Michael J. Baker - Snell & Wilmer Under Construction BlogPublic entities are known to assert False Claims actions “to up the ante” to intimidate and aggressively address contractor construction claims. This strategy in the case of John Ross of Industrial Sheet Metal, Inc. (JRI) V. City of Los Angeles Department of Airports (LAWA), 29 Cal. App. 5th 378 (2018), backfired on the public entity, LAWA, in a big way and should serve as a warning to public entities about expanding claims to include False Claim actions. In this case, LAWA was awarded $1 in contract damages, its California False Claims Act (CFCA) claim was rejected by the jury as were JRI’s claims against LAWA. Despite losing on the substantive contract claims, the trial court found that JRI “prevailed in the action” under the relevant CFCA fee provision, Government Code 12652, subd. (g)(9)(B), regardless of JRI’s failure to prevail in the action as a whole. The California Appellate Court (hereinafter “Court”) affirmed the trial court’s finding.
The CFCA is analogous to the federal False Claims Act (FFCA; 31 U.S.C. 3729 et seq.). Since the CFCA is patterned on similar federal legislation, it was appropriate for the Court to look to precedent construing this similar federal act in interpreting the CFCA provisions. Accordingly, the Court looked at the False Claims Act cases for guidance in upholding the trial court’s decision in its determination that JRI was the “prevailing party” for determining an attorney’s fees award against LAWA.
Read the court decisionRead the full story...Reprinted courtesy of
Michael J. Baker, Snell & WilmerMr. Baker may be contacted at
mjbaker@swlaw.com
Admissibility of Expert Opinions in Insurance Bad Faith Trials
November 04, 2019 —
David M. McLain – Colorado Construction LitigationIn 2010, Hansen Construction was sued for construction defects and was defended by three separate insurance carriers pursuant to various primary CGL insurance policies.[i] One of Hansen’s primary carriers, Maxum Indemnity Company, issued two primary policies, one from 2006-2007 and one from 2007-2008. Everest National Insurance Company issued a single excess liability policy for the 2007-2008 policy year, and which was to drop down and provide additional coverage should the 2007-2008 Maxum policy become exhausted. In November 2010, Maxum denied coverage under its 2007-2008 primarily policy but agreed to defend under the 2006-2007 primarily policy. When Maxum denied coverage under its 2007-2008 primary policy, Everest National Insurance denied under its excess liability policy.
In 2016, pursuant to a settlement agreement between Hansen Construction and Maxum, Maxum retroactively reallocated funds it owed to Hansen Construction from the 2006-2007 Maxum primary policy to the 2007-2008 Maxum primary policy, which became exhausted by the payment. Thereafter, Hansen Construction demanded coverage from Everest National, which continued to deny the claim. Hansen Construction then sued Everest National for, among other things, bad faith breach of contract.
In the bad faith action, both parties retained experts to testify at trial regarding insurance industry standards of care and whether Everest National’s conduct in handling Hansen Construction’s claim was reasonable. Both parties sought to strike the other’s expert testimony as improper and inadmissible under Federal Rule of Evidence 702.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Construction Defect Lawsuit Came too Late in Minnesota
June 28, 2013 —
CDJ STAFFThe Minnesota Court of Appeals has upheld a summary judgment in a construction defect case, Lee v. Gorham. Minnesota law requires that contractors warranty that the home will be free of major construction defects during the first ten years, but claims must “be brought within two years of the discovery of the breach.” The Lees received a home inspection report in 2009 that identified a variety of defects, including “several possible structural defects.” The court noted that the report stated, “Contact your builder in writing of the findings, and discuss your options with an attorney.”
The Lees contacted the contractor, Gorham Builders. After initial silence, Gorham told the Lees that problems would “have to be ‘turned over to [the] insurance company.’” Rodney noted in his testimony that he had two choices, to either sue Gorham or hire an outside contractor. Mr. Lee had concluded that the legal costs were likely to be equal to the cost of the contractor.
In June, 2011, the Lees changed their mind about bringing a suit. Gorham sought and received a summary judgment dismissing the case on the grounds that too much time had passed since the Lees learned of the construction defect. The Lees appealed.
The appeals court upheld the summary judgment. The Lees claimed that the 2009 home inspection did not alert them of a “major construction defect,” but the court concluded that the language of the report fit within the Minnesota statutory definition of a “major construction defect.”
Nor was the appeals court convinced that at any time did Gorham provide “assurances that it would cure the defects to the home.” Within the same month as the May 2009 inspection, Gorham had made it clear that any problems were an issue for the insurance company. Thus, the appeals court concluded that the Lee’s equitable-estoppel argument was without merit.
The Lees also brought to appeal the new argument that they did not realize they were dealing with “major construction defects” until they received a subsequent home inspection in 2011. The court noted that the second report does not detail “new defects or structural issues not identified in the 2009 inspection report.” In addition to being “without merit,” the court noted that this claim was not made in the district court and so the appeals court “need not consider this issue on appeal.”
Read the court decisionRead the full story...Reprinted courtesy of
Water Drainage Case Lacks Standing
March 28, 2012 —
CDJ STAFFThe Texas Court of Appeals has ruled in the case La Tierra de Simmons Familia Ltd. V. Main Event Entertainment, LP. The trial court had found for Main Event. On appeal, the court threw out some of the grounds on which the trial court had reached its decision.
The case involved two commercial lots in northwest Austin, Texas. The uphill tract (Phase III of the Anderson Arbor development) diverts its runoff onto the lower tract (the “Ballard tract”). The owners of the Ballard tract claim that “the drainage system was designed or constructed in a manner that has damaged and continues to damage the Ballard tract.”
Both tracts have undergone changes of ownership since the construction of the drainage system in 2004. At the time the drainage system was constructed, the parcel was owned by Sears Roebuck and Co. Sears later sold the property. Main Event Entertainment is the current tenant. Likewise, the Ballard tract was previously owned by the Ballard Estate which sold the property to La Tierra on an “as is” basis in 2007.
After La Tierra bought the Ballard tract, La Tierra’s engineer “witnessed and videotaped what he described as ‘flooding’ on the Ballard tract caused by storm water discharge from the Anderson Arbor drainage system during a rainfall event.” La Tierra determined that an adequate drainage system would cost about $204,000. Development plans were put on hold.
La Tierra sued Main Event and various other parties associated with the uphill tract, seeking “actual damages for (1) decrease and loss in rental income due to delay in obtaining the development permit, (2) interest on carrying costs during that time period, (3) the cost to build a water conveyance system on the Ballard tract, (4) engineering fees incurred to redesign the water conveyance system, (5) unspecified out-of-pocket real estate expenses, and (6) property devaluation occasioned by the need to construct an expensive water conveyance system.” The trial court never reached these claims, ruling instead that La Tierra lacked standing, that its claims were barred under the statute of limitations, and that there was no evidence of damage.
La Tierra appealed, arguing that “(1) the summary-judgment evidence does not conclusively establish that property damage claims accrued or were discovered prior to September 11, 2007, which is within the limitations period and was after La Tierra purchased the property; (2) even if the property was damaged before La Tierra acquired ownership of the Ballard tract, standing exists based on the assignments of interest from the Ballard Estate heirs, and the discovery rule tolls limitations until the injury was discovered on September 11, 2007; (3) limitations does not bar La Tierra's request for injunctive relief; (4) La Tierra's water code claim against Main Event and M.E.E.P. is viable based on their control over the drainage system, which makes them necessary and indispensable parties for injunctive relief; (5) La Tierra presented more than a scintilla of evidence to raise a fact issue on damages, causation, and other essential elements of its causes of action; and (6) the trial court abused its discretion when it sustained the defendants' objections to La Tierra's summary-judgment evidence.”
The appeals court concluded that La Tierra’s second claim was irrelevant to standing, as La Tierra “obtained assignments from the Ballard Estate heirs ? nearly one year after the lawsuit was initially filed.” Nor did the court accept their first point. The water system had been operating unaltered since January, 2004, with monthly maintenance and inspection to maintain its designed operation. Further, a feasibility report La Tierra received stated that “over sixteen acres drain into those ponds, and thus onto this site.” The court noted that “the underlying facts giving rise to a cause of action were known before La Tierra acquired ownership of the Ballard tract.”
The court concluded that the drainage issue is a permanent injury, but that it “accrued before La Tierra acquired an ownership interest in the property.” As La Tierra has standing, the appeals court ruled that it was improper for the trial court to rule on the issues. The appeals court dismissed the questions of whether the case was barred under the statute of limitation and also the question of whether or not La Tierra had damages.
As the issue of standing would not allow La Tierra to bring the suit, the appeals court found for the defendants, dismissing the case for this single reason, and otherwise affirming the ruling of the lower court.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defect Lawsuit May Affect Home Financing
February 14, 2013 —
CDJ STAFFHomeowners in the Burlingame Ranch I Condominium Association already say they have problems with the siding on their units. The Aspen Business Journal says that their next problem might be with lenders. According to the homeowners’ attorney, Chris Brody, the association attempted to work things out, but this was not successful.
Mr. Brody was unaware of any issues with sales or refinancing, but the article notes that “at least one homeowner was told he could not refinance with a Fannie Mae backed loan if there’s pending litigation.” Last year, Fannie Mae did adopt a guideline that made homes involved in construction defect lawsuits ineligible for home loans.
Read the court decisionRead the full story...Reprinted courtesy of
Should CGL Insurer have Duty to Defend Insured During Chapter 558 Notice of Construction Defects Process???
September 01, 2016 —
David Adelstein – Florida Construction Legal UpdatesDoes a CGL insurer have a duty to defend its insured-contractor during Florida Statutes Chapter 558 notice of construction defects pre-suit process? This answer is currently undecided and will be up to the Florida Supreme Court to decide. (It is on appeal stemming from a federal district court saying that an insurer does not have a duty to defend its insured-contractor in the 558 process based on the definition of the word “suit” in the CGL policy.)
Why is this an important issue?
The 558 pre-suit notice of construction defects process is designed to facilitate an avenue for construction defect lawsuits to get resolved without having to file a lawsuit or, at least, have issues narrowed before a lawsuit needs to be filed. (Check here for a summary of the 558 process.) It requires pre-suit notifications so that implicated parties can become aware of the defects and have an opportunity to inspect the defects / damage, test the defects / damage, and respond to the notice of construction defects; it provides an avenue for beneficial pre-suit discovery. Through participating in the 558 process, the contractor and/or design professional (and those downstream from them) can: (i) offer to remedy the defect, (ii) settle the defect, whether through money or a combination of money and repairs, (iii) dispute the defect, or (iv) advise that available insurance proceeds will be determined by its liability insurer. See Fla. Stat. s. 558.004.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Traub Lieberman Attorneys Lisa M. Rolle, Eric D. Suben, and Justyn Verzillo Secure Dismissal of All Claims in a Premises Liability Case
November 16, 2023 —
Lisa M. Rolle, Eric D. Suben & Justyn Verzillo - Traub LiebermanOn an appeal of an order denying Defendant’s motion to dismiss the complaint in a slip-and-fall action commenced in Kings County Supreme Court, Traub Lieberman attorneys Lisa M. Rolle, Eric D. Suben, and Justyn Verzillo successfully secured dismissal of all claims by the Appellate Division, Second Department, on behalf of Traub Lieberman’s client.
The lawsuit sought to recover damages arising out of injuries the Plaintiff allegedly sustained when she slipped and fell in the shower of a rental property owned by the Defendant, a limited liability company. Plaintiff alleged that the subject shower was defective, and the Defendant negligent, based on the absence of non-slip surfacing and grab bars in the shower. Aside from premises liability (negligence), Plaintiffs asserted eight other causes of action, including gross negligence, breach of warranty of habitability, intentional infliction of emotional distress, negligent infliction of emotional distress, alter-ego liability, loss of consortium, and for declaratory judgment.
The judge in Supreme Court denied Traub Lieberman’s motion to dismiss on behalf of Defendant, citing as the sole reason that the affidavits submitted with the motion were unsigned, and ignoring Traub Lieberman’s arguments pointing out the glaring facial deficiencies of Plaintiff’s pleading and that the signed affidavits were in fact submitted before the return date.
Reprinted courtesy of
Lisa M. Rolle, Traub Lieberman,
Eric D. Suben, Traub Lieberman and
Justyn Verzillo, Traub Lieberman
Ms. Rolle may be contacted at lrolle@tlsslaw.com
Mr. Suben may be contacted at esuben@tlsslaw.com
Mr. Verzillo may be contacted at jverzillo@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
It Ain’t Over Till it’s Over. Why Project Completion in California Isn’t as Straightforward as You Think
May 07, 2015 —
Garret Murai – California Construction Law BlogBaseball legend Yogi Berra was famous for his pithy quotes such as “the future ain’t what it used to be,” “half the lies they tell about me aren’t true,” and what is probably his most famous, “it ain’t over till it’s over.”
The last, of course, begs the question of when over is over? And, on California construction projects when over is over, or more accurately, when a project is complete, can be as paradoxical as a “yogiism.”
Why “Completion” is Important in California
In California, project “completion,” is important not only for getting paid, but for knowing the deadlines associated with California’s statutory construction payment remedies.