Be Careful with Continuous Breach and Statute of Limitations
January 21, 2019 —
Christopher G. Hill - Construction Law MusingsIf you are a construction attorney like me (or anyone that takes cases to court), you deal with statutes of limitation on a daily basis. These statutes seem pretty simple. A party has “X” amount of time in which to file its lawsuit after accural of the cause of action. In a breach of contract suit, the accrual is the date of breach. Easy, right? Wrong, at least in some circumstances.
Take for example, the case of Fluor Fed. Sols., LLC v. PAE Applied Techs., LLC out of the 4th Circuit Court of Appeals. In this unpublished opinion the Court looked at “continuous breach” versus “series of separate breaches.” The basic facts are that in 2000 Flour entered into a contract with PAE whereby PAE requested and claims to have received consent from Flour to a 2.3% administrative cost cap on Flour’s work on an Air Force contract. Flour claimed that it did not agree to this cap. In 2002, Flour begain billing PAE for its costs plus the 2.3% administrative markup and billed in this fashion for the first full year. However, in subsequent years and for the next 11 years, Flour billed PAE at a higher markup rate than the 2.3%. PAE disputed the increased markup and paid Flour at the 2.3% rate. Flour periodically protested but made no move to court until it filed suit in March of 2016. After a bench trial, the district court found that Flour had agreed to the cap and found for PAE.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Hunton Insurance Team Wins Summary Judgment on Firm’s Own Hurricane Harvey Business Income Loss
March 23, 2020 —
Michael S. Levine & Michelle M. Spatz - Hunton Insurance Recovery BlogA Texas judge has ruled that Hunton Andrews Kurth is entitled to coverage from Great Northern Insurance Co., a unit of Chubb, Ltd. (“Chubb”), for losses its predecessor firm suffered when Hurricane Harvey closed its Houston office and disrupted business in 2017.
The court agreed with Hunton’s position that the policy, written specifically for a law firm, covered its business income loss until the firm’s operations were restored to their pre-loss levels. The court rejected in its entirety Chubb’s argument that coverage lasted only until the physical damage that closed the building had been repaired. Rather, siding with Hunton, the court found that the policy language affords, in addition to ordinary business income coverage during the damage period, “extended period” coverage that commences after the damaged property is repaired and after the firm’s operations resume.
From August 27 to August 31, 2017, the firm was forced to close its Houston office due to flooding and damage caused by Hurricane Harvey. While employees were permitted to return to the office on August 31, income did not return to its pre-loss level until September 14, 2017. The firm submitted a claim to Chubb for the loss sustained from August 27 to September 14, but Chubb paid only for income loss suffered during the 3-day closure period, and refused to cover the loss suffered after the building reopened.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Michelle M. Spatz, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Spatz may be contacted at mspatz@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
The ALI Restatement – What Lies Ahead?
July 30, 2018 —
Adam M. Berardi & Sara C. Tilitz - Complex Insurance Coverage ReporterThe American Law Institute voted on May 22, 2018 to approve the final draft of its “Restatement of the Law of Liability Insurance.” This was the culmination of an eight-year project that evolved through 29 drafts resulting in a nearly 500-page final product. At least nine courts cited to the Restatement while it was still in draft form. On June 28, 2018, White and Williams LLP had the privilege of hosting a seminar about the Restatement, chaired by the Reporter for the Restatement, University of Pennsylvania Law Professor Tom Baker, and Randy Maniloff of White and Williams, author of “General Liability Insurance Coverage, Key Issues In Every State.” The seminar was geared toward assisting members of the liability insurance community in navigating the key provisions of the Restatement, including how they compare and contrast with existing case law and the role the Restatement may play in courts’ decision-making processes going forward.
Reprinted courtesy of
Adam M. Berardi , White and Williams, LLP and
Sara C. Tilitz, White and Williams, LLP
Mr. Berardi may be contacted at berardia@whiteandwilliams.com
Ms. Tilitz may be contacted at tilitzs@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
California Pipeline Disaster Brings More Scandal for PG&E
September 17, 2014 —
Mark Chediak – BloombergA deadly pipeline explosion that shattered a California town four years ago continues to rip through the state agency weighing a record penalty for the disaster.
The president of the California Public Utilities Commission asked his chief of staff to resign and recused himself from the case after “inappropriate e-mail exchanges” with PG&E Corp. (PCG) raised questions about bias, according to a statement from the commission yesterday. The CPUC may decide within weeks whether to levy a proposed $1.4 billion penalty -- the biggest safety fine in the state’s history -- against PG&E for the 2010 explosion of a natural gas pipeline that killed eight people in San Bruno.
Commission President Michael Peevey, who has been accused by San Bruno officials and consumer advocates of being too close to the utility, said in the statement he would not take part in penalty deliberations to eliminate any appearance of impropriety. The move is a step toward regaining credibility for the CPUC after two years of political infighting has created an ongoing climate of scandal.
Read the court decisionRead the full story...Reprinted courtesy of
Mark Chediak, BloombergMr. Chediak may be contacted at
mchediak@bloomberg.net
Spotting Problem Projects
October 26, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPPerhaps more than any other specialty contractor, electrical contractors bear the brunt of the “problem project.” Long after most other trades have completed their work and scattered in the wind, electrical contractors remain on site until the owner’s last inspection. And when the project is a “problem project,” the owner or prime contractor tend to liberally share their losses and liquidated damages among those specialty contractors remaining on site at the end. So what is an electrical contractor to do when the project starts coming off the rails?
What is a Problem Project?
First, it helps to identify the attributes of a problem project. While there are many negative qualities of a bad job, a problem project is one that busts budgets – whether labor, material, or time. Most commonly, the problem project will significantly exceed the labor budget. Because an electrical contractor’s most important (and understandably expensive) resource is its people, the labor budget is critical to the success of a job. When a project suffers delays or is ineptly managed, the labor costs soar, turning a potentially profitable job into a disaster.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Illinois Law Bars Coverage for Construction Defects in Insured's Work
September 24, 2014 —
Tred R. Eyerly – Insurance Law HawaiiApplying Illinois law, the Seventh Circuit determined there was no coverage for faulty workmanship causing property damage to the insured's project. Nautilus Ins. Co. v. Board of Directors of Regal Lofts Condominium Ass'n, 2014 U.S. App. LEXIS 16250 (7th Cir. Aug. 21, 2014).
The developer converted a vacant building into a condominium. The construction was completed in 2000. The Condominium Board took control of the condo association on July 27, 2000. As early as May 2000, one homeowner was aware of water damage problems in the building. Other complaints surfaced. An investigation found that the exterior brick masonry walls were not fully waterproofed, which caused leaks. The investigation further showed that deteriorated conditions had likely developed over many years, even prior to the condominium conversion, but the present water penetration was caused by the inadequate restoration of the walls to a water-tight condition.
The underlying action was filed against the developer for failure to properly construct the exterior walls. The developer's carrier, Nautilus, denied coverage. In an amended complaint, the Board added a count of negligence. Again, Nautilus denied coverage. The Board's second amended complaint alleged that the developer's negligence had caused damage to personal property within the building, in addition to the interior of the building and the building itself. For the third time, Nautilus denied coverage and filed for declaratory relief.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Leaning Tower of San Francisco
January 24, 2018 —
Dave Suggs - CDJ STAFFThe Millennium Tower located at 301 Mission Street in San Francisco, California opened in 2009 and is fifty-eight stories high. It is comprised of expensive apartments with price tags in the millions. “Yet for all its curb appeal, the building has, quite literally one fundamental problem: it’s sinking into mud and tilting towards its neighbors” reports John Wetheim of CBS News in the
60 Minutes segment about the condition of the tower “San Francisco’s Leaning Tower of Lawsuits.”
In the Tower’s basement along columns that protrude from the foundation of the building there are stress gauges lining the walls illustrating cracks with slow growth which is cause for concern. The tower is tilting a total of 14 inches toward the northwest and has sunk 17 inches so far. Petar Marinkovic, an engineer for the European Space Agency estimates that the tower is sinking 1.5 to 2 inches per year.
Jerry Cauthen, a local engineer, weighs in on what he believes is the cause of the sinking and leaning; it was built from concrete instead of steel. “Concrete is often cheaper. And it’s just as good, but it is a lot heavier. And so you got to design your foundation and your sub-surface to support that higher weight.” A local geotechnical engineer, Larry Karp agrees stating that the foundation of a building of this size and weight should be on solid rock (bedrock). The Millennium Tower is sitting on layers debris from the 1906 earthquake, a gold rush landfill, as well as clay, mud, and sand.
There over 20 parties involved in the Millennium Tower lawsuits so far. Solutions to “fix” the tower’s issues range from removing 20 stories from the top of the building to perpetually freezing the ground beneath the building. There are also ongoing mediation talks to determine the feasibility of drilling down to bedrock under a building where a thousand residents are still upstairs.
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Round-Up (10/06/21)
October 18, 2021 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogReal estate tokenization and smart home technology continue to grow, negotiations surrounding the bipartisan infrastructure bill stall its passing, artificial intelligence is poised to transform the construction industry, and more.
- Contra Global leverages real estate tokenization, the process of creating tokens on the Blockchain and assigning them to real estate properties that already exist or are under construction, to remove traditionally high barriers to investment entry as well as intermediary fees in the industry. (Navid Ladani, Yahoo Finance)
- Following the 2-week closure of the construction industry after protests turned violent over vaccine mandates, the Victorian government announced its reopening with up to 25 percent capacity of workers and new vaccination rules. (ABC News)
- Though the construction industry has traditionally relied heavily on human experience and expertise to complete projects, the industry is rapidly adopting digital solutions to adapt to chronic labor shortages, the need for sustainable solutions, and supply-chain disruptions. (Tom Taulli, Forbes)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team