Be Careful When Walking Off of a Construction Project
November 24, 2019 —
Christopher G. Hill - Construction Law MusingsI am truly grateful that my buddy Craig Martin (@craigmartin_jd) continues his great posts over at The Construction Contractor Advisor blog. He is always a good cure for writer’s block and once again this week he gave me some inspiration. In his most recent post, Craig discusses a recent Indiana case relating to the ever present issue of termination by a subcontractor for non-payment. In the Indiana case, the court looked at the payment terms and determined that the subcontractor was justified in walking from the project when it was not paid after 60 days per the contract.
This result was the correct, if surprising. Why do I say surprising? Because I am always reluctant to recommend that a subcontractor walk from a job for non payment if it is possible to continue. This is not so much for legal reasons (not paying a sub is a clear breach of contract by a general contractor) but practical ones. The practical effect of walking from the job is that the subcontractor is put on the defensive. Instead of arguing later that it performed but was not paid, that subcontractor is put in the position of arguing that the general contractor cannot collect its completion related and other damages because it breached first. This is a more intuitively difficult argument and one that is not as strong as the first.
Of course, all of this is contingent on the language in your contract (is there a “pay if paid” or language like that in the Indiana case?).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Contractors: Revisit your Force Majeure Provisions to Account for Hurricanes
September 14, 2017 —
David Adelstein - Florida Construction Legal UpdatesWe now know and can appreciate the threat of hurricanes. Not that we did not appreciate the reality of hurricanes–of course we did–but Hurricane Harvey and Hurricane Irma created the type of actual devastation we fear because they hit close to home. The fear came to life, creating panic, anxiety, and uncertainty. It is hard to plan for a force majeure event such as a hurricane because of the capriciousness of Mother Nature. But, we need to do so from this point forward. No exception! And, I mean no exception!!
A force majeure event is an uncontrollable event that cannot be anticipated with any degree of definitiveness. The force majeure event will excusably delay or hinder performance obligations under a contract. One type of force majeure event is a hurricane—an uncontrollable and unforeseen act of Mother Nature.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
California Contractors: Amended Section 7141.5 Provides Important License Renewal Safety Net
July 25, 2021 —
Amy L. Pierce, Mark A. Oertel, John Lubitz & Adam B. Wiens - Lewis BrisboisUnder California’s Contractors State License Law, Cal. Bus. & Prof. Code §§ 7000 et seq., contractors’ licenses expire two years from the last day of the month in which the license was issued or two years from the date on which the renewed license last expired. The Contractors State License Board (CSLB) sends licensees a renewal application 60 to 90 days in advance of the date the license is set to expire. Even with various controls in place, mistakes happen and a renewal application filing deadline can be missed.
During the August 5-6, 2019 Executive, Licensing, and Legislative Committee Meetings, the CSLB discussed proposed amendments to Section 7141.5 to reduce both the burden on it to review applications for retroactive renewal of a license that had not been timely submitted and to provide contractors with some relief from the high burden to establish “the failure to renew was due to circumstances beyond the control of the licensee.” Not long after, the CSLB’s Board of Directors gave staff approval to seek an author for the bill and, on September 29, 2020, Governor Newsom signed Senate Bill 1474 into law, which includes the CSLB’s proposed amendments to Section 7141.5, effective January 1, 2021.
Reprinted courtesy of
Amy L. Pierce, Lewis Brisbois,
Mark A. Oertel, Lewis Brisbois,
John Lubitz, Lewis Brisbois and
Adam B. Wiens, Lewis Brisbois
Ms. Pierce may be contacted at Amy.Pierce@lewisbrisbois.com
Mr. Oertel may be contacted at Mark.Oertel@lewisbrisbois.com
Mr. Lubitz may be contacted at John.Lubitz@lewisbrisbois.com
Mr. Wiens may be contacted at Adam.Wiens@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
California Judicial Council Votes to Rescind Prohibitions on Eviction and Foreclosure Proceedings
September 28, 2020 —
David Rao & Lyndsey Torp - Snell & Wilmer Real Estate Litigation BlogThe California Judicial Council’s emergency rules staying evictions and judicial foreclosures are coming to an end.
On March 27, 2020, the Governor of California issued executive order N-38-20, giving the Judicial Council emergency authority to act in response to the COVID-19 pandemic. On April 6, 2020, the Judicial Council of California voted to approve temporary emergency rules of court. Rule 1 prohibited the issuance of a summons, or the entering of a default, in an eviction action for both residential and commercial properties except as necessary to protect public health and safety. Rule 1 also continued all pending unlawful detainer trials for at least 60 days, with no new trials being set until at least 60 days after a request was filed. Rule 2 stayed all pending judicial foreclosure actions, tolled the statute of limitations, and extended the deadlines for responding to such actions.
Rule 1 and Rule 2 were to remain in effect until 90 days after the Governor declared the state of emergency resulting from the COVID-19 pandemic lifted, or until repealed by action of the Judicial Council. On August 13, 2020, the Judicial Council voted 19-1 to sunset Rule 1 and Rule 2 as of September 1, 2020. Beginning September 2, 2020, California state courts are authorized to issue summons on unlawful detainer actions, enter defaults, and set trial dates on request. Stays on pending judicial foreclosure actions will be lifted.
Reprinted courtesy of
David Rao, Snell & Wilmer and
Lyndsey Torp, Snell & Wilmer
Mr. Rao may be contacted at drao@swlaw.com
Ms. Torp may be contacted at ltorp@swlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Despite Construction Gains, Cement Maker Sees Loss
May 10, 2013 —
CDJ STAFFVulcan Materials, the Birmingham, Alabama-based business that describes itself as the nation’s largest producer of construction aggregates and aggregate-based construction materials, has reported that its losses have increased to $54.8 million in the first quarter of 2013. This was on revenues of $538 million, an increase from the past. The first quarter also saw the company shipping 248,000 tons of material, an increase of fourteen percent over the first quarter of 2012. Losses were attributed to bad weather, lower production volumes, and an increase in costs.
Global Cement quotes Don James, the chairman and CEO of Vulcan, “growth in residential construction activity and its traditional follow-on impact to private non-residential construction underpins our expectations for volume and earnings improvement in 2013.”
Read the court decisionRead the full story...Reprinted courtesy of
Times Square Alteration Opened Up a Can of Worms
January 26, 2017 —
Nadine M. Post – Engineering News-RecordCompared with some of its Manhattan neighbors, a high-rise on the corner of Seventh Avenue and West 47th Street looks standard. Like many buildings in Times Square, the 41-story retail-entertainment-hotel development, nearly topped out, has a tower springing from a boxy base that will sport a flashy billboard.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. Post, Engineering News-RecordMs. Post may be contacted at
postn@enr.com
Avoid a Derailed Settlement in Construction
March 28, 2022 —
Patrick Barthet - Construction ExecutiveMore and more construction cases are settling because lawyers know juries can prove to be unpredictable. The litigation process, as well as any actual trial, can be stressful, expensive and quite lengthy. Settlements are, for the most part, private while suits are public. Current reports find more than 90% of civil cases filed in state circuit courts are disposed of before trial. When that doesn't happen, things could go very poorly, as the case below illustrates.
The Case
Adam was seriously injured in a collision with a dump truck owned by Bang and driven by Tomas. While suit by Adam against Bang and Tomas was pending, Adam suggested they settle by having Bang pay him. Upon receipt of the offer, Bang's lawyer reached out confirming that his client was okay with the settlement amount but wished to add that the settlement also include the satisfaction of a lien filed by Adam's workers' compensation carrier. Adam's attorney refused that additional request, but that didn't stop Bang's lawyer. Based on the fact that Adam had agreed to the settlement amount, the lawyer filed a boiler plate notice of acceptance of settlement and had Bang issue a settlement check payable to Adam in the amount Adam had requested. Adam remained unwilling to compromise. He continued to resist the modified terms, which added satisfaction of the worker’s compensation lien. Bang then filed a motion to enforce settlement, arguing that since there was agreement on the settlement amount, Adam was required to do the deal.
Reprinted courtesy of
Patrick Barthet, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Barthet may be contacted at
pbarthet@barthet.com
No Coverage for Construction Defect Claim Only Impacting Insured's Work
January 08, 2024 —
Tred R. Eyerly - Insurance Law HawaiiIn a coverage dispute between two insurers over a claim for damages caused by faulty workmanship, the court found there was no right to equitable contribution or indemnity. Travelers Prop. Cas. Co. of Am. v. Mallcraft, Inc., 2023 Cal. Super. LEXIS 67568 (Cal. Super. Ct. Sept. 15, 2023).
Mallcraft was the general contractor for a building project and was sued for construction defects. Travelers was an additional insured under a policy issued to a subcontractor, KitCor. Travelers defended Mallcraft in an arbitration. Travelers sought equitable contribution and equitable indemnity from Hartford, Mallcraft's insurer.
Mallcraft and Travelers stiulated to a judgment agianst Mallcraft for all costs Travelers incurred in the arbitration. Travelers' insured, KitCor, was not implicated in the construction defect claims against Mallcraft. The judgment set forth findings, including the fact that the underlying plaintiff never made any claim that KitCor perfomred work on the project or casued property damage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com