. Consequently, the Court remanded the case to the Fourth Circuit where it can decide, “in the first instance,” whether there actually exist grounds to remove this case to federal court.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Connecticut Supreme Court Finds Faulty Work By Subcontractor Constitutes "Occurrence"
July 31, 2013 —
Tred Eyerly, Insurance Law HawaiiThe U.S. District Court in Alabama certified a question to the Connecticut Supreme Court: Is damage to a project caused by faulty workmanship "property damage" resulting from an "occurrence"? With some qualification, the Connecticut Supreme Court answered in the affirmative. Capstone Building Corp. v. Am. Motorists Ins. Co., SC 18886 (Conn. June 11, 2013).
Captsone Development agreed to coordinate and supervise construction on a building at the University of Conneticut. Capstone Building was the general contractor. UConn secured an OCIP policy from American Motorist Insurance Company ("AMICO"). More than three years after completion, UConn notified the insureds of alleged defects in the project, including elevated levels of carbon monoxide. The source of the leak was the individual hot water heaters in residential units and insufficient draft of exhaust from the heater.Other defects were found during an investigation.
The insureds tendered to AMICO. Coverage was denied because the liability arose out of the insureds' own work.The insureds settled with UConn, paying $1 million each. The insureds then sued AMICO in Alabama and the question was certified to the Connecticut Supreme Court.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
United States Supreme Court Limits Class Arbitration
May 13, 2019 —
Jeffrey K. Brown & Raymond J. Nhan - Payne & FearsOn April 24, 2019, the United States Supreme Court held that the Federal Arbitration Act ("FAA") bars orders requiring class arbitration when an agreement is ambiguous about the availability of such a procedure. Lamps Plus v. Varela, 587 U.S. __ , 2019 WL 1780275, (2019). In Lamps Plus, the Court clarified a 2010 case in which it held that a court may not compel arbitration on a class-wide basis when an agreement is silent on the availability of class arbitration. Stolt-Nielsen S.A. v. Animal Feeds Int'l Corp., 559 U.S. 662, 687 (2012).
In Lamps Plus, a 5-4 decision authored by Chief Justice Roberts, the Court explained that because the FAA envisions the use of traditional individualized arbitration, a party cannot be forced under the FAA to submit to class arbitration unless the parties explicitly agreed to do so. Because class arbitration does not share the benefits of traditional arbitration -- lower costs, greater efficiency and speed, and the parties' choice of a neutral -- the FAA requires more than an "ambiguous" agreement to show that the parties bound themselves to arbitrate on a class-wide basis. Unlike individualized arbitration, or even traditional class actions, class arbitration raises serious due process concerns because absent class members will have limited judicial review. Based on these critical differences between individual and class arbitration, the Court reiterated in Lamps Plus that "courts may not infer consent to participate in class arbitration absent an affirmative contractual basis for concluding that the party agreed to do so."
Reprinted courtesy of
Jeffrey K. Brown, Payne & Fears and
Raymond J. Nhan, Payne & Fears
Mr. Brown may be contacted at jkb@paynefears.com
Mr. Nhan may be contacted at rjn@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
A Survey of New Texas Environmental Laws
December 30, 2019 —
Anthony B. Cavender - Gravel2GavelThis is a brief survey of many of the environmental and regulatory laws passed by the Texas Legislature and signed by the Governor in the 86th Regular Session of the Legislature, which ended in May 2019. Altogether, more than 1,300 laws were enacted in this session, including a surprising number of environmentally related bills. Most of these new laws take effect on September 1, 2019. This survey places them in the following broad categories: Air, Water; Waste; Disaster (principally because of the effects of Hurricane Harvey); and Miscellaneous.
(Special thanks to Jay Bowlby, a summer intern in our Houston office, who made a significant contribution to this survey.)
1.
Air
HB 1627—amends Section 386.001(2) of the Health and Safety Code to remove several counties from the list of counties with deteriorating air quality subject to the Texas Emissions Reductions Plan.
HB 1346—relates to the diesel emissions reductions incentives and gives the TCEQ flexibility in administering this program.
HB 2726—concerns amended air quality permit applications. The law provides that construction of a project may proceed, at the applicant’s own risk, after the TCEQ Executive Director has issued a draft permit including the permit amendment. However, this provision does not apply to a permit amendment affecting a concrete batch plant located within 888 yards of a residence.
HB 3725—creates the Texas Emissions Reduction Plan Trust Fund, which will be held by the Comptroller and administered by the TCEQ, which also administers the TERP program.
SB 698—authorizes the TCEQ to provide expedited processing of certain Texas Clean Air Act permit applications by increasing the agency’s permitting staff.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Not All Design-Build Projects are Created Equal
June 28, 2021 —
Nicole Markowitz & Richard Robinson - Peckar & Abramson, P.C.As the need for faster and more efficient construction increases, design-build agreements are growing in popularity. Design-build projects may account for 44% of nonresidential building in the United States this year. However, contractors who venture into a “design builder” role may unexpectedly become liable for design errors/omissions that are not covered by their insurance policies. In turn, they may expose themselves to liability and insurance risks that are neither insured nor managed.
In this article, we’ll discuss how the contractor who becomes a design-builder, or performs design-related work through subcontractors, faces potentially unmanaged risk. We will also explore indemnity, warranty, and insurance traps by paying attention to contract language in both traditional design-build and design-assist scenarios.
Reprinted courtesy of
Nicole Markowitz, Peckar & Abramson, P.C. and
Richard Robinson, Peckar & Abramson, P.C.
Ms. Markowitz may be contacted at nmarkowitz@pecklaw.com
Mr. Robinson may be contacted at rrobinson@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of