Contractors and Force Majeure: Contractual Protection from Hurricanes and Severe Weather
October 11, 2017 —
Christopher G. Hill - Construction Law MusingsThis week’s Guest Post Friday here at Musings welcomes back Clay Olsen. Clay is is an attorney at Harper Whitwell PLLC. The firm is located in Mississippi and South Carolina where they routinely represent the interests of construction.
This season is not special as hurricanes are a part of life on the east coast and gulf shores. From New York to Louisiana, just about every state has seen massive property loss from hurricanes during the past ten years.
We often see harsh outcomes for those on the coast living in finished homes. What happens to the unfinished and current projects awaiting completion? If you’re building on the coast, take a look at all of the following risk aversion mechanisms:
- Builders Risk Insurance is necessary as is Coverage for named storms. Be sure to review the “excluded perils” or speak to your agent as hurricane coverage best not be omitted.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Offices of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
U.S. Government Bans Use of Mandatory Arbitration Agreements between Nursing Homes and Residents, Effective November 28, 2016
November 17, 2016 —
Jeffrey M. Daitz & Joseph Vento – Peckar & Abramson, P.C.On September 28, 2016, the Centers for Medicare and Medicaid Services (“CMS”), which is part of the U.S. Department of Health and Human Services, issued a new rule that bans federal funding to any nursing home that requires its residents to enter mandatory pre-dispute arbitration agreements upon admission. The rule prevents nursing homes from forcing residents to submit any disputes concerning care, payment for services, etc., to mandatory binding arbitration rather than to a court.
Mandatory arbitration agreements are frequently used in many types of industries and have been for decades. However, recent eff orts by several consumer advocate groups have sought to curtail the use of mandatory arbitration clauses in industries where the individuals who executed such agreements have little to no bargaining power. According to these groups, nursing home residents are potentially more vulnerable than most to being unwittingly bound by such agreements because of the nature of the admissions process. The new rule is set to take effect on November 28, 2016, and will only apply to agreements entered into after that date.
Reprinted courtesy of
Jeffrey M. Daitz, Peckar & Abramson, P.C. and
Joseph Vento, Peckar & Abramson, P.C.
Mr. Daitz may be contacted at jdaitz@pecklaw.com
Mr. Vento may be contacted at jvento@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The Great Skyscraper Comeback Skips North America
February 05, 2015 —
Patrick Clark – BloombergTall buildings are back. Developers around the globe completed a record 97 buildings of at least 200 meters (656 feet) in height in 2014, according to a new report from the Council on Tall Buildings and Urban Habitat, as size-obsessed builders got back on a growth track after a two-year skyscraper dip.
It’s not hard to explain the pattern. A typical skyscraper takes two to four years to finish, says report co-author Daniel Safarik. Work back from the year of completion, and the global financial crisis looks like an easy explanation for the drop-off in tall buildings. If you thought it was hard to get a home loan in 2009, imagine asking bankers to finance a gravity-and-wind-defying symbol of luxury, industry, and capitalist will. Especially, as Bloomberg Businessweek’s Bryant Urstadt pointed out, since supertall buildings are notorious for being hard to fill with tenants. (It’s worth noting that “tall” isn’t a technical term, though “supertall,” which is used to describe buildings more than 300 meters tall, is. And construction schedules vary. The Ryugyong Hotel in Pyongyang, North Korea, planned for 330 meters, has been under construction for 28 years, according to a CTBUH report last year.)
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Clark, Bloomberg
How Algorithmic Design Improves Collaboration in Building Design
June 18, 2019 —
Aarni Heiskanen - AEC BusinessDesign, like everything else in a construction project, is a collaborative effort. Even with digital tools, collaboration across design disciplines is not yet optimal. An experimental project thus set out to test whether algorithmic design could help streamline the interaction between architects and structural engineers.
Design data originating from an architect is used in several engineering tools for visualization, analysis, and calculation. Ideally, changes in the architect’s design would propagate automatically across all the software. Unfortunately, the process is in fact mostly manual. Hence, the design data is seldom, if ever, in perfect sync on all systems.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Recovering For Inflation On Federal Contracts: Recent DOD Guidance On Economic Price Adjustment Clauses
October 24, 2022 —
Amanda L. Marutzky - ConsensusDocsSince October 2020, inflation in the United States has seen its fastest increase in more than 30 years. In the last year alone, inflation has remained as high as 8.6%. This hike has impacted everything from diesel to steel. In the construction industry, the higher prices of goods and services directly affect how contractors draft their construction contracts.
The Department of Defense (DoD) has taken note of this dramatic price increase and recently issued guidance to its commanding officers and the procurement community. On May 5, 2022, DoD issued a memorandum titled “Guidance on Inflation and Economic Price Adjustments.” The stated purpose of the memo is “to assist COs to understand whether it is appropriate to recognize cost increases due to inflation under existing contracts as well as offer considerations for the proper use of EPA when entering into new contracts.” DoD’s memo responds to contractor and contracting officer concerns about the sudden and unexpected cost increases in labor and materials.
Economic Price Adjustments, or EPAs, are adjustments to a stated contract price upon the occurrence of certain contingencies. FAR 16.203-1. They are of three general types – (1) adjustments based on established prices, (2) adjustments based on actual costs of labor or material, or (3) adjustments based on cost indexes of labor or material. Id. Because EPAs allow for adjustments in a contract price, EPA clauses allow a contractor to recover unanticipated increases in its project costs. For example, FAR 52.216-4, Economic Price Adjustment-Labor and Material, authorizes a contractor to recover for increases in the cost of material or labor. Such recovery is available when costs increase more than 3%, with a maximum recovery of 10% of the original contract price. See also FAR 52.216-2 through FAR 52.216-4. These EPA clauses provide contractors with relief and protection from issues such as dramatic inflation. EPA clauses, however, are not included in all contracts.
Read the court decisionRead the full story...Reprinted courtesy of
Amanda L. Marutzky, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)Ms. Marutzky may be contacted at
amarutzky@watttieder.com
Georgia Federal Court Holds That Pollution Exclusion Bars Coverage Under Liability Policy for Claims Arising From Discharge of PFAS Into Waterways
December 18, 2022 —
Paul Briganti - White and WilliamsOn December 5, 2022, the U.S. District Court for the District of Georgia held that a total pollution exclusion (TPE) in a CGL policy relieved the insurer of any obligation to defend or indemnify a recycling company in a putative class action alleging PFAS contamination of Georgia waterways. See Grange Ins. Co. v. Cycle-Tex Inc., et al., Order, Civ. A. No. 4:21-cv-00147-AT (N.D. Ga. Dec. 5, 2022). The decision adds to a slowly-developing body of case law addressing coverage issues arising out of PFAS-related claims.
In Grange, the insured, Cycle-Tex, Inc., was the operator of a thermoplastics recycling facility in Dalton, Georgia. Cycle-Tex and other defendants – which included chemical suppliers, carpet manufacturers, intermediaries, the City of Dalton and the Dalton-Whitfield Solid Waste Authority – were named in a putative class action complaint alleging that residents of Dalton had been injured as a result of the defendants’ discharge of PFAS into local waterways. The complaint sought damages for: (1) alleged harm to the residents’ health by virtue of ingesting contaminated water; (2) alleged property damage resulting from the contamination of the public water supply; and (3) the payment of surcharges and heightened water rates as a result of the alleged contamination.
Read the court decisionRead the full story...Reprinted courtesy of
Paul Briganti, White and WilliamsMr. Briganti may be contacted at
brigantip@whiteandwilliams.com
General Contractor’s Intentionally False Certifications Bar It From Any Recovery From Owner
November 03, 2016 —
Masaki James Yamada – Ahlers & Cressman PLLCIn a public works dispute in Massachusetts, a Massachusetts Court judge ruled that a general contractor could not recover any of its over $14 million claim against a public owner because it had violated its contract with the Owner by certifying that it had paid its subcontractors in full and on time when in fact it had not.[i] The case involves a contract dispute arising from a state and federally-funded project to design and construct a fiber optic network in western Massachusetts. The Owner was a state development agency established and organized to receive both state and federal funding to build a 1,200–mile fiber optic network known as MassBroadband123 in Western Massachusetts (the Project). Of that amount, $45.4 million was awarded pursuant to the American Recovery and Reinvestment Act of 2009 (ARRA). One of the stated goals of ARRA was (as its title suggests) to create jobs in the wake of the 2008 recession and to provide a direct financial boost to those impacted by the economic crisis. In the context of the instant case, that meant that, if there were to be subcontractors on the job providing labor and materials, they needed to be paid on a timely basis in keeping with the statutory purpose of stimulating the economy.
Read the court decisionRead the full story...Reprinted courtesy of
Masaki James Yamada, Ahlers & Cressman PLLCMr. Yamada may be contacted at
myamada@ac-lawyers.com
Congratulations to Haight Attorneys Selected to the 2021 Southern California Super Lawyers List
January 25, 2021 —
Haight Brown & Bonesteel LLPEight Haight attorneys have been selected to the 2021 Southern California Super Lawyers list.
Congratulations to:
Read the court decisionRead the full story...Reprinted courtesy of
Haight Brown & Bonesteel LLP