What Every Project Participant Needs to Know About Delay Claims
August 05, 2024 —
Andrew G. Vicknair - The Dispute ResolverA “delay” on a construction project is defined as the stretching out of the time for completion of certain key milestone scopes of work which can impact the completion date of an entire project, due to some circumstances or events that were not reasonably anticipated when the project began. 2 Construction Law ¶ 6.01 (Matthew Bender, 2024). While delays can be caused by any number of events, the most common are defective plans and specifications; design changes; severe weather and other, similar unforeseeable events; unforeseen or differing site conditions; unavailability of materials or labor; labor inefficiencies or stoppages; contractor negligence; and owner influences, including construction changes or outright interference by the owner or its agents. If the project schedule is not recovered following a delay, then the project schedule will likely be extended, resulting in an increase in the contractor’s costs of performance. A contractor that has experienced a delay on a project can take certain actions to pursue recovery of any damages the contractor may have incurred. However, to do so it is important to understand the different types of delays and the methods for establishing the delays.
I. Types of Delays
Delays may be categorized as (1) critical versus non-critical delays, (2) excusable versus non-excusable delays, and (3) compensable versus non-compensable delays. A critical delay is a delay that affects the project completion date and delays the entire project. In essence, a critical delay is one that will extend the critical path of a project. A non-critical delay is a delay that has no effect on the project’s critical path. Courts have recognized that delays to work not on the critical path will generally not delay the completion of a project. G.M. Shupe, Inc. v U.S., 5 Cl. Ct. 662, 728 (1984). Such a non-critical delay may affect the completion of certain activities, but does not affect the completion date of the entire project. In order for a delay to provide the basis for a claim for additional time or money, the delay must impact critical path activities on the project schedule.
Read the court decisionRead the full story...Reprinted courtesy of
Andrew G. Vicknair, D'Arcy Vicknair, LLCMr. Vicknair may be contacted at
agv@darcyvicknair.com
SB 939 Proposes Moratorium On Unlawful Detainer Actions For Commercial Tenants And Allows Tenants Who Can't Renegotiate Their Lease In Good Faith To Terminate Their Lease Without Liability
June 01, 2020 —
Rhonda Kreger – Newmeyer DillionSB 939 is currently working its way through the Senate Judiciary Committee. The legislation would impose new obligations on landlords, and provide protections for commercial tenants who meet specified criteria. SB 939 would impose a moratorium on eviction of those qualified commercial tenants while emergency COVID-19 orders are in effect. Any eviction actions commenced after the date of the emergency COVID-19 order, but before the adoption of SB 939, would be void and unenforceable. The Senate Judiciary Committee has scheduled a hearing for SB 939 on May 22, 2020, at 9:00 a.m.
Who qualifies as a commercial tenant under SB 939?
To qualify under this legislation, a commercial tenant must be a business that operates primarily in California. The commercial tenant must be a small business, nonprofit, an eating or drinking establishment, place of entertainment, or performance venue. Publicly traded companies or any company owned by, or affiliated with a publicly traded company, do not qualify. The commercial tenant must have experienced a decline of at least 40 percent monthly revenue, either as compared to two months before the emergency COVID-19 order, or other local government shelter-in-place orders took effect, or as compared to the same month in 2019. If the commercial tenant is an eating or drinking establishment, place of entertainment, or performance venue, the commercial tenant must also show a decline of 25 percent or more in capacity due to social or physical distancing orders or safety concerns, and show that it is subject to regulations to prevent the spread of COVID-19 that will financially impair the business when compared to the period before the emergency COVID-19 order or other local shelter-in-place orders took effect.
What eviction actions are prohibited while emergency COVID-19 orders are in effect?
If adopted, SB 939 would add Section 1951.9 to the Civil Code. This section would make it unlawful to terminate a tenancy, serve notice to terminate a tenancy, use lockout or utility shutoff actions to terminate a tenancy or otherwise evict a tenant of commercial real property, including a business or nonprofit, during the pendency of the COVID-19 emergency order proclaimed by Governor Newsome on March 4, 2020. Exceptions apply if a tenant poses a threat to the property, other tenants or a person, business or other entity. Any violations of this eviction prohibition would be against public policy and unenforceable.
Any eviction started after proclamation of the state of emergency but before the effective date is deemed void, against public policy and is unenforceable.
Does SB 939 impose new penalties or remedies?
Any landlord who harasses, mistreats or retaliates against a commercial tenant to force the tenant to abrogate the lease would be subject to a fine of $2,000 for each violation. Further, any such violation would be an unlawful business practice and an act of unfair competition under Section 17200 of the Business and Professions Code and would be subject to all available remedies or penalties for those actions under state law.
When is a commercial tenant required to pay unpaid rent due to COVID-19?
If a commercial tenant fails to pay rent during the emergency COVID-19 order, the sum total of the past due rent must be paid within 12 months following the date of the end of the emergency proclamation, unless the commercial tenant has successfully negotiated an agreement with its landlord to pay the outstanding rent at a later date. Nonpayment of rent during the state of emergency cannot be used as grounds for eviction. Notwithstanding lease terms to the contrary, landlords may not impose late charges for rent that became due during the state of emergency.
Are landlords required to provide notice of protections adopted under SB 939?
Landlords would be required to provide notice to commercial tenants of the protections offered under SB 939 within 30 days of the effective date. SB 939 does not preempt local legislation or ordinances restricting the same or similar conduct which impose a more severe penalty for the same conduct. Local legislation or ordinances may impose additional notice requirements.
Does SB 939 impose new protections for commercial tenants when negotiating lease modifications?
If enacted, SB 939 would permit commercial tenants to open negotiations for new lease terms, and provide commercial tenants the ability to terminate the lease if those negotiations fail. A commercial tenant who wishes to modify its commercial lease, may engage in good faith negotiations with its landlord to modify any rent or economic requirement regardless of the term remaining on the lease. The commercial tenant must serve a notice on the landlord certifying that it meets the required criteria, along with the desired modifications.
If the commercial tenant and landlord do not reach a mutually satisfactory agreement within 30 days, then within 10 days, the commercial tenant may terminate the lease without any liability for future rent, fees, or costs that otherwise may have been due under the lease by providing a written termination notice to the landlord. The commercial tenant would be required to pay previously due rent, in an amount no greater than the sum of the following: (1) the actual rent due during the emergency COVID-19 order, or a maximum of three months of the past due rent during that period, and (2) all rent incurred and unpaid during a time unrelated to the emergency COVID-19 order through the date of the termination notice. The payment is due within 12 months from date of the termination notice. The commercial tenant would be required to vacate the premises within 14 days of the landlord's receipt of the termination notice. Upon service of the notice, any lease, and any third party guaranties of the lease would terminate. If the landlord and commercial tenant reach an agreement to modify the lease, the commercial tenant would not have the option to later terminate the lease under this provision.
When is the next Senate Judiciary Committee Meeting for SB 939?
The Senate Judiciary Committee set a hearing for SB 939 on May 22, 2020 at 9:00 a.m. The Senate will livestream the hearing on its website at www.sen.ca.gov. Public comments or testimony may be submitted in writing to the Judiciary Committee by emailing Erica.porter@sen.ca.gov. Alternatively, the public may participate via telephone during the public comment period. Any changes to the Judicial Committee schedule may be found at: https://www.senate.ca.gov/calendar.
Newmeyer Dillion continues to follow COVID-19 and its impact on your business and our communities. Feel free to reach out to us at NDcovid19response@ndlf.com or visit us at www.newmeyerdillion.com/covid-19-multidisciplinary-task-force/.
Rhonda Kreger is Senior Counsel on Newmeyer Dillion's transactional team at our Newport Beach office. Her practice focuses on all aspects of commercial real estate law, with a particular emphasis on the representation of residential developers, merchant builders and institutional investors. You can reach Rhonda at rhonda.kreger@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Companies Can Be Liable for “Secondary Exposure” of Asbestos to Household Members
October 26, 2017 —
Garret Murai - California Construction Law BlogThe history of asbestos regulation in the United States is complicated. Prior to the 1970s, asbestos-containing materials used in construction was widespread.
In 1971, when the U.S. Environmental Protection Agency issued an emissions standard for asbestos as part of the Clean Air Act. In 1972, the EPA extended this regulation to an occupational standard and, over the next decade, the EPA together with the U.S. Occupational Safety and Health Administration and the U.S. Consumer Product Safety Commission issued a wide array of regulations aimed at asbestos.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Steps to Defending against Construction Defect Lawsuits
July 21, 2011 —
CDJ STAFFWriting in Claims Journal, Bryan Rendzio notes that the decline in construction has not been matched by a decline in construction defect lawsuits over condominiums. He reviews the ways in which lawyers representing developers can help protect their clients. He identifies four important considerations in defending developers from claims of construction defects.
He advocates a careful review of the contract. “Under a breach of contract claim, the insured’s duties to the party who brought the claim against the insured flow from the contract. Commonly, construction contracts limit the scope of recoverable damages, such as by waiving consequential damages.’
The next step, according to Rendzio is to check of a settlement agreement is already in place, noting that these are “a familiar occurrence in the construction industry, regardless of any lawsuits having been filed.”
He considers the statute of repose “the single-most decisive weapon an insured possesses in its arsenal during a condo defect lawsuit.” He notes that no lawsuits can be brought for construction defects after the end specified by the statute of repose, and if a lawsuit is brought beforehand, no additional parties can be named once the statute has taken effect.
Finally, he warns adjusters to be suspicious when a condo association requests contractual indemnification. He notes that the pitfall in this is that developers and the subsequent condominium association often have similar names, given the theoretical example of a condo project built by “Fake Lakes LLC” and later run by the “Fake Lakes Condominium Association.” Writing in regards to Florida law, he notes that condominium associations do not have successor interest in contracts developers made with contractors.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Granted Summary Judgment on Faulty Workmanship Claim
October 20, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe federal district court found no coverage for the insured developer after water intruded into the homeowners' basements. W. Bend Mut. Ins. Co. v. Cleland Homes, 2016 U.S. Dist. LEXIS 108030 (N.D. Ind. Aug. 16, 2016).
The underlying complaint alleged that the subdivision was designed to create a run off of ground water onto the lots where Cleland built plaintiffs' homes. The design of the subdivision and construction of the homes was defective in that the plaintiffs' homes were situated so that the water table underneath their homes was so high that their basements flooded and damage occurred to the structure of their homes. Cleland was allegedly negligent in designing and/or constructing the homes or negligent in the water drainage plan for the subdivision.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Separation of Insureds Provision in CGL Policies
August 31, 2020 —
David Adelstein - Florida Construction Legal UpdatesCGL policies contain a “Separation of Insureds” provision. This provision oftentimes states:
Except with respect to the Limits of Insurance, and any rights or duties specifically assigned this Coverage Part to the first Named Insured, this insurance applies:
- As if each named insured were the only Named Insured; and
- Separately to each insured against whom claim is made or “suit” is brought.
This provision is designed to “create separate insurable interests in each individual insured under a policy, such that the conduct of one insured will not necessarily exclude coverage for all other insured.” Evanson Ins. Co. v. Design Build Interamerican, Inc., 569 Fed.Appx. 739 (11th Cir. 2014). This provision also allows one insured under the policy (e.g., additional insured) to sue another (e.g., named insured) without violating potential coverage because there are separate insurable interests. This is a valuable provision in CGL policies.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Arizona – New Discovery Rules
May 16, 2018 —
John Belanger - Bremer Whyte Brown & O'Meara LLPEffective July 1, 2018
New Rules of Civil Procedure are taking effect in Arizona on July 1, 2018. The new Rules will change how discovery works in civil litigation in the state. Here is a sneak peek at the changes that will impact your file handling the most:
Tiered Discovery
- How much discovery is allowed in a case will now depend on the amount and type of relief sought
- Cases will be assigned to one of three tiers
- Parties can agree on a tier assignment, the court can assign a tier, or a tier can be assigned based on the amount of damages, or a combination of monetary and non-monetary damages
Read the court decisionRead the full story...Reprinted courtesy of
John Belanger, Bremer Whyte Brown & O'Meara LLPMr. Belanger may be contacted at
jbelanger@bremerwhyte.com
Connecticut’s New False Claims Act Increases Risk to Public Construction Participants
April 02, 2024 —
Fred Hedberg & William Stoll - Construction Law ZoneAfter several decades, Governor Ned Lamont signed a bill into law, effective July 1, 2023, An Act Concerning Liability for False and Fraudulent Claims, Public Act No. 23-129, eliminating language that previously limited enforcement of Connecticut’s False Claims Act to claims relating to a state-administered health or human services program. The revisions dramatically expanded potential liability under the False Claims Act, allowing both private citizens and the Attorney General to bring actions under the Act in any context, including the construction industry. Consequently, contractors, subcontractors, suppliers and design professionals on public construction projects in Connecticut must be familiar with this newly enacted law and take steps to reduce the risks of doing business on such projects.
Reprinted courtesy of
Fred Hedberg, Robinson & Cole LLP and
William Stoll, Robinson & Cole LLP
Mr. Hedberg may be contacted at fhedberg@rc.com
Mr. Stoll may be contacted at wstoll@rc.com
Read the court decisionRead the full story...Reprinted courtesy of