Construction Defects in Home a Breach of Contract
September 09, 2011 —
CDJ STAFFThe Supreme Court of North Dakota has ruled in Leno v. K & L Homes, affirming the verdict of the lower court. K & L Homes argued that district court had erred in several ways, including by refusing to instruct the jury on comparative fault, denying a request for inspection, and not allowing a defendant to testify on his observations during jury viewing.
The Lenos purchased a home constructed by K & L Homes, after which they alleged they found cracks, unevenness, and shifting, which they attributed to improper construction. They claimed negligence on the part of K & L Homes. K & L Homes responded that the Lenos were responsible for damage to the home. The Lenos dropped their negligence claim, arguing breach of contract and implied warranties.
Before the trial, after the discovery period had passed, K & L Homes requested to inspect the home. This was rejected by the court. Kelly Moldenhauer, the owner of K & L Homes sought to testify about his observations during the jury’s viewing of the house. The court denied this too. The jury found that K & L was in breach of contract and awarded damages to the Lenos.
The North Dakota Supreme Court noted that K & L Homes gave “warranties that the home had been built according to local building codes and laws, and that the house was fit for its particular purpose as a residence.” The court found that a defective home breached this warranty. Further, the home violated an implied warranty of fitness.
The district court had denied K & L’s request to inspect the home, as the discovery period had ended and it would not give the Lenos time to do further discovery of their own. At the time of the request, there was only twenty-two days before the trial. The Supreme Court ruled that this was not an abuse of discretion of the part of the district court.
The Lenos had requested that Moldenhauer’s testimony not be permitted, as it would “have the same effect as if the court had granted K & L Homes’ pretrial request for inspection.” K & L Homes agreed to this in court, replying, “okay.”
The decision affirms the judgment of the district court and the damages awarded to the Lenos by the jury.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
President Obama Vetoes Keystone Pipeline Bill
February 26, 2015 —
Angela Greiling Keane - Bloomberg(Bloomberg) -- President Barack Obama issued his third veto Tuesday to reject legislation that would allow construction of the Keystone XL pipeline, escalating a battle over the project with Republicans in Congress.
Notice of the long-expected veto was released without fanfare via a message to the Senate just hours after the bill formally arrived at the White House. The Senate has agreed to hold a vote on overriding the veto no later than March 3.
Obama has repeatedly said a State Department review of the TransCanada Corp. project -- which would carry crude oil produced in Alberta, Canada, south through the U.S. -- should proceed before a decision is made on whether to allow construction of the $8 billion pipeline.
Read the court decisionRead the full story...Reprinted courtesy of
Angela Greiling Keane, Bloomberg
Tarriffs, a Pandemic and War: Construction Contracts Must Withstand the Unforeseeable
May 16, 2022 —
Brett Moritz, Adrian Bastianelli III & Adam Handfinger - Construction ExecutiveSince the tariffs on steel and the first wave of the COVID-19 pandemic, the construction industry has been reeling from the impact of material shortages and price increases, labor shortages, breakdowns in the supply chain and the inflationary effect of these issues. Unfortunately, the war in Ukraine has only exacerbated the situation.
International conflicts can constrain supply, resulting in delays and price increases for contractors, subcontractors and suppliers. The disruption caused by the war is expected to be particularly acute due to the role that Russia and Ukraine play in the world economy and the effect of the economic sanctions that have been imposed on Russia by the United States and other countries. Russia controls approximately 10% of the global copper reserves and is estimated to produce about 10% of the world’s nickel supply. It also provides at least 30% of Europe’s oil and natural gas. Ukraine is a significant source of raw materials, such as iron. Thus, the war will cause significant shortages and price increases to the global construction industry. There are already reports of delays and cost increases for commodities such as nickel, aluminum, copper and—most importantly—steel, which have resulted in impacts to construction costs and schedules. Suppliers are especially sensitive to the volatile markets caused by these conditions. Some are insisting on automatic price increases in their purchase orders.
All of this, not to mention the anticipation of what may come next, points to the necessity for a new paradigm to achieve a successful project. It is more important today than ever that owners, contractors, subcontractors and suppliers reasonably address the economic and time impacts of these unforeseeable events in preparing contracts for future work and in administering existing contracts. Otherwise, the risk of a default on more than one level may put projects in jeopardy, to no one’s benefit.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Courts Generally Favor the Enforcement of Arbitration Provisions
May 10, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn recent posts (
here and
here) I have discussed arbitration provisions and cases dealing with the enforceability of arbitration provisions.
The case of Lemos v. Sessa, 46 Fla.L.Weekly D701a (Fla. 3d DCA 2021) deals with two noteworthy principles when it comes to arbitration that warrant another post about arbitration provisions.
First, courts will and should try to resolve any ambiguity in arbitration provisions in favor of arbitration.
Second, when there is an offending arbitration provision or one that includes language that violates public policy, the trial court “should sever the offending provisions from the arbitration clause so long as such severance does not undermine the parties’ intent.” Lemos, supra. This principle is reinforced when the arbitration provision is in an agreement that contains a severability provision.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
How Long Does a Civil Lawsuit Take?
August 14, 2018 —
Bremer Whyte Brown & O’MearaHow long does a civil lawsuit take?
One common question among parties to a civil lawsuit, whether a plaintiff or defendant, is how long will it take to reach a resolution? The answer is tricky. The time it takes to resolve a civil lawsuit is highly dependent on various factors including the complexity of the matter and the parties’ willingness to settle.
At the outset, parties to a civil case may resolve the matter at any time by mutual agreement (i.e., settlement). In that case, the parties draft a Stipulation and Order outlining the terms of the agreed settlement and submit the document to the judge for approval. Absent of any glaring inequity in the terms of the Stipulation, the judge will typically approve of the parties’ settlement, and the matter will be deemed resolved (either in whole or in part, depending on the case, the terms of the settlement and indemnity agreement).
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O’Meara
Dispute Resolution Provision in Subcontract that Says Owner, Architect or Engineer’s Decision Is Final
March 29, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn subcontracts, it is not uncommon to see a provision that says something to the effect:
Should any dispute arise between the parties respecting the true construction or interpretation of the Plans, Specifications and/or the Contract Requirements, the decision of the Owner or the Owner’s designated representative as set forth in the General Contract shall be final.
This is a provision in a subcontract dealing with dispute resolution, typically when there is a dispute as to whether the subcontractor is performing extra-contractual or base contract work regarding an “interpretation of the Plans, Specifications, and/or the Contract Requirements.” It is not uncommon for there to be a dispute as to whether certain work is within the subcontractor’s scope of work or outside the subcontractor’s scope of work and subject to a change order.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Insurer in Bad Faith For Refusing to Commit to Appraisal
October 08, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe court denied State Farm's motion for summary judgment on the insured homeowners' bad faith claim for State Farm's failure to agree to an appraisal. Currie v. State Farm Fire and Cas. Co., 2014 WL 4081051 (E.D. Pa. Aug. 19, 2014).
Superstorm Sandy caused a tree to crash in the insureds' home. The loss was reported to State Farm. The State Farm adjuster verbally quoted the roof replacement at more than $100,000. State Farm eventually paid $60,000 for the roof replacement. The insureds' adjuster estimated the loss at $363,804.98.
The insureds demanded an appraisal. State Farm rejected the demand because the claim involved certain items for which State Farm did not admit liability, including damage to the interior hardwood floors. State Farm contended that since the dispute went beyond the amount of loss, an appraisal was not an appropriate method of resolution.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Deference Given To Procuring Public Agency Regarding Material Deviation
April 10, 2019 —
David Adelstein - Florida Construction Legal UpdatesDeference will be given to a procuring public agency in a bid protest, particularly when the issue involves whether a bid is non-responsive and constitutes a material deviation from the solicitation. You do not believe me? Perhaps you will after this holding in Biscayne Marine Partners, LLC v. City of Miami, Florida, 44 Fla.L.Weekly D467a (Fla. 3d DCA 2019):
Consequently, no principle of law is clearly established…as to any obligation of the trial court (and, by analogy, an administrative hearing officer) [in a bid protest] to decide or to defer [whether a bid constitutes a material deviation from the solicitation]. If anything, the existing and clearly established principle of law inclines toward judicial deference in public agency competitive bidding disputes when the agency has exercised it discretion absent illegality, fraud, oppression or misconduct.
I do not know about you, but that last underlined sentence is pretty strong language regarding judicial deference!
In this case, Miami (the procuring public agency) issued a Request for Proposals (RFP) for the redevelopment and lease of waterfront property, for the operation of a marina, boatyard, restaurant, wet slips, and a dry storage facility on the property. Miami issued five addenda to the RFP. There were three bidders.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com