No Coverage for Faulty Workmanship Causing Property Damage to Insured's Product Only
October 07, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Nebraska court found there was no coverage for rebar that did not meet specifications and did not cause property damage to other portions of the construction project. Drake-Williams Steel, Inc. v. Cont'l Cas. Co., 2016 Neb. LEXIS 116 (Neb. Aug. 5, 2016).
The general contractor was hired by the city to build an arena. Drake-Williams Steel, Inc. (DWS) was hired to supply rebar for the arena. The rebar was improperly bent when it was fabricated by DWS and did not conform to the terms of the contract. The rebar was incorporated into three components of the arena: the columns, the grade beams, and the pile caps. The pile caps were made of concrete with reinforcing rebar and were installed below ground level on top of the concrete piles that extended to the bedrock. The grade beams were also made of concrete and rebar. The beams formed an oval around the arena and connected different pile caps together and were also installed below ground level. No corrections were made to the grade beams.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Insurer Has Duty to Defend Faulty Workmanship Claim
January 22, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe magistrate judge recommended a determination that the insurer owed a defense to the subcontractor sued for faulty workmanship. Hanover Lloyds Ins Co. v. Donegal Mut. Ins. Co., 2023 U.S. Dist. LEXIS 180877 (W.D. Texas Oct. 5, 2023).
Poe Investments, Ltd. entered into an agreement with Jordan Foster Construction, LLC for construction of an auto sales and service facility ("Facility"). Jordan hired multiple subcontractors, including Texas Electrical Contractors, LLC ("TEC"). Subsequently, Poe sold the Facility to 6330 Montana, LLC ("Montana").
Montana filed suit against Jordan for breach of express warranties, breach of contract, and negligence. Jordon filed a third-party complaint against its subcontractors, including TEC. Jordan alleged that TEC provided "defective and negligent construction work" while carrying out the provision and installation of electrical and fire alarm systems at the Facility.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Emergency Paid Sick Leave and FMLA Leave Updates in Response to COVID-19
April 06, 2020 —
Yvette Davis & Kyle R. DiNicola - Haight Brown & BonesteelThe Families First Coronavirus Response Act (“FFCRA”) was signed by the President on March 18, 2020 and will become effective no later than April 2, 2020. The law contains numerous updates to the country’s employment regulations in response to the Coronavirus pandemic of which employers should be familiar.
Of particular note, the FFCRA makes limited amendments to the Family and Medical Leave Act. Now, pursuant to the Emergency Family and Medical Leave Expansion Act (“EFMLEA”) employees may take up to 12 weeks of family and medical leave after having worked with the employer for 30 calendar days if the employee is unable to work (or telework) due to the employee’s need to care for a son or daughter under 18 years of age due to the child’s school closure or unavailability of a childcare provider due to a public health emergency, i.e., COVID-19. Unlike the FMLA, which does not apply to many small employers, this requirement applies to any employers with 500 or fewer employees. No mileage radius requirement exists under the EFMLEA.
When an employee utilizes leave pursuant to EFMLEA, the first 10 days of that leave may consist of unpaid leave, but the employee may elect to substitute any accrued paid vacation leave, personal leave, or medical or sick leave, including the Emergency Paid Sick Leave provided for by the Act and described below). All subsequent days of leave taken by the employee after the tenth day must be paid by the employer at a rate of not less than two thirds of the employee’s regular rate of pay and the number of hours the employee would otherwise normally be scheduled to work. The cap is $200 per day or $10,000 in the aggregate.
Reprinted courtesy of
Yvette Davis, Haight Brown & Bonesteel and
Kyle R. DiNicola, Haight Brown & Bonesteel
Ms. Davis may be contacted at ydavis@hbblaw.com
Mr. DiNicola may be contacted at kdinicola@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
What Construction Contractors Should Know About the California Government Claims Act
May 28, 2024 —
Garret Murai - California Construction Law BlogIf you work on state or local public works projects in California you should have at least a basic understanding of the Government Claims Act formerly known as the Tort Claims Act (Govt. Code §§ 900 et seq.). In the event of a dispute with a public entity, the Government Claims Act will usually apply, absent contractual provisions providing otherwise (Govt. Code §§930, 930.2) (e.g., in a construction contract), and requires that a “claim” first be presented to a “public entity” before a claimant files a lawsuit against the public entity. Failure to comply with the Government Claims Act can serve as a bar to maintaining a lawsuit against a public entity.
What types of claims does the Government Claims Act apply to?
The Government Claims Act broadly applies to most claims against state and local public entities. This is not limited to construction projects and includes all claims for “money or damage” arising from death, personal injury, breach of contract, and damage to real and personal property, wrongful death, or breach of contract.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Hilti Partners with Canvas, a Construction Robotics Company
April 03, 2023 —
Aarni Heiskanen - AEC BusinessHilti announced a strategic partnership with Canvas, a construction robotics company that has developed a robotic drywalling solution. The partnership allows Canvas to scale globally.
Hilti launched its
Jaibot, the world’s first semi-autonomous ceiling-drilling robot, in 2020. As part of the partnership, Hilti will assume the manufacturing responsibilities for future Canvas systems. They will be based on the Jaibot platform, giving Canvas a reliable and scalable global supply to meet the huge demand for its finishing robots.
The partnering companies share a common vision: that robotic tools will unlock vastly untapped potential and drive a new era of productivity and safety for skilled trade workers.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Former UN General Assembly President Charged in Bribe Scheme
October 21, 2015 —
Patricia Hurtado & Greg Farrell – BloombergA former president of the United Nations General Assembly and a billionaire Macau developer were accused of taking part in a four-year corruption scheme that included bribes to help fund a campaign for the post at the organization in exchange for the promotion of Chinese businesses.
John Ashe, president of the UN General Assembly from September 2013 to September 2014, accepted more than $1 million in payoffs from developer Ng Lap Seng and an associate to help persuade the international body to build a multibillion-dollar conference center in Macau and promote Chinese businesses, including a bank, in Antigua, according to the U.S.
The new charges, announced Tuesday, relate to an earlier case against Ng, 68, who has a personal net worth of about $1.8 billion. He’s been held in a federal jail in Manhattan since he was arrested Sept. 19, accused of bringing $4.5 million into the country and lying about its purpose to U.S. authorities.
Reprinted courtesy of
Patricia Hurtado, Bloomberg and
Greg Farrell, Bloomberg
Read the court decisionRead the full story...Reprinted courtesy of
Florida Appellate Court Holds Four-Year Statute of Limitations Applicable Irrespective of Contractor Licensure
June 22, 2016 —
Clay Whittaker – Florida Construction Law UpdateIn Brock v. Garner Window & Door Sales, Inc.,[1] Florida’s Fifth District Court of Appeal rejected a novel attempt to circumvent Florida’s well-established four-year statute of limitations for all actions founded on the construction of an improvement to real property. Plaintiff filed a lawsuit alleging breach of contract as a result of water intrusion damage following the installation of windows.[2] It was undisputed that Plaintiff commenced the litigation more than four years following the discovery of the allegedly latent defect in the window installation.[3] Plaintiff’s counsel argued that the window contractor could not rely on the four-year statute of limitations because the window subcontractor was not a licensed contractor and, therefore, the five-year statute of limitations for actions founded on written contracts should apply.
Read the court decisionRead the full story...Reprinted courtesy of
Clay Whittaker, Cole, Scott, & Kissane, P.A.Mr. Whittaker may be contacted at
clay.whittaker@csklegal.com
Montana Federal District Court Finds for Insurer in Pollution Coverage Dispute
October 24, 2021 —
Melanie A. McDonald - Saxe Doernberger & VitaApplying Louisiana law, a recent federal court decision exemplifies why policyholders should thoroughly read claims-made policies to understand when notice is due to insurers and truthfully complete policy applications. In Admiral Insurance Company v. Dual Trucking, Inc.,1 the Court determined the insurer, Admiral Insurance Company (“AIC”), owed no duty to defend or indemnify Dual Trucking and Transport, LLC (“DTT”), Dual Trucking of Montana, LLC (“DTM”), and Dual Trucking, Inc. (“DTI”) (collectively, the “Dual Entities”) under two Environmental Impairment Liability Policies (“EIL Policies”) and four Contractor Pollution Liability Policies (“CPL Policies”). The Court justified its decision because the Dual Entities: 1) did not give notice during the 2012-2013 EIL Policy period; 2) had discovered or knew of, but did not disclose, potential pollution conditions before the inception of the 2013-2014 EIL Policy and before the expiration of the extended reporting period of the 2012-2013 EIL Policy; 3) failed to provide AIC with notice during the extended reporting period of the 2013-2014 EIL Policy of claims for which the Dual Entities were seeking coverage; and 4) materially misrepresented known facts on the CPL Policy applications.
I. Factual Background.
The Dual Entities were Louisiana-based companies that provided oilfield equipment rental services. In 2011, the Dual Entities leased land in Montana under three leases, collectively referred to as “the Bainville site.” Shortly afterward, the Dual Entities applied for, and AIC issued, an EIL Policy and two CPL Policies with a policy period of October 1, 2012, to October 1, 2013. AIC renewed all three policies for the October 1, 2013, to October 1, 2014, policy period.
Read the court decisionRead the full story...Reprinted courtesy of
Melanie A. McDonald, Saxe Doernberger & VitaMs. McDonald may be contacted at
MMcDonald@sdvlaw.com