Apprentices on Public Works Projects: Sometimes it’s Not What You Do But Who You Do the Work For That Counts
September 17, 2015 —
Garret Murai – California Construction Law BlogIf you’re a public works contractor in California you’re familiar with prevailing wages. The Prevailing Wage Law, a Depression era law designed to encourage the hiring of local labor, sets a minimum wage that employers must pay to workers on public works projects.
But because the Prevailing Wage Law sets a floor on wages it also limits the opportunity for lesser-skilled workers to gain experience. To address this, the Prevailing Wage Law permits contractors to pay apprentices a lower “apprentice wage” if the apprentice is enrolled in a state-approved apprenticeship program and requires contractors who hire workers in an “apprenticeable craft or trade” to hire a certain number of apprentices.
But are particular apprentices required to be hired depending on the type of work being performed? In Henson v. C. Overaa & Company, Case No A139966 (June 29, 2015), the California Court of Appeals for the First District held that apprentices are required to be hired based on the craft or trade of the journeymen performing work not based on the type of work being performed.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Firm Pays $8.4M to Settle Hurricane Restoration Contract Case
December 13, 2022 —
James Leggate - Engineering News-RecordAn electricity distribution infrastructure contractor that worked for the U.S. Army Corps of Engineers on hurricane restoration in Puerto Rico has agreed to pay the government $8.4 million to resolve allegations that it improperly withheld pricing data. The company denies the charges, agreeing to the settlement in order to avoid lengthy litigation.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Differences in Types of Damages Matter
June 22, 2016 —
Christopher G. Hill – Construction Law MusingsOver the last 7 and a half years (yes I have been doing this for that long), I have often “mused” on various contractual provisions and their application. Why? Because
the contract matters and will be enforced. Provisions like “no damages for delay” and “
pay if paid” litter construction contracts and will be enforced if properly drafted. These types of clauses affect whether and what types of damages you as a construction company can collect.
Of course, these clauses have their limitations. For instance, and as
pointed out by my pal Matt DeVries at his great Best Practices Construction Law blog, not all damages that a subcontractor or general contractor may attribute to coordination or other scheduling related issues are “delay damages” to which a “no damages for delay” clause may apply.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Recent Developments in Legislative Efforts To Combat Climate Change
October 30, 2023 —
Dominick Weinkam & Robert B. Cimmino - ConsensusDocsGovernments across the United States have been increasingly integrating climate considerations into legislation affecting various sectors of the economy. The construction industry is no exception. Recent legislative developments at various levels of government are reshaping construction practices to mitigate the industries’ greenhouse gas emissions and vulnerability to climate-related risks. These developments include incentivizing eco-friendly construction projects, mandating stricter regulations to reduce carbon emissions, and enhancing building resilience to more severe weather events. Contractors must stay abreast of these developments to ensure compliance with new substantive and administrative requirements to remain competitive in a changing environment.
Funding Greener Construction Projects: The Inflation Reduction Act
The federal Inflation Reduction Act (IRA) enacted in August 2022 marked a significant milestone in the pursuit of greener construction. The IRA is widely considered to be the single largest investment into climate change in history, with potential ripple effects throughout the construction industry. The IRA allocates substantial funds for projects utilizing “low-carbon” materials, with an explicit focus on climate-conscious construction. This initiative aligns with the broader goal of curbing emissions from sectors like steel, concrete, and glass, which have been major contributors to the nation’s carbon footprint.
Reprinted courtesy of
Dominick Weinkam, Watt Tieder and
Robert B. Cimmino, Watt Tieder
Mr. Weinkam may be contacted at dweinkam@watttieder.com
Mr. Cimmino may be contacted at rcimmino@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
Are COVID-19 Claims Covered by Builders Risk Insurance Policies?
May 04, 2020 —
Jason M. Adams, Gibbs Giden Locher Turner Senet & Wittbrodt LLP and Cheryl L. Kozdrey, Saxe Doernberger & Vita, P.C.If you are an attorney, insurance broker, or other professional representing developers and contractors, then your clients have likely reached out with concerns about losses related to COVID-19. One common question is whether there is potential coverage under builders risk insurance policies.
The short answer is: It depends. As with most questions pertaining to insurance coverage, the answers depend on the specific policy language and underlying facts required to trigger coverage. Builders risk policies are even more fact specific due to the lack of uniformity of base policy forms and endorsements between insurance carriers.
The first step in any analysis is to gather facts and carefully document any impending and potential damages or delays. The facts are crucial because the coverage analysis may vary depending on the specific reason the project was shut down. For example, the analysis would be different if the project was shut down as a result of an express government order, such as those in Northern California and Washington, versus the project shutting down as a result of workers testing positive for COVID-19. Properly analyzing builders risk coverage involves a granular account of the facts and damages, and can require a great deal of hair splitting with respect to specific policy language.
Regardless of the strength of the insured’s facts and damages, or the breadth of its policy language, the policyholder still likely faces an uphill battle in finding coverage for COVID-19 related claims. The unfortunate reality of most builders risk policies is that they are property policies that require some evidence of physical loss or damage to trigger coverage. Whether or not COVID-19 claims constitute property damage will be the subject of great debate and litigation over the coming months and years. The outcome will likely depend on how the insured’s jurisdiction ultimately rules on the litany of COVID-19 cases that have already been filed – specifically, how broadly each court interprets the meaning of “physical loss or damage.”
Although these key issues have yet to be clearly defined by the courts, some policies are better than others and there are specific variables that could affect the likelihood of coverage. For example, some of the more policyholder-friendly insurance programs may contain coverage extensions for delay in completion, business interruption, loss of rental income, or civil authority that may not be tied to the property damage requirement, and which would tend to support coverage for COVID-19 claims.
Even if the insured crosses the initial threshold and can demonstrate a covered claim, the following common endorsements and exclusions may require additional analysis depending on the facts.
- Virus or Pandemic Exclusions: Virus or pandemic exclusions are not as common on builders risk policies as they may be on other forms of coverage. However, they do exist and, if present, result in a significant barrier to coverage. As with the policy itself, every endorsement is different and should be analyzed in terms of the express language contained in the endorsement and the facts.
- Abandonment or Cessation of Work: Most builders risk policies include provisions that preclude coverage in the event of the abandonment of the project or a lengthy cessation of work. As a result, the insured should take steps to articulate to the carrier that the project has not been abandoned, and that there exists an intent to return as soon as possible. The insured should also maintain a record of ongoing project oversight and protection efforts taken during the period when construction operations are suspended.
- Security and Safety Requirements: Many builders risk policies contain provisions requiring the insured to maintain protective safeguards and security protocols throughout the pendency of the project. Safety fencing, lighting and security guards are common examples. The policy should be analyzed to ensure that the policyholder can meet any such requirements during a COVID-19 related shutdown. For example, can the insured continue to staff a security guard? If not, arrangements will likely need to be made with the carrier depending on the language of the policy.
- Insurable Limits: Builders risk policies are typically underwritten based upon the total completed value of the structure, including materials and labor. The insured will need to analyze the policy to consider whether increased material or labor costs as a result of COVID-19 will alter the terms of coverage, trigger any escalation clauses, or result in an increase in premium due. If increased cost projections become apparent, the insured should report these changes to the carrier immediately.
- Extensions of Coverage: The insurance industry was facing a hard market even before the COVID-19 pandemic, which resulted in higher premiums and limited coverage options. The COVID-19 pandemic has only exacerbated these issues and it may be difficult to obtain coverage extensions on projects that have been shut down. The insured should work with its risk management team (risk manager, insurance broker and lawyer) to engage the carriers to negotiate any necessary coverage extensions resulting from COVID-19 related project delays.
To summarize, builders risk coverage for COVID-19 claims is far from certain, but not impossible. Insureds should provide notice of a claim to all potentially applicable carriers in order to preserve their rights. The insured should also report increased construction cost and articulate its intent to return to the project to preserve their escalation clause and avoid arguments that they have abandoned the project. The insured should continue to document its claims and damages, and be ready to substantiate its claims and push back on any coverage denial. Throughout the entirety of this process, the insured should work with its risk management team to get out in front of any extensions it may need to complete the project. In a climate where insurance carriers are receiving an insurmountable number of claims, the insured should be prepared to fight for coverage and not simply throw up its hands in the face of a denial. Given the intense social, legislative and executive pressure to cover COVID-19 claims, there may be a tendency for the courts to find coverage in gray areas, particularly if the insured was fortunate enough to have purchased one of the broader coverage forms referenced above.
About the Authors
Jason M. Adams, Esq. (jadams@gibbsgiden.com) is a partner at Gibbs Giden representing construction professionals in the areas of Construction Law, Insurance Law and Risk Management and Business/Civil Litigation. Adams is also a licensed property and casualty insurance broker and certified Construction Risk & Insurance Specialist (CRIS). Jason represents developers, contractors, public entities, investors, lenders, REITs, design professionals, and other construction professionals at all stages of the construction process. Jason is a published author and sought-after speaker at seminars across the country regarding high level construction risk management and insurance topics. Gibbs Giden is nationally and locally recognized by U. S. News and Best Lawyers as among the “Best Law Firms” in both Construction Law and Construction Litigation. Chambers USA Directory of Leading Lawyers has consistently recognized Gibbs Giden as among California’s elite construction law firms.
Cheryl L. Kozdrey, Esq. (clk@sdvlaw.com) is an associate at Saxe Doernberger & Vita, P.C., a national insurance coverage law firm dedicated exclusively to policyholder representation and advocacy. Cheryl advises insurance brokers, risk managers, and construction industry professionals regarding optimal risk transfer strategies and insurance solutions, including key considerations for Builder’s Risk, Commercial General Liability, D&O, and Commercial Property policies. She assists clients with initial policy reviews, as well as renewals and modification(s) of existing policies to ensure coverage needs are satisfied. Cheryl also represents policyholders throughout the claims process, and in coverage dispute litigation against insurance carriers. She is currently working on some of the largest construction defect cases in the country. Cheryl is a published author and is admitted to practice in the State of California and all federal district courts within the State.
Read the court decisionRead the full story...Reprinted courtesy of
Ahead of the Storm: Preparing for Irma
September 07, 2017 —
Stephen H. Reisman – Peckar & Abramson, P.C.While Hurricane Irma boils in the Atlantic and seems to be aiming towards Florida, storm preparations are well underway. As contractors are busy organizing efforts to secure their job sites, we at Peckar & Abramson offer some quick reminders that may prove helpful when the dust finally settles:
- Review your contracts, particularly the force majeure provisions, and be sure to comply with applicable notice requirements.
- Even if not expressly required at this point in time, consider providing written notice to project owners that their projects are being prepared for a potential hurricane or tropical storm and that productivity and the progress of the work will be affected, with the actual time and cost impact to be determined after the event.
- Consult your hurricane plan (which is often a contract exhibit) and confirm compliance with all specified safety, security and protection measures.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen H. Reisman, Peckar & Abramson, P.C.Mr. Reisman may be contacted at
sreisman@pecklaw.com
Home insurance perks for green-friendly design (guest post)
February 04, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaWondering how to get your residential clients to pony up more money for green design? Check out today’s guest post by Carrie Van Brunt-Wiley and Katherine Wood. They are writers for the Homeowners’ Insurance Blog, which serves as a resource center for insurance consumers and homebuyers across the country.
The U.S. Green Building Council’s new LEEDv4 standards present challenges for contractors, engineers, and architects – the restrictions in many cases are more stringent. There is, however an added bonus to remaining on the sustainable-building track: it’s more marketable than you think.
That’s because green homes don’t just appeal to buyers with environmental concerns any more. Now smart budgeters seek them out as well. Why? While it’s true that sustainable construction can cost about 2% more than conventional methods, McGraw-Hill’s Smart Market Report says it typically increases a building’s overall value by an average of 7.5% and improves the return on investment by 6.6%.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback can be contacted at
mbrumback@rl-law.com
Flow-Down Clauses Can Drown Your Project
August 26, 2015 —
Craig Martin – Construction Contractor AdvisorFlow-Down or pass-through clauses obligate downstream contractors to certain provisions contained in the up up-stream contractor contracts, such as the contract between the general contractor and the owner. These clauses are contained in every major form subcontract and they can expand the scope of your potential liability. This blog will look at typical language of a flow-down clause, what it means and how you can deal with them.
Typical Flow-Down Clause
A simple flow down clause might provide:
“The Subcontractor agrees to be bound to the Contractor by the terms of the prime contract and to assume to the Contractor all the obligations and responsibilities that the Contractor by those documents assumes to the Owner, except to the extent that the provisions contained therein are by the terms or by law applicable only to the Contractor.”
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com