Slow Down?
December 03, 2024 —
Daniel Lund III - LexologyAbsolutely not, said the Louisiana Fifth Circuit Court of Appeal to a masonry subcontractor being sued for allegedly improperly refusing to honor a subcontract bid.
A general contractor preparing its overall bid for a public project in Jefferson Parish relied in the process on the defendant masonry subcontractor’s bid. After a public bid process and receiving the award of the project, the general contractor was informed by the subcontractor that it believed that the unit price form that had been supplied to the sub “contained inaccuracies.” Notwithstanding offers by the GC to endeavor to address the purported “inaccuracies” during the project, most likely by a change order, the subcontractor refused to execute its subcontract. The general contractor then awarded the masonry work to another subcontractor for $368,222 more than the original sub’s bid.
The GC filed suit – for recovery of $368,222 – against the defendant subcontractor during the course of the public project. The defendant sub objected, arguing to the court that the lawsuit was “premature.” At the heart of the prematurity argument: the sub urging that the general contractor filed suit before its right to recover damages had accrued.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Insurer Unable to Declare its Coverage Excess In Construction Defect Case
January 06, 2012 —
CDJ STAFFThe Ninth Circuit Court of Appeals has upheld a summary judgment in the case of American Family Mutual Insurance Co. v. National Fire & Marine Insurance Co. Several other insurance companies were party to this case. In the earlier case, the US District Court of Appeals for Arizona had granted a summary judgment to Ohio Casualty Group and National Fire & Marine Insurance Company. At the heart of it, is a dispute over construction defect coverage.
The general contractor for Astragal Luxury Villas, GFTDC, contracted with American Family to provide it with a commercial liability policy. Coverage was issued to various subcontractors by Ohio Casualty and National Fire. These policies included blanket additional insured endorsements that provided coverage to GFTDC. The subcontractor policies had provisions making their coverage excess over other policies available to GFTDC.
The need for insurance was triggered when the Astragal Condominium Unit Owners Association filed a construction defect claim in the Arizona Superior Court. CFTDC filed a third-party claim against several subcontractors. The case was settled with American Family paying the settlement, after which it filed seeking reimbursement from the subcontractor’s insurers. The court instead granted summary judgment in favor of Ohio Casualty and National Fire.
American Family appealed to the Ninth Circuit for a review of the summary judgment, arguing that the “other insurance” clauses were “mutually repugnant and unenforceable.” The Ninth Circuit cited a case from the Arizona Court of Appeals that held that “where two policies cover the same occurrence and both contain ‘other insurance’ clauses, the excess insurance provisions are mutually repugnant and must be disregarded. Each insurer is then liable for a pro rate share of the settlement or judgment.”
The court noted that unlike other “other insurance” cases, the American Family policy “states that it provides primary CGL coverage for CFTDC and is rendered excess only if there is ‘any other primary insurance’ available to GFTDC as an additional insured.” They note that “the American Family policy purports to convert from primary to excess coverage only if CFTDC has access to other primary insurance as an additional insured.”
In comparison, the court noted that “the ‘other insurance’ language in Ohio Casualty’s additional insured endorsement cannot reasonably be read to contradict, or otherwise be inconsistent with, the ‘other primary insurance’ provision in the American Family policy.” They find other reasons why National Fire’s coverage did not supersede American Family’s. In this case, the policy is “written explicitly to apply in excess.”
Finally, the Astragal settlement did not exhaust American Family’s coverage, so they were obligated to pay out the full amount. The court upheld the summary dismissal of American Family’s claims.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Potential Extension of the Statutes of Limitation and Repose for Colorado Construction Defect Claims
April 27, 2020 —
David M. McLain – Colorado Construction LitigationOn January 27th, Senator Robert Rodriguez introduced SB 20-138 into the Colorado Legislature. The bill has been assigned to the Senate Judiciary Committee and has not yet been scheduled for its first hearing in that committee. In short, Senate Bill 20-138, if enacted, would:
- Extend Colorado’s statute of repose for construction defects from 6+2 years to 10+2 years;
- Require tolling of the statute of repose until the claimant discovers not only the physical manifestation of a construction defect, but also its cause; and
- Permit statutory and equitable tolling of the statute of repose.
Colorado’s statute of repose for construction defect claims are codified at C.R.S. § 13-80-104. In 1986, the Colorado Legislature set the statute of repose period at 6+2 years. For the last 34 years, Colorado’s statute of repose for owners’ claims against construction professionals has been substantially the same, to wit:
(1) (a) Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
(2) In case any such cause of action arises during the fifth or sixth year after substantial completion of the improvement to real property, said action shall be brought within two years after the date upon which said cause of action arises.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
The Sounds of Silence: Pennsylvania’s Sutton Rule
January 29, 2024 —
William L. Doerler - The Subrogation StrategistIn Westminster Am. Ins. Co. a/s/o Androulla M. Toffalli v. Bond, No. 538 EDA 2023, 2023 Pa. Super. LEXIS 626, 2023 PA Super 272, the Superior Court of Pennsylvania (Appellate Court) recently discussed the impact of silence on the Sutton Rule with respect to the landlord, Androulla M. Toffalli (Landlord), securing insurance. After holding that the tenant, Amy S. Bond (Bond) t/a Blondie’s Salon – who leased both commercial and residential space in the building pursuant to written leases – was not an implied “co-insured” on Landlord’s insurance policy, the Appellate Court reversed the decision of the trial court.
In this case, Bond rented the ground floor of a property located in Monroe County pursuant to a written commercial lease (Commercial Lease) and operated Blondie’s salon out of the leased location. In addition, Bond rented and lived in a second-floor apartment pursuant to a residential lease (Residential Lease). Both leases required the tenants (Tenants) to obtain insurance for personal items. The leases, however, did not require Landlord to obtain fire insurance for the property.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Subcontract Should Flow Down Delay Caused by Subcontractors
December 21, 2020 —
David Adelstein - Florida Construction Legal UpdatesA general contractor’s subcontract with its subcontractor should include a provision that entitles it to flow down liquidated damages assessed by the owner stemming from delays caused by the subcontractor. Such a provision does not mean the general contractor does not have to prove delays caused by the subcontractor or can arbitrarily allocate the amount or days it claims the subcontractor is liable. The general contractor still will need to reasonably establish the delays the subcontractor caused the critical path of the schedule, i.e., delayed the job. In addition to the right to flow down liquidated damages, the subcontract should also entitle the general contractor to recover its actual extended general conditions caused by the subcontractor’s delays (regardless of whether the owner assesses liquidated damages). The objective is that if the subcontractor delays the job, the subcontractor is liable for liquidated damages the general contractor is liable to the owner for in addition to the general contractor’s own delay damages. This is an important subcontractual provision so that the risk of delay caused by subcontractors is clearly flowed down to them in the subcontract.
In a 1987 case, Hall Construction Co., Inc. v. Beynon, 507 So.2d 1225 (Fla. 5th DCA 1987), the subcontract at-issue contained language that stated, “The parties hereto agree that a supplier who delays performance beyond the time agreed upon in this Purchase Order shall have caused [general contractor] liquidated damages in the amount required of [general contractor] by their contract per day for each day such delay continues which sum the supplier hereby agrees to pay.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Homeowner Who Wins Case Against Swimming Pool Contractor Gets a Splash of Cold Water When it Comes to Attorneys’ Fees
February 05, 2024 —
Garret Murai - California Construction Law BlogLooking outside as of late it seems like the glorious, sun-drenched days of Summer are just a nostalgic memory of days long gone. So, to bring back some of those warm-weather memories, I have a swimming pool case for you. Although, like most of the things we write about here on the California Construction Law Blog it’s not all fun-in-the-sun.
The Lee Case
In Lee v. Cardiff, 94 Cal.App.5th 398 (2023), Homeowner Dianne Lee entered into a construction contact with contractor David Brian Cardiff doing business as Advantage Pools Bay Area for a swimming pool and landscaping project totaling $231,500. It must have been quite a pool.
As these things sometimes go, a dispute arose and Cardiff left the job before its was finished. Lee later sued alleging breach of contract, negligent construction and violation of the Contractor State License Law.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
County Sovereign Immunity Invokes Change-Order Ordinance
December 20, 2017 —
Lizbeth Dison - AHC Contruction Law BlogThe recent case of Fulton County v. Soco Contracting Company, Inc. addresses two very interesting questions for local government attorneys. First, can a county ordinance bolster a defense of sovereign immunity against a contractor’s claims? Second, can a county waive sovereign immunity by failing to respond to Requests for Admission?
Facts:
County hired Contractor to construct a facility near the airport. The contract provided that change orders must satisfy a county ordinance, which required approval by the Board of Commissioners. But in emergency situations, the County Manager could approve change orders, as long as the contractor executes a proposed modification and the purchasing agent approves it.
The project suffered substantial delays, which Contractor attributed to weather, design delays, delays by the County in providing decisions on changes, and delays in obtaining permits during the federal government’s shutdown. As a result of these issues, Contractor comes County changed the scope of the contract. Contractor asserted claims against County for the delays and the changes to the work. The appellate opinion addresses the change order claims.
Read the court decisionRead the full story...Reprinted courtesy of
Lizbeth Dison, Autry Hall & Cook, LLP
Your Construction Contract
April 08, 2024 —
David Adelstein - Florida Construction Legal UpdatesYour construction contract is an important topic. What’s even more important is YOUR process for reviewing and negotiating construction contracts.
Are you simply acting as a riverboat gambler willing to assume undue risk because you don’t value the investment in understanding what you are signing? If so, it becomes hard to complain about what you agreed to and signed when you chose NOT to invest in the process. Investing in the process means you are working with a construction attorney, you have an insurance broker that understands your industry, you have resources in place to ensure risk is negotiated and allocated, and you understand what risk you are assuming to make sure you are properly protecting and perfecting your rights, and transferring risk downstream.
When it comes to construction contracts, there are really three approaches:
1. Riverboat Gambler. This is the “I’ll sign whatever you give me because I don’t want to lose the contract / revenue.” Under this approach, you are not worried about undue risk because you don’t value the investment in the next two approaches. Your thought process is that you’ll care about the risk when an issue pops up, i.e., the riverboat gambler. This is not an approach I’d recommend because it is contrary to the adage, “an ounce of prevention is worth a pound of cure.” This is simply a reactive approach to issues and risks. The other two approaches are more proactive and better suited to understand and manage risk.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com