Supreme Court Grants Petition for Review Regarding Necessary Parties in Lien Foreclosure Actions
August 17, 2017 —
Lindsay K. Taft - Ahlers & Cressman PLLCFor several years, the requirements for which parties must be named in a lien foreclosure action when a release of lien bond is in place have been cloudy. RCW 60.04 et seq., the “mechanics’ lien” or “construction lien” statute, provides protection for a party or person who provides labor, materials, or equipment to a construction project. That person or party, if not paid, can file a lien against the construction project property to secure recovery. As the lien impacts the property by “clouding title” and could potentially result in foreclosure of the property, the statute sets forth strict requirements with respect to timing, notice, and parties. For example, the lien must be recorded within 90 days of the person or party’s last day of work or materials or equipment supplied, and the lien claimant must then give a copy of the claim of lien to the owner or reputed owner within 14 days of the lien recording. RCW 60.04.081.
The statute also allows a property owner or other party to “free” the property from the lien prior to the claim being resolved by issuing a release of lien bond. While the claim is still in dispute, the lien then attaches to the bond and not the property. The same rules about foreclosure, however, still apply but not without some confusion.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay K. Taft, Ahlers & Cressman PLLCMs. Taft may be contacted at
ltaft@ac-lawyers.com
Insurer's Motion to Dismiss Business Interruption, COVID-19 Claims Under Pollution Policy Fails
January 11, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer was unsuccessful in seeking to dismiss business interruption claims due to COVID-19 under a pollution policy. New York Botanical Garden v. Allied World Assur., 2021 N.Y. Misc. LEXIS 6012 (N.Y. Sup. Ct. Oct.15, 2021).
The insured was forced to cease operation after executive orders by the governor and mayor were issued in March 2020. The insured also had to reduce its in-person workforce by 100%. The insured's claim for business interruption and contingent business interruption were denied by Allied. The insured sued for a declaratory judgment.
Allied moved to dismiss, arguing that the executive orders were issued for prophylactic reasons in an effort to mitigate the spread of the virus. They were not issued solely to address the presence of COVID-19 at any non-insured owned location, but were issued broadly to limit the risk of spreading the COVID-19 virus. The insured responded that its broader pollution liability policy was not a typical civil authority policy that required the physical loss or damage to property.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
One Colorado Court Allows Negligence Claim by General Contractor Against Subcontractor
December 20, 2012 —
HEATHER ANDERSON , HIGGINS, HOPKINS, MCLAIN & ROSWELLJudge Paul King of the Douglas County District Court recently confirmed that subcontractors in residential construction owe an independent duty, separate and apart from any contractual duties, to act without negligence in the construction of a home in Colorado. See Order, dated September 7, 2010,
Sunoo v. Hickory Homes, Inc. et al., Case No. 2007CV1866; see also
Cosmopolitan Homes, Inc. v. Weller, 663 P.2d 1041 (Colo. 1983);
A.C. Excavating v. Yacht Club II Homeowners Ass’n, Inc., 114 P.3d 862 (Colo. 2005). He also verified that the holding in the
B.R.W. Inc. v. Dufficy & Sons, Inc., 99 P.3d 66 (Colo. 2004)[1] case does not prohibit general contractors, such as Hickory Homes, from enforcing a subcontractor’s independent duty to act without negligence in the construction of a home.
Read the court decisionRead the full story...Reprinted courtesy of
Heather Anderson, Higgins, Hopkins, McLain & Roswell, LLC.Ms. Anderson can be contacted at
anderson@hhmrlaw.com
New Orleans Drainage System Recognized as Historic Civil Engineering Landmark
May 29, 2023 —
The American Society of Civil EngineersNEW ORLEANS, La. – The
American Society of Civil Engineers (ASCE) today recognized the New Orleans Drainage System in New Orleans, Louisiana as a
Historic Civil Engineering Landmark. The project was innovative and largely unprecedented for its time, and the first portions came online in the year 1900. The system now consists of 22 drainage pumping stations and 1,200 miles of network drains, as well as green infrastructure elements to manage stormwater runoff. The infrastructure is largely credited for making the existence of New Orleans possible, and the improved drainage and reduction in standing water contributed to better public health and reduced the number of malaria and typhoid deaths in the early 20th century.
New Orleans' position near the mouth of the Mississippi River made it a vital city for trade and commerce in the U.S. economy since the early 1800s, despite its problematic natural environment. The city was perched along the banks of the Mississippi River and next to Lake Pontchartrain, surrounded by swamps. Improvements to levee systems prevented the city from being inundated with flooding from the river, but rainfall became a pervasive issue as the city's population grew in the 1870s.
The drainage system was first proposed in 1876 to replace primitive "drainage machines," steam-powered paddle wheels that moved water runoff into canals that led to Lake Pontchartrain. The existing system was inefficient and could not handle the frequent, heavy tropical rain New Orleans experiences and could not lift water sufficiently to drain the city. After several proposals, construction on the current drainage system started in 1897, and the first portions of the system came online in 1900. The system drains stormwater through pipes and canals to reach drainage pump stations which expel the water into several bodies of water surrounding the city. Engineers have repeatedly expanded and enlarged the drainage system, including a massive investment in the drainage system authorized by the Southeast Louisiana Urban Flood Control Project and approved by Congress in 1996. The Sewerage and Water Board's green infrastructure plan is a critical partner and complement to the drainage system today.
The New Orleans Drainage System's design has inspired water management system design in communities around America and worldwide. In Southeastern Florida, water management systems using pumps and canals divert excess water away from heavily populated areas during heavy rain, including tropical storms and hurricanes. Engineers in Kolkata, India and Shanghai, China have also used drainage and pumping systems like the ones in New Orleans to assist with water management.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of
Nebraska Joins the Ranks—No CGL Coverage for Faulty Work
September 17, 2014 —
Craig Martin – Construction Contractor AdvisorThe Nebraska Court of Appeals has ruled that a home builder that fails to adequately compact the soil does not have insurance coverage to repair damages to the home caused by the settling soil. In “insurance speak”, there was no occurrence to trigger coverage.
In this case, Cizek Homes, Inc. v Columbia National Insurance Company, a home builder contracted with a buyer to build a house. A lot was selected and the home was built. After the buyer moved in, the house started to settle, causing damage to the house. The buyer told the builder about these problems and the builder agreed to fix the problems. The builder also contacted its insurance company and requested coverage for the buyer’s claim. The insurer rejected the claim, determining that the buyer’s claim was not covered by the builder’s Commercial General Liability (CGL) insurance.
The insurer then filed suit asking the court to interpret the insurance policy and to determine whether the CGL insurance covered the claim. The court looked to the buyer’s allegations that the builder failed to construct the home in accordance with accepted construction and industry standards and that the builder was negligent in designing and constructing the home. The builder admitted that it was obligated to pay for the costs of repairs, but denied that it was negligent in constructing the home.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
The Practical Distinction Between Anticipatory Breach and Repudiation and How to Deal with Both on Construction Projects
June 10, 2024 —
Devon Griger - ConsensusDocsWhen a multilevel construction project is underway and a contractor or subcontractor isn’t performing as expected, it can be difficult to know how to address the low performance without putting the parties’ contract and good working relationship at risk. However, there may come a time when poor performance lapses into a something much worse: an anticipatory breach or repudiation of the subject contract.
Imagine Scenario One: You are a general contractor managing a large-scale construction project and one of your subcontractors is falling behind on their work. The project manager for the subcontractor calls you and says, “Look, I don’t think we’re going to be able to hit our next milestone, and probably not the next one after that.” A conversation like this would generally trigger concern for most general contractors, but it would not necessarily invoke panic. These types of delay conversations are not uncommon on large scale projects.
Compare that example, however, with Scenario Two, where the subcontractor instead says, “We received an offer to work another job for much more money, so we’re leaving the project site today and will not be returning.” This is obviously different (and potentially worse) than Scenario One, and likely cause for much greater concern.
Read the court decisionRead the full story...Reprinted courtesy of
Devon Griger, Jones WalkerMs. Griger may be contacted at
dgriger@joneswalker.com
Additional Insured Prevails on Summary Judgment For Duty to Defend, Indemnify
October 02, 2015 —
Tred R. Eyerly – Insurance Law HawaiiOn summary judgment, the insured general contractor prevailed not only on the duty to defend, but also the duty to indemnify. Wausau Underwriters Ins. Co. v. Old Republic Gen. Ins. Co., 2015 U.S. Dist. LEXIS 103954 (S.D. N. Y. Aug. 7, 2015).
170 Broadway entered into a construction management agreement with McGowan Builders Inc. to serve as its construction manager for a hotel being built in Manhattan. Under the agreement, McGowan obtained a general liability policy from Old Republic naming 170 Broadway as an additional insured. 170 Broadway also secured its own policy from Wausau.
Adam Burawski, an employee of a security company, came to the 170 Broadway site to meet with McGowan about provided security services for the project. Before the meeting, Burawski tripped and fell, sustaining a serious injury.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Guilty Pleas Draw Renewed Interest In Nevada’s Construction Defect Laws
December 09, 2011 —
CDJ STAFFA report this week by David McGrath Schwarz of the Las Vegas Sun suggests that Nevada’s construction defect laws will be a point of much contention in upcoming legislative sessions. The report cites renewed interest in the state’s construction defect laws due to ongoing federal investigations of construction defect attorney Nancy Quon and construction company owner Leon Benzer. Guilty pleas have been entered by at least ten individuals including an attorney, property managers, straw purchasers, and former HOA board members.
The article suggests that Nevada’s Chapter 40 laws are easily manipulated to the detriment of Nevada’s homebuilding industry. Construction industry lobbyists have tried unsuccessfully to change the laws in past legislative sessions.
The Sun’s article speculates that the building industry might be able to gain legislative concessions due to the volume of guilty pleas and what it refers to as examples of Chapter 40 abuses. ”With federal authorities collecting guilty pleas, the construction industry has prime examples of the system being abused, and how lucrative it can be for attorneys.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of