Liquidated Damages: Too High and It’s a Penalty. Too Low and You’re Out of Luck.
November 21, 2022 —
Christian Fernandez - Snell & Wilmer Real Estate Litigation BlogLiquidated damages provisions in commercial and residential real estate contracts play a vital role when a transaction goes south, and should be given careful consideration when negotiating a real estate contract. Liquidated damages may be referred to in a variety of ways, such as “earnest money,” a “good-faith deposit,” or a “non-refundable deposit,” but each typically denote a negotiated amount of money that a seller is entitled to retain should a buyer breach a purchase and sale agreement. The purpose of liquidated damages is to provide the parties with certainty when actual damages arising from a breach of contract may be difficult to calculate. Accordingly, liquidated damages provisions alleviate the need for potentially expensive litigation associated with proving damages.
While parties are free to negotiate the amount of liquidated damages, the amount must approximate the loss anticipated at the time of contracting, or the loss that actually occurs as a result of a breach. Arizona courts have held that where the amount of liquidated damages is unreasonably large when compared to the anticipated loss or actual loss, the liquidated damages provision is unenforceable as a penalty. A breaching party faced with high liquidated damages will often seek to invalidate the provision as a penalty. If a court agrees, the non-breaching party may still recover damages, but must go through the process of proving such damages. Therefore, when negotiating a real estate contract, consideration should be given as to whether a liquidated damages amount is arbitrarily high when compared to an anticipated loss in the event of a breach.
Read the court decisionRead the full story...Reprinted courtesy of
Christian Fernandez, Snell & WilmerMr. Fernandez may be contacted at
cfernandez@swlaw.com
Failure to Allege Property Damage Within Policy Period Defeats Insured's Claim
October 03, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe insured's inability to determine when water damage occurred meant it could not pursue claims of property damage against the insurers. Creek v. State Farm Fire & Cas. Co., 2022 U.S. Dist. LEXIS 116939 (W.D. Wash. July 1, 2022).
Gold Creek Condominium complex experienced water damage. The complex was completed in 1982. The owners sued State Farm and Travelers under all-risk policies when tenders for the damage were denied.
In 2017, Creek hired an expert to investigate deterioration due to water intrusion. The expert noted that "water intrusion had been evident in the exterior walls, soffits, terraces, handrails and elevated entry walkways for some time." Thereafter, Creek tendered claims for property damage to State Farm and to Travelers.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Eastern District of Pennsylvania Clarifies Standard for Imposing Spoliation Sanctions
October 19, 2020 —
Kean Maynard - The Subrogation StrategistCourts are faced with the difficult task of drawing a line to determine when the failure to preserve evidence becomes culpable enough to permit a judicial remedy. In State Farm Fire & Cas. Co. v. Cohen, No. 19-1947, 2020 U.S. Dist. LEXIS 163681, the United States District Court for the Eastern District of Pennsylvania (District Court) made clear that a party is not entitled to a spoliation sanction without proof that the alleged spoliation was beyond accident or mere negligence. The District Court emphasized that when evidence goes missing or is destroyed, the party seeking a spoliation sanction must show that the alleged spoliation was intentional and that the alleged spoliator acted in “bad faith” before adverse inferences will be provided.
In Cohen, Joshua Cohen (Cohen) rented a residential property to Lugretta Bryant (Bryant). Bryant’s property suffered damages as a result of a kitchen fire. Bryant’s insurer, proceeding as subrogee, hired a fire investigator to determine the cause and origin of the fire. Based on eyewitness testimony and examination of the burn patterns, the fire investigator concluded that the fire started at the General Electric (GE) microwave located in the kitchen. The investigator advised all parties to preserve the microwave so that a joint examination could take place with the property owner and GE present. In the following weeks, the tenant returned to the property to collect belongings and perform some cleaning in anticipation of repairs beginning. Importantly, the tenant claimed the microwave was preserved during these cleaning efforts and remained at the site as instructed. However, in the fall of 2017, one of Cohen’s workers discovered that the microwave was missing and its whereabouts remain unknown.
Read the court decisionRead the full story...Reprinted courtesy of
Kean Maynard, White and WilliamsMr. Maynard may be contacted at
maynardk@whiteandwilliams.com
Options When there is a Construction Lien on Your Property
June 02, 2016 —
David Adelstein – Florida Construction Legal UpdatesThere is a construction lien on my property. What are my best options? I hear this question quite a bit…so here it goes…
(1) Do nothing. That’s right – do nothing. If you are not looking to sell your house or refinance in the next year or so, you can do nothing and see whether the lienor files a construction lien foreclosure lawsuit. The lienor has one year from the recording of the lien to file the lawsuit.
(2) Record a
Notice of Contest of Lien. The
Notice of Contest of Lien shortens the lienor’s statue of limitations to foreclose on the lien from one year to 60 days. If the lienor fails to foreclose on the lien within 60 days, the lien is extinguished by operation of law. This is the route I tend to prefer. If the lienor is going to file a lien foreclosure lawsuit, I tend to think it is better forcing the issue on the front end as opposed to waiting a year. But every situation is different.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
VOSH Jumps Into the Employee Misclassification Pool
February 23, 2016 —
Christopher G. Hill – Construction Law MusingsThe proper classification of workers by construction companies has been on the radar of the Department of Labor for both the US and Virginia governments for quite a while. While most of the misclassification is innocent and not done to create issues, there have been enough instances of purposeful misclassification of certain workers as independent contractors (thus avoiding workers comp and other payroll expenses) that innocent contractors have born the brunt of these issues through increased payroll costs over those that misclassify (in the form of necessarily higher bids, higher overhead, etc.).
As an additional deterrent to improper classification of workers, the Virginia Department of Labor and Industry has issued guidelines for what will occur in Virginia Department of Safety and Health (VOSH) cases.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Mass. Gas Leak Follows NTSB Final Report, Call for Reforms
November 24, 2019 —
Johanna Knapschaefer - Engineering News-RecordA major natural-gas leak forced Lawrence, Mass., residents to evacuate their homes early on Sept. 27. National Grid cut power to more than 1,300 customers to avoid another disaster like last year’s natural-gas explosions and fires in Lawrence and two other towns north of Boston. The leak came just days after federal officials called for changes to national pipeline regulations as they released a final report on the causes of the Sept. 13, 2018, disaster.
Reprinted courtesy of
Johanna Knapschaefer, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Is Safety Compliance Putting Your Project in Jeopardy? Examining the Essentials of DOE’s Worker Safety and Health Program
July 02, 2024 —
Lucas T. Daniels & Benjamin J. Hochberg - ConsensusDocsMost contractors are familiar with the myriad of labor and safety regulations intended to safeguard the health and safety of workers. Many contractors will be equally familiar with the maze of forms and reports, the maintenance of safety personnel, safety walks and talks, and the many other measures intended to prevent and prepare for accidents. Less known among contractors and construction industry leaders is the regulatory framework establishing safety requirements and the ramifications of ignoring safety-related rules. Knowing and understanding the jurisdiction and authority of the agencies monitoring safety compliance on your project is critical to avoiding administrative ordeals and audits that could add days or weeks to your schedule and frustrate your staff.
The Department of Energy’s Worker Safety and Health Program
Under the Occupational Safety and Health Act of 1970, as amended (OSH), the Department of Labor’s Occupational Safety and Health Administration (OSHA) issues and enforces occupational health and safety regulations. OSHA, or a state with approval from OSHA, regulates the occupational health and safety of private sector employees unless another federal agency has and exercises its statutory authority to regulate. Several federal agencies have developed their own safety programs and conduct their own enforcement of those regulations independent of OSHA. For example, projects receiving funding from the Department of Energy (DOE) are subject to additional oversight of their safety programs by this agency. DOE directly manages its own Worker Safety and Health Program (WSHP), codified at 10 C.F.R. § 851, et seq., and will enforce compliance with its WSHP at all DOE sites. A “DOE site” is defined as a DOE-owned or -leased area or location or other area or location that DOE controls, where a contractor performs activities and operations in furtherance of a DOE mission. This broad definition encompasses a wide range of facilities and operations, including those not directly managed by the DOE but still under its control. The contractor at such a site must be aware of the specific requirements and procedures of the DOE under the WSHP and the ramifications of violating these regulations.
Reprinted courtesy of
Lucas T. Daniels, Peckar & Abramson, P.C and
Benjamin J. Hochberg, Peckar & Abramson, P.C
Mr. Daniels may be contacted at ldaniels@pecklaw.com
Mr. Hochberg may be contacted at bhochberg@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Does the Recording of a Mechanic’s Lien Memorandum by Itself Constitute Process? Read to Find Out
August 04, 2021 —
Christopher G. Hill - Construction Law MusingsAs a Virginia construction attorney representing those in the construction industry, mechanic’s liens are near and dear to my heart. The enforcement of mechanic’s lien rights in Virginia is a two-step process. The first step is the recording of a properly-timed memorandum of lien that includes all of the statutorily required information. The second step is a suit to enforce that memorandum of lien filed in Circuit Court. A recent case out of Norfolk, VA examined the first of these steps.
In Central Radio Co. v. Warwick Builders, et al., and as Count III of a three-count Complaint, the Plaintiff, Central Radio Co., alleged that the Defendant, Warwick Builders, recorded a memorandum of lien that Warwick knew to be without merit and therefore committed an abuse of process. However, Warwick did not file any Circuit Court suit to enforce that lien. Central Radio Co. essentially alleged that the filing of the memorandum by itself constituted an attempt to extort payment and therefore was an abuse of process.
Read the court decisionRead the full story...Reprinted courtesy of