Massachusetts Judge Holds That Insurer Breached Its Duty To Defend Lawsuit After Chemical Spill
October 16, 2018 —
Lawrence J. Bracken, II & Alexander D. Russo - Hunton Insurance Recovery BlogA District Court Judge for the District of Massachusetts recently ruled that Ace Property and Casualty Insurance Co. breached its duty to defend its insured in a lawsuit brought by Plaistow Project, LLC, after a family owned laundromat leaked chemicals onto Plaistow Project’s property. Plaistow Project, LLC v. ACE Prop. & Cas. Ins. Co., No. 16-CV-11385-IT, 2018 WL 4357480, (D. Mass. Sept. 13, 2018). Plaistow Project sued State Line Laundry Services in state court, and ACE denied coverage under the pollution exclusion in State Line Laundry’s insurance policy. Plaistow Project then settled with State Line Laundry. Under the settlement terms, Plaistow Project was assigned State Line Laundry’s rights against ACE.
In the subsequent coverage litigation, Plaistow Project alleged that ACE had breached its duty to defend State Line Laundry under its insurance policy. ACE argued that (1) the burden was on the policyholder to demonstrate that the policy’s “sudden and accidental” exception applied to the policy’s pollution exclusion; and (2) the policyholder could not show the “sudden and accidental” exception applied based on the complaint.
Reprinted courtesy of
Lawrence J. Bracken, II, Hunton Andrews Kurth and
Alexander D. Russo, Hunton Andrews Kurth
Mr. Bracken, may be contacted at lbracken@HuntonAK.com
Mr. Russo may be contacted at arusso@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
California Joins the Majority of States in Modifying Its Survival Action Statute To Now Permit Recovery for Pain, Suffering And Disfigurement
January 03, 2022 —
Krsto Mijanovic & Elizabeth D. Rhodes - Haight Brown & BonesteelOn January 1, 2022, California Code of Civil Procedure (“CCP”)Section 377.30 et seq., as amended by Senate Bill 447, otherwise known as the “survival action” statute1, goes into effect. On that date, all plaintiffs filing new civil cases filed on or after January 1, 2022, and before January 1, 2026, and plaintiffs in any action or proceeding granted trial preference pursuant to CCP Section 36 before January 1, 2022, will be expressly allowed to recover damages for a decedent’s pain, suffering, or disfigurement in a survival action.2 This is a significant change in California law. In that regard, California is now the 46th state to permit this form of recovery.
As reported in the Legislative Counsel’s Digest3, Consumer Attorneys of California and Consumer Federation of California, which co-sponsored Senate Bill 447, opined to the Legislature that the prior law provided a “death discount” to defendants which incentivized bad faith delays in resolution, and caused unnecessary congestion of the already overburdened court system. These argued issues will be vetted by the Legislature using the four-year reporting requirement that is also part of the amendment to the statute, requiring plaintiffs who recover this newly permitted category of damages to report the valuation and details of the case to the Judicial Council within 60 days of the judgment or other operative court document being entered in the court’s docket.4 The amendment will be evaluated by the Legislature for amendment or extension on or before January 1, 2026.
Reprinted courtesy of
Krsto Mijanovic, Haight Brown & Bonesteel and
Elizabeth D. Rhodes, Haight Brown & Bonesteel
Mr. Mijanovic may be contacted at kmijanovic@hbblaw.com
Ms. Rhodes may be contacted at erhodes@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The Role of Code Officials in the Design-Build Process
November 16, 2023 —
Grace Calengor - Construction ExecutiveBuilding codes are an integral part of the design-build process, but what role do building code professionals play throughout that process? Kevin McOsker, vice president of technology services for the government relations department at the International Code Council, breaks it down, from basic design to groundbreaking ideas to incorporating new technology and retrofitting older builds.
McOsker, whose experience includes serving as building official for the city of Las Vegas, is no stranger to striking architecture and the safety protocols that go along with it. He believes that safety protocol starts before the contractors begin building and that contractors should be involved throughout the entire journey.
Reprinted courtesy of
Grace Calengor, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Reconstructing the Francis Scott Key Bridge Utilizing the Progressive Design-Build Method
June 04, 2024 —
Lisa D. Love - The Dispute ResolverHaving awakened on the morning of March 26 to the devastating news of the collapse of Baltimore’s Francis Scott Key Bridge after being struck by the Dali, a 984 length /52 beam foot cargo container ship, I thought of the many times I crossed the bridge as a child growing up in Washington, D.C. I also recalled Montgomery Schyler’s comments on the opening of the Brooklyn Bridge, when he stated that “the work which is likely to be our most durable monument, and to convey some knowledge of us to the most remote posterity, is a work of bare utility; not a shrine, not a fortress, not a palace, but a bridge.”
I thought of the beauty of New York’s Mario Cuomo Bridge, a 3.1-mile cable-stayed twin-span bridge with eight traffic lanes, bicycle and pedestrian paths, six lookout points and room for future rapid transit. It was completed in 2018 and constructed under a design-build procurement model[i] at a cost of $3.98 billion. Accelerated bridge construction (ABC) techniques were utilized in its construction. ABC techniques employ innovative planning, design, materials, and construction methods in a safe and cost-effective manner to reduce the on-site construction time that occurs when building new bridges or replacing and rehabilitating existing ones. ABC techniques improve site constructability, total project delivery time, work-zone safety for the traveling public and traffic impacts, on-site construction time, and weather-related time delays.[ii]
I also thought of the gracefulness of Boston’s Leonard P. Zakim Bunker Hill Memorial Bridge, a 0.27-mile hybrid cable-stayed steel and concrete bridge with pedestrian and bicycle access that holds 10 lanes of traffic. The Zakim Bridge was completed in 2004 at a cost of approximately $100 million as part of the $24.3 billion Big Dig.[iii] Despite its elegant, streamlined appearance, the bridge was designed to be exceptionally strong, withstand winds over 400 miles per hour and endure a magnitude 7.9 earthquake.[iv]
Read the court decisionRead the full story...Reprinted courtesy of
Lisa D. Love, JAMS
Traub Lieberman Team Obtains Summary Judgment in Favor of Client Under Florida’s Newly Implemented Summary Judgment Standard
August 23, 2021 —
Heather Fleming & Gregory H. Lercher - Traub LiebermanOn July 27, 2021, the Circuit Court of the Ninth Judicial Circuit in and for Osceola County, Florida granted summary judgment in favor of a client insurer defended by Traub Lieberman Partner Heather M. Fleming and Associate Gregory H. Lercher in connection with a first party property lawsuit arising from Hurricane Irma that involved multiple, comingled claims, in part resolved via prior appraisal.
As of May 1, 2021, Florida state courts have applied a new summary judgment standard after Florida’s longstanding rule was amended by the Supreme Court of Florida. The amendment aligns Florida’s standard with that of the federal courts and the supermajority of states that have already adopted the federal summary judgment standard codified in Rule 56 of Federal Rules of Civil Procedure. The Supreme Court of Florida’s stated goal in adopting the new standard across the Sunshine State was to improve the fairness and efficiency of Florida's civil justice system, to relieve parties from the expense and burdens of meritless litigation, and to save the work of juries for cases where there are real factual disputes that need resolution.
Reprinted courtesy of
Heather Fleming, Traub Lieberman and
Gregory H. Lercher, Traub Lieberman
Ms. Fleming may be contacted at hfleming@tlsslaw.com
Mr. Lercher may be contacted at glercher@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Four Key Steps for a Successful Construction Audit Process
May 03, 2021 —
Ronald L. Williams, Fox Rothschild LLP - ConsensusDocsThe implications of the audit provisions contained in construction agreements between owners and contractors owners extend far beyond post-completion bean counting, and can affect multiple aspects of a project, from project administration to relationships with key subcontractors. It is critically important that contractors give audits the attention they deserve by taking the following four steps. First, invest the time to negotiate the audit provisions that ultimately appear in contracts with the owner. Second, ensure that the project team and the owner’s project auditors engage in timely communication during construction. Third, make certain that post-completion audit administration is prompt and complete. And finally, carefully draft adequate “flow-down” provisions with subcontractors and vendors so that they understand and comply with their contractual obligations, as well as the expectations of the contractor and owner. All four aspects are critical, and if not addressed effectively can undermine the profitability of the contract, and contractors’ business relationships with both upstream and downstream parties.
Negotiations
At the outset of contract negotiations, a contractor must completely understand the owner’s audit process expectations. An owner’s understanding of the audit process and its potential pitfalls depends on their own experience, as well as the knowledge of their personnel, including internal audit members and external auditors. Negotiations, which like the audit itself need not be adversarial, can be educational for both the owner and any representatives involved.
Read the court decisionRead the full story...Reprinted courtesy of
Ronald L. Williams, Fox Rothschild LLPMr. Williams may be contacted at
rwilliams@foxrothschild.com
Wine without Cheese? (Why a construction contract needs an order of precedence clause)(Law Note)
August 11, 2011 —
Melissa Brumback, Construction Law in North CarolinaFor today’s law note, I’m addressing a comment that came to me last week from Dave O’Hern of Miller O’Hern Construction. Dave writes:
I am a general contractor doing a fuel tank replacement project for our county. In the specifications there is a spec for a UL 142 tank, on the plans the spec references UL 2085 ? a much more expensive tank. My subcontractor bid the UL 142 tank. The specifications state that the specs and plans are on the same level of precedence.
The county wants me to furnish the more expensive tank without compensation citing the clause that states the plans and specs are complementary and what is called for by one is binding as if called by all and the most stringent requirement will apply.
Read the full story…
Reprinted courtesy of Melissa Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.
Read the court decisionRead the full story...Reprinted courtesy of
Homebuilders Are Fighting Green Building. Homeowners Will Pay.
April 22, 2024 —
Mark Gongloff - BloombergBack in the 1990s, political guru James Carville said he wanted to be reincarnated as the bond market because it could “intimidate everybody.” Here in the 2020s, you might prefer to come back as a homebuilder. The industry has the political muscle to protect its profits at the expense of both homeowners and the climate.
In some fast-growing parts of the US, lobbyists are frustrating efforts to make new homes more efficient and compatible with clean technology, making it that much harder for the rest of us to avoid the worst effects of a heating planet. They’re doing it in the name of housing affordability, naturally — but it doesn’t hurt that they’re keeping a lid on homebuilders’ costs at the same time. Their sabotage will cost homeowners much more in the long run.
In 2021, the International Code Council, a nonprofit group that every few years suggests building codes for the whole country, released an aggressive set of proposals that could reduce residential carbon emissions and annual energy costs by 9%, according to one estimate. This was in response to a groundswell of requests from local officials to update standards that had long been stagnant.
Read the court decisionRead the full story...Reprinted courtesy of
Mark Gongloff, Bloomberg