The Hazards of Carrier-Specific Manuscript Language: Ohio Casualty's Off-Premises Property Damage and Contractors' E&O Endorsements
October 05, 2020 —
Theresa A. Guertin & Eric M. Clarkson - Saxe Doernberger & VitaRisk transfer in the construction industry depends heavily on industry-standard insurance language. Insurance provisions in subcontracts typically reference ISO standard insurance terminology or endorsements in order to guarantee (or, at least, attempt to secure) coverage for upstream parties. The contract may require, for example, that a subcontractor maintains general liability insurance on a “current ISO occurrence form,” and name upstream parties as additional insureds, and both parties will have a general understanding of what that entails for purposes of risk transfer.
Problems arise, however, when insurance companies stray from standard language, especially on issues that go to the heart of construction risk transfer. In some instances, provisions that track ISO language may contain subtle changes that seem to meet the contractual insurance requirements. Upon closer scrutiny, it could significantly change how a policy will respond to a given claim. Given the extent of potential liability arising from construction projects, if the insurance programs intended to back up risk transfer and indemnity agreements do not respond as expected, all the potentially liable parties may be left in the lurch.
Reprinted courtesy of
Theresa A. Guertin, Saxe Doernberger & Vita and
Eric M. Clarkson, Saxe Doernberger & Vita
Ms. Guertin may be contacted at tag@sdvlaw.com
Mr. Clarkson may be contacted at emc@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Boston Water Main Break Floods Trench and Kills Two Workers
October 27, 2016 —
Justin Rice – Engineering News-RecordTwo workers died in Boston on Friday afternoon after a water main break flooded the trench where they were working, according to the Boston Fire Dept.
Read the court decisionRead the full story...Reprinted courtesy of
Justin Rice, Engineering News-RecordMr. Rice may be contacted at
enrmidatlanticeditor@enr.com
Building Down in November, Even While Home Sales Rise
January 17, 2013 —
CDJ STAFFThe Chicago Sun-Times reports that construction saw a small decline in November, the first since the spring. Happily, though this was the first dip in eight months, construction spending dropped only 0.3 percent, compared to October. The Sun-Times noted that the level of construction is well below what is considered healthy for the economy, while still being above the low of February 2011.
While fewer homes (and other buildings) were built, sales of new homes were up 4.4 percent in November. Home purchases were at their highest rate in more than two years.
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations to Walnut Creek Partner Bryan Stofferahn and Associate Jeffrey Schilling for Winning a Motion for Summary Judgment on Behalf of Their Client, a Regional Grocery Store!
July 05, 2023 —
Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is excited to share that Partner
Bryan Stofferahn and Associate
Jeffrey Schilling recently won their Motion for Summary Judgment in favor of a prominent Bay Area Grocery Store, and long-time client of the firm.
BWB&O’s Client is a regional Grocery Store with locations throughout California and Nevada. The Client was sued in an action pertaining to a claimed dangerous condition of public property, resulting in a vehicle versus pedestrian collision in an intersection, adjacent to a Northern California store of BWB&O’s Client. The Plaintiff asserted our Client allowed the use of the store’s parking lot as a pickup and drop-off location by agricultural laborers, resulting in increased pedestrian and vehicle traffic, which the surrounding streets were not capable of accommodating thereby creating an allegedly dangerous condition.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Construction Litigation Roundup: “This Is Sufficient for Your Purposes …”
April 08, 2024 —
Daniel Lund III - Lexology… but just barely.
Federal courts are “notice” pleading courts. One source writes: “Notice pleading refers to pleading standards that merely notify the opposing party and court of the general issues in the case. In contrast to fact pleading standards, notice pleading standards do not require pleadings to include hyper-detailed facts in support of each claim.”
Some state courts – including Louisiana – are fact pleading courts. Ordinarily, no one practicing in Louisiana state courts would describe the fact pleading requirements for initiating a lawsuit as mandating “hyper-detailing” of the facts, but … why risk it?
In a construction mechanics lien case – the jurisprudence for which requires that courts strictly construe the related law because liens empower lien holders with rights which are “in derogation” of common property ownership rights – the defendant was successful in having the trial court dismiss a lien suit for failing to affirmatively set forth in the complaint (a “petition” in Louisiana) the date of substantial completion. The lien claimant appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Harmon Hotel Construction Defect Update
July 18, 2011 —
CDJ STAFFCoverage of the ongoing litigation concerning the Harmon Hotel continues to proliferate. Architectural Record and a number of other news outlets continue to provide additional details and coverage of the matter. Chief among the conditions alleged are improperly installed reinforcing steel inside link beams on 15 floors. MGM Claims that the conditions amount to hundreds of millions of dollars in damages, while Perini (the builder) indicated in a July 12th statement that the buildings problems are related to the design, and the they are “fixable.”
There is significant speculation that MGM Resorts International isn’t interested in repairing the hotel due to a glut of hotel rooms attendant to the troubled economy. In a statement Tuesday Perini reportedly stated that “Repairing and opening the Harmon would only create a greater glut of unused hotel rooms for MGM,” “If market conditions were better and MGM found that demand existed for the Harmon hotel rooms, MGM would not be claiming that the Harmon is unstable.”
MGM asserts that Perini failed to ”properly construct” the project. Clark County’s Department of Development Services has reportedly asked MGM to provide a plan to fix the project by August 15th.
The Harmon is part of the $8.5 billion CityCenter project that opened in the fourth quarter of 2009 and is jointly owned by MGM Resorts and Dubai World.
Prior reports indicated that the owner (MGM) had considered razing the entire project. The future of the project remains uncertain.
Read the court decisionRead the full story...Reprinted courtesy of
General Indemnity Agreement Can Come Back to Bite You
October 21, 2019 —
Christopher G. Hill - Construction Law MusingsI talk about payment bonds often here at Construction Law Musings. I talk a bit less about performance bonds and even less about the General Indemnity Agreements (GIA) that are signed by companies and their principals as part of the agreement between a construction company and its bonding company for the provision of these bonds. However, this does not mean that these GIA’s are not important. In fact, these are the agreements that allow a bonding provider to recoup any money paid out pursuant to either a payment or performance bond.
A 2018 case illustrates their importance. In Allegheny Cas. Co. v. River City Roofing, LLC, the Court considered a claim by Allegheny seeking both specific performance of the collateral agreement and reimbursement of certain expenses and investigative costs expended by Allegheny pursuant to its performance bond. Allegheny sought to be reimbursed for certain payments for siding work, investigative costs, and costs spent enforcing the GIA. Allegheny further sought to force the defendants to post sufficient collateral. To do so, Allegheny sued in the Eastern District of Virginia and then moved for summary judgment stating that the GAI uneuivocally required such a result due to the good faith payment for the siding work and the plain language of the GIA.
In response, the Defendants, River City Roofing and its principals that had personally guaranteed the indemnity, argued that the GIA did not apply to the siding work because only the roofing contract was subject to the performance bond and that any bond claims for which collateral was demanded were inchoate and therefore not proper for specific performance.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Baltimore Bridge Collapse Occurred After Ship Lost Power Multiple Times
May 28, 2024 —
Allyson Versprille - BloombergThe container ship that rammed into Baltimore’s Francis Scott Key Bridge in March lost power multiple times on both the day of the fatal accident and the day before, according to a preliminary report.
The Dali, which sails under the flag of Singapore, lost power twice on March 26 before hitting the bridge and causing it to collapse, killing six construction workers who were on the structure at the time. The first blackout was caused when electrical breakers powering most of the vessel’s equipment and lighting unexpectedly tripped, the National Transportation Safety Board said in a report Tuesday.
The crew eventually was able to restore electrical power, but then a second blackout occurred only 0.2 miles from the bridge. They regained power, but the ship lacked the propulsion needed to avoid striking the bridge, safety inspectors found.
Read the court decisionRead the full story...Reprinted courtesy of
Allyson Versprille, Bloomberg