Touchdown! – The Construction Industry’s Winning Audible to the COVID Blitz
February 08, 2021 —
Bill Shaughnessy, Jones Walker, LLP - ConsensusDocsCOVID-19 has changed the way we live, work, play football, and build. As with all of society (and our football leagues and teams), the construction industry was impacted over the last year through the implementation of new safety protocols in response to COVID-19. While some construction projects were delayed or put on hold, much of the construction industry was fortunate to continue to build throughout the pandemic. Building under COVID-19 safety protocols led contractors to “call an audible” in order to make up for lost time and to save costs. In doing so, many contractors started incorporating or expanding the use of under-utilized tools, resources, capabilities, and technology such as pre-fabrication, and modular construction, while at the same time reexamining planning methods, monitoring critical schedule activities, and ways to better execute construction.
In many ways, the effects of COVID-19 safety protocols and measures implemented by contractors in the past year have led to more efficient and cheaper construction projects now and for the future. So, it is not surprising as we turn our calendars to 2021 that contractors can expect these tools, resources, and technologies to be utilized more in the years ahead, even once the pandemic subsides. This article highlights some of the “positive” effects of COVID-19 on projects and highlights several ways contractors attempted to increase efficiency and reduce costs in response to the pandemic.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Shaughnessy, Jones Walker, LLPMr. Shaughnessy may be contacted at
bshaughnessy@joneswalker.com
Florida County Suspends Impact Fees to Spur Development
November 18, 2011 —
CDJ STAFFHernando County, just north of Tampa on Florida’s west coast, has suspended impact fees for a year, hoping to spur development. Hernando Today reports that the move drew applause from the audience at the county commissioners meeting. Many of those in attendance were builders or members of the Greater Hernando Chamber of Commerce.
Not all were convinced. Frankie Burnett, the mayor of Brooksville, told the commissioners that his city council were not convinced that this would spur development. “Development should pay its fair share, even in slow economic times.” Burnett’s letter to the board warned that “if lowering impact fees succeeded in stimulating more residential overbuilding, it would only further depress the current real estate market.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Litigation Privilege Saves the Day for Mechanic’s Liens
November 23, 2020 —
Stephen M. Tye & Lawrence S. Zucker II - Haight Brown & BonesteelIn RGC Gaslamp v. Ehmcke Sheet Metal Co., the Fourth Appellate District held that a trial court properly granted an anti-SLAPP motion because the recording of a mechanic’s lien is protected by the litigation privilege.
In RGC Gaslamp, subcontractor Ehmcke Sheet Metal Company (“Ehmcke”) recorded a mechanic’s lien to recoup payment due for sheet metal fabrication and installation done at a luxury hotel project in downtown San Diego. Project owner RGC Gaslamp, LLC (“RGC”) recorded a release bond for the lien. Thereafter, Ehmcke recorded three successive mechanic’s liens identical to the first, prompting RGC to sue it for quiet title, slander of title, and declaratory and injunctive relief. After retaining California counsel, Ehmcke then released its liens and advised it did not intend to record any more. Ehmcke then filed a special motion to strike under the anti-SLAPP statute (Code Civ. Proc. § 425.16.) which was granted.
Reprinted courtesy of
Stephen M. Tye, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Mr. Tye may be contacted at stye@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Muir named Brown and Caldwell Eastern leader
January 09, 2023 —
Brown and CaldwellHARTFORD, Conn., Jan. 04, 2023 — Leading environmental engineering and construction services firm Brown and Caldwell today announces Senior Vice President Eric Muir has been promoted to leader of its growing Eastern business.
The largest of the company's regions with over 40 offices east of the Mississippi River, the Eastern business consists of clients in the water, wastewater, stormwater, environmental services, and water resources sectors.
Muir has a 20-year background in delivering highly technical civil and environmental engineering projects. He has held leadership and technical roles on some of the most complex projects encompassing water and wastewater treatment, distribution and collection, pumping, and conveyance systems. His experience includes master planning, detailed design, permitting, and construction services.
Since joining Brown and Caldwell in 2018, Muir's business development expertise and client-centric focus have played a key role in setting the company's regional strategic direction to achieve strong financial results.
"Eric is a highly strategic and inclusive leader, passionate about mentoring employees to reach their full potential," said Brown and Caldwell Chief Operating Officer Euan Finlay. "His deep knowledge of clients' environmental obstacles will enhance the positive impacts our teams have on the communities we serve."
Based in Connecticut, Muir will manage overall operations and lead the implementation of the firm's strategy in the East. He will continue the region's growth and lead efforts to make Brown and Caldwell the company of choice for clients, employees, and partners. He will work alongside regional leadership to align the firm's talent pool with clients to provide innovative, cost-effective solutions to challenges related to water quality, biosolids management, and aging infrastructure.
About Brown and Caldwell
Headquartered in Walnut Creek, California, Brown and Caldwell is a full-service environmental engineering and construction services firm with 52 offices and 1,800 professionals across North America and the Pacific. For 75 years, our creative solutions have helped municipalities, private industry, and government agencies successfully overcome their most challenging water and environmental obstacles. As an employee-owned company, Brown and Caldwell is passionate about exceeding our clients' expectations and making a difference for our employees, our communities, and our environment. For more information, visit www.brownandcaldwell.com
Read the court decisionRead the full story...Reprinted courtesy of
“Wait! Do You Have All Your Ducks in a Row?” Filing of a Certificate of Merit in Conjunction With a Complaint
January 13, 2020 —
Rahul Gogineni - The Subrogation StrategistIn Barrett v. Berry Contr. L.P., No. 13-18-00498-CV, 2019 Tex. LEXIS 8811, the Thirteenth District Court of Appeals of Texas considered, among other things, the procedural timing requirements of filing a certificate of merit in conjunction with a complaint. The court concluded that the proper reading of the statute requires a plaintiff to file a certificate of merit with the first complaint naming the defendant as a party.
In Barrett, after sustaining injuries while working at a refinery, David Barrett (Barrett) filed suit against Berry Contracting, LP and Elite Piping & Civil, Ltd. on July 6, 2016. In Barrett’s first amended complaint, which he filed on August 23, 2016, Barrett added Govind Development, LLC (Govind) as another defendant. Barrett subsequently filed a second amended complaint (omitting Govind) and, on December 27, 2017, shortly before the statute of limitations ran, a third amended complaint (reasserting claims against Govind). On January 28, 2018, after the statute of limitations period ran, Barrett filed a certificate of merit. Govind filed a motion to dismiss the claim, asserting that Barrett violated the statute that required a certificate of merit to be filed with the complaint, Tex. Civ. Prac & Rem. Code §150.002.
Tex. Civ. Prac. & Rem. Code §150.002(a) states,
In any action or arbitration proceeding for damages arising out of the provision of professional services by a licensed or registered professional, a claimant shall be required to file with the complaint an affidavit of a third-party licensed architect, licensed professional engineer, registered landscape architect or registered professional land surveyor…
Read the court decisionRead the full story...Reprinted courtesy of
Rahul Gogineni, White and Williams LLPMr. Gogineni may be contacted at
goginenir@whiteandwilliams.com
You Can Take This Job and Shove It!
June 10, 2015 —
Garret Murai – California Construction Law BlogThat’s it.
You’ve had it.
They can take their job and shove it!
But can you really tell an owner on a construction project to proverbially shove it where the sun don’t shine?
Well, far be it for me to tread on your First Amendment Rights or stick my nose into the subsequently brought public disturbance charges against you. But can you legally tell an owner to shove it, and that you’re no longer going to perform work on their [insert expletive] project? Well, indeed you can, in limited circumstances, and it’s called a “Stop Work Notice.”
Note: A stop work notice is different from a stop payment notice.
What is a stop work notice?
A stop work notice is a notice given by a direct contractor to a project owner that the contractor will stop work if an amount owed to the contract is not paid within 10 days after notice is given.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Insurer Must Defend Construction Defect Claims
October 07, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe federal district court found that under New York law, the insurer had a duty to defend construction defect claims where damage to property other than the insured's work product was possible. Am.Home Assur. Co. v. Allan Window Techs., 2016 U.S. Dist. LEXIS 101118 (S.D. N. Y. Aug 2, 2016).
Kent Avenue Property ("Kent") sued Allan Window Technologies, Ltd. ("Allan"), alleging that Allan entered a written contract for the design, manufacture, assembly and installation of the window wall systems for a residential condominium building. Pursuant to the contract, Allan agreed to correct all work rejected as defective and to bear all costs for correcting the work. According to the complaint, the window wall systems and vent windows installed by Allan were not water-tight or air-tight, and therefore did not meet the air and water penetration requirements of the contract.The contract had an indemnification provision under which Allan agreed to indemnify, defend and hold harmless Kent from all losses, claims, lawsuits, etc. arising out of damage or injury to property at the project site. Kent sued for: (1) breach of contract; (2) breach of warranty, and (3) contractual indemnity.
American Home agreed to defend Allan under a full reservation of rights. American Home then sued for a declaratory judgment to establish it had no duty to defend or indemnify.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Appreciate The Risks You Are Assuming In Your Contract
February 10, 2020 —
David Adelstein - Florida Construction Legal UpdatesAPPRECIATE THE RISKS YOU ARE ASSUMING IN YOUR CONTRACT. Otherwise, those risks will come back and bite you in the butt. This language is not capitalized for naught. Regardless of the type of contract you are entering into, there are risks you will be assuming. You need to appreciate those risks because there may be insurance you can obtain to cover that risk.
For instance, exculpatory provisions (or get-out-of-jail provisions) in contracts are enforceable if they are unambiguous. “Such provisions are deemed to be unambiguous and enforceable when the language unequivocally demonstrates a clear and understandable intention for the defendant to be relieved from liability such that an ordinary and knowledgeable person will know what he or she is contracting away.” Pillay v. Public Storage, Inc., 44 Fla.L.Weekly D2744c (Fla. 4th DCA 2019).
An example of an exculpatory provision can be found in the public storage rental contract found in Pillay that read:
(1) ALL PERSONAL PROPERTY IS STORED BY OCCUPANT AT OCCUPANT’S SOLE RISK.
(2) Owner and Owner’s agents . . . will not be responsible for, and Tenant releases Owner and Owner’s agents from any responsibility for, any loss, liability, claim, expense, damage to property . . . including without limitation any Loss arising from the active or passive acts, omission or negligence of Owner or Owner’s agents.
Read the court decisionRead the full story...Reprinted courtesy of