WA Supreme Court Allows Property Owner to Sue Engineering Firm for Lost Profits
February 25, 2014 —
Beverley BevenFlorez-CDJ STAFFIn the Daily Journal of Commerce, Scott A. Smith and James H. Wendell discussed the recent Washington Supreme Court decision in Donatelli v D. R. Strong Consulting Engineers. The court’s ruling casts “doubt on a company's ability to limit its liability for economic losses arising out of a contract dispute.”
The Donatellis hired D. R. Strong Consulting Engineers to develop vacant land in King County, however, the “project did not go according to plan and the real estate market collapsed before the project was completed,” according to the Daily Journal of Commerce. The “Donatellis lost their property through foreclosure” and then “sued the engineering firm for more than $1.5 million in lost profits.”
D. R. Strong Consulting Engineers asked for the negligence claims to be dismissed “because the parties' contract contained a provision limiting the engineering firm's liability to the amount of its fee for ‘any injury or loss on account of any error, omission, or other professional negligence.’” However, the Washington Supreme Court ruled that “the case could proceed in the trial court on a theory that the engineers could be liable if they made negligent misrepresentations that induced the Donatellis to enter into the contract in the first place.”
Smith and Wendell stated that because of “this decision, engineering, architectural, construction, and other professional service companies may now face damage claims they thought they were contractually protected against.”
Read the court decisionRead the full story...Reprinted courtesy of
Design-Build Contracting for County Road Projects
September 19, 2022 —
David R. Cook Jr. - Autry, Hall & Cook, LLPEffective July 1, 2022, counties may execute design-build contracts for transportation-related projects that include buildings, bridges and approaches, rail corridors, technology deployments, and limited- or controlled-access project, or projects that may be constructed within existing rights of way when the work is clearly defined or when significant savings may result in project delivery time.
[1] Additionally, counties may combine any environmental services, utility-relocation services, right-of-way services, design services, and construction phases of a public road or other project into a single design-build contract.
Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLP
Mr. Cook may be contacted at cook@ahclaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Housing Agency Claims It Is Not a Party in Construction Defect Case
February 28, 2013 —
CDJ STAFFThe Aspen/Pitkin County Housing Authority (APCHA) is seeking to be removed from a construction defect suit filed by Aspen homeowners. APCHA claims that it should not be a party to the suit, since it had nothing to do with the development of the Burlingame Ranch community. Responsibility should instead, according to the agency, rest with the City of Aspen. APCHA’s role was to sell the homes to individuals whom it had verified were eligible to purchase affordable housing. Tom McCabe, the director of APCHA said that “APCHA has no part in the building of housing anymore, and we haven’t for a long time.”
Chris Rhody, who represents the Burlingame homeowners, feels that APCHA should be involved. The homeowners are alleging that construction defects, including cracked exterior siding, are the result of faulty materials and improper installation.
Read the court decisionRead the full story...Reprinted courtesy of
Why You Make A Better Wall Than A Window: Why Policyholders Can Rest Assured That Insurers Should Pay Legal Bills for Claims with Potential Coverage
March 14, 2018 —
Alan Packer and Graham Mills - Newmeyer & Dillion, LLPUnfortunately, policyholders, such as manufacturers and contractors, routinely face the unnecessary challenge of how to access all of the insurance coverage which they have purchased. Frequently, the most pressing need is to get the insurance company to pay the legal bills when the policyholders have been sued. The recent Iowa federal district court opinion in
Pella Corporation v. Liberty Mutual Insurance Company should help a policyholder in a dispute to require its insurance company to pay those legal bills sooner rather than later by highlighting that the duty to defend arises from the potential for coverage, and the insurer may not force the policyholder to prove the damage to obtain a defense.
In
Pella, a window manufacturer purchased several years of insurance coverage from Liberty Mutual. Similar to many companies, Pella had many “layers” of insurance coverage in any given year. These layers collectively function like a tower. The general idea is that each layer provides a certain amount of coverage after the insurance policy below it had paid its money. The Liberty Mutual insurance policies provided excess coverage.
After the
Pella window manufacturer made and sold its windows, it was sued in numerous lawsuits alleging that its windows were defective and that those defective windows caused a wide variety of damage to the structures in which they were installed. The window manufacturer tendered those lawsuits to its insurance companies in its tower of coverage, asking that the insurance companies pay its legal bills incurred in its defense. As to Liberty Mutual, the window manufacturer argued that the Liberty Mutual insurance policies were triggered, and so obligated to reimburse it, if a window was installed during the years that those policies provided coverage or if there was a mere allegation that a window was installed during the years that those policies provided coverage. Liberty Mutual opposed, arguing that the date of installation of the windows was insufficient to trigger the policies, and that the manufacturer was required to demonstrate the date that damage actually occurred to trigger a defense.
The key issue before the
Pella Court in this decision was a simple one: which insurance policies, if any, issued by Liberty Mutual had an obligation to pay the window manufacturer’s legal bills? The answer to that question is critical and financially significant. Getting an insurance company to honor its obligations and start paying the legal bills as soon as possible is very important for a policyholder because of the cost of defending oneself in a lawsuit; often the key reason why an insurance policy is even purchased is to provide the policyholder with the right to call upon the insurance company’s financial resources to defend it should it be sued.
In a ruling that will be welcomed by policyholders, the
Pella Court held that Liberty Mutual’s multiple insurance policies were triggered, and so obligated to pay for the window manufacturer’s defense, if one of two events occurred during the years in which those insurance policies provided coverage: (1) a window was actually installed during a year when the insurance policy provided coverage or (2) the window was alleged to be installed in the year that the insurance policy provided coverage. The Court agreed with the policyholder that once the windows were installed, property damage was alleged and “may
potentially have occurred” from that point on, thus the policies on the risk from that point forward. The practical effect of this ruling meant that Liberty Mutual had to reimburse the window manufacturer for the defense fees and costs that it had paid.
While
Pella was decided under Iowa law, the principles upon which it relied are similar to those applied under California law. Importantly, both California and Iowa law hold that an insurance company must provide a defense in response to a claim that is, or could be, covered by the insurance policy. The mere potential that the claim might be covered is enough for the insurance company to be obligated to pay for policyholder’s legal fees and costs.
Establishing that an insurance company must pay legal fees and costs as soon as possible allows a policyholder to save its own money. Why should a policyholder pay legal bills when it purchased an insurance policy as protection to ensure that it did not have to pay those bills? The answer is that a policyholder should not and, under
Pella, the policyholder does not have to. Rather, the insurance company must start paying for that defense from a very early date. Pella confirms for policyholders the position that their insurance companies should pay legal bills earlier rather than later.
Alan Packer is a partner in the Walnut Creek office for Newmeyer & Dillion, LLP, representing homebuilders, property owners, and business clients on a broad range of legal matters, including risk management, insurance matters, wrap consultation and documentation, efforts to counter solicitation of homeowners, subcontract documentation, as well as complex litigation matters. Alan can be reached at alan.packer@ndlf.com.
Graham Mills is a partner in the Walnut Creek offce of Newmeyer & Dillion, LLP, representing clients in the area of complex insurance law with an emphasis on insurance recovery, construction litigation, real estate litigation, and business litigation. He regularly examines and analyzes a wide variety of insurance policies. Graham can be reached at graham.mills@ndlf.com.
ABOUT NEWMEYER & DILLION LLP
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review’s AV Preeminent® highest rating.
For additional information, call 949.854.7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Louisiana 13th in List of Defective Bridges
November 27, 2013 —
CDJ STAFFAbout 1,800 bridges in the state of Louisiana have been rendered structurally deficient. According to a report by WAFB, that means “at least one of the three key parts of a bridge has a major defect.” Although the bridges need repair, they are not yet classified as unsafe, which would lead to the Louisiana Department of Transportation and Development closing the bridges.
Over the last five years, the state has spent a billion dollars on repairing, maintaining, and replacing bridges, but the number keeps growing. The DOTD would not release a list of compromised bridges in the state, citing legal concerns.
Read the court decisionRead the full story...Reprinted courtesy of
Perrin Construction Defect Claims & Trial Conference
June 11, 2018 —
Beverley BevenFlorez-CDJ STAFFRichard Glucksman, Esquire, Partner of the Los Angeles firm Chapman Glucksman Dean Roeb & Barger, will be moderating the panel, “Green Building/LEED: An Overview and Claims Discussion” at the Perrin Construction Defect Claims & Trial Conference in Las Vegas, Nevada. The panel will be discussing the following topics:
- Risk and claims case studies including solar and SIPs (Structural Insulated Panels)
- Green Building/LEED and The Law: Review of National Claims/Lawsuits
- AIA Documents for Sustainable Projects
Thursday, June 21st, 2018
Four Seasons Hotel
3960 S Las Vegas Blvd
Las Vegas, NV 89119
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations to Partner Nicole Whyte on Being Chosen to Receive The 2024 ADL’s Marcus Kaufman Jurisprudence Award
May 28, 2024 —
Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is proud to announce Founder/CEO Nicole Whyte has been chosen by the Orange County/Long Beach region of the Anti-Defamation League (“ADL”) to receive the 2024 ADL’s Marcus Kaufman Jurisprudence Award.
The ADL annual Jurisprudence Dinner, at which Nicole will be honored along with the Hon. Kirk Nakamura (retired) and Michael Ermer, will be held on Thursday, September 19, 2024, at the Turnip Rose Promenade in Costa Mesa.
Congratulations to Nicole for her lifetime of service not only to Bremer Whyte Brown & O’Meara, LLP but also to the larger community. Immediate past recipients include Brian Farrell, the Hon. Glenda Sanders (retired), and Eric Trout.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Don’t Put Yourself In The Position Of Defending Against An Accord And Satisfaction Defense
October 10, 2022 —
David Adelstein - Florida Construction Legal UpdatesThe doctrine of accord and satisfaction lives and breathes in disputes including construction disputes. Unfortunately, a contractor, in the case discussed below, found out the hard way after it cashed checks that were accompanied with a letter that clearly indicated the checks were final payment. Once those payments were cashed, there was no “buyer’s remorse” that would allow it to still pursue disputed amounts. Remember this the next time you accept and cash a payment that says on the check it is full and final payment OR is accompanied by a letter that makes clear the payment is full and final payment. If you cash it, there is no second bite out of the apple, so to speak. If you are not interested in the payment being full and final payment, return the check. If you are not sure, either return the check or inquire and get that response in writing. Don’t put yourself in the position of defending against an
accord and satisfaction defense.
Even without the doctrine of accord and satisfaction, the contract between the contractor and owner discussed below made clear that contractor’s acceptance of final payment meant that contractor was unconditionally waiving other claims against the owner, further reinforcing that there would be no second bite out of the apple.
The morale:
(1) read the letter that accompanies a check and do NOT cash a check that indicates it is for final payment unless you are prepared to accept that amount; and
(2) read your contract to understand any contractual obligation that kicks-in with the acceptance of final payment.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com